Saturday, 28 September 2024

Abha Khanna (IPE) Vs. KVG Realtech Pvt. Ltd. - It is upto the allottee to proceed either under Section 18(1) or under proviso to Section 18(1).

 REAT UP (2024.09.14) in Abha Khanna (IPE) Vs. KVG Realtech Pvt. Ltd. [(2024) ibclaw.in 133 REAT, Appeal No. 243/2020] held that; 

  • That as per the provisions of the U.P. Apartments Act, 2010 read with the provisions of Act, 2016  a  Promoter is required to offer legal and habitable possession to the allottees only after obtaining OC/CC and ask for clearing dues by raising final demand.

  • The failure of the Developer to comply with the contractual obligation to provide the flat within the contractually stipulated period, would amount to a deficiency of service. Given the one-sided nature of the Apartment Buyer’s Agreement, the consumer fora had the jurisdiction to award just and reasonable compensation as an incident of the power to direct removal of deficiency in service.

  • That the right so given to the allottee is unqualified and if availed, the money deposited by the allottee has to be refunded with interest at such rate as may be prescribed and the

  • Proviso to Section 18(1) contemplates a situation where the allottee does not intend to withdraw from the Project. In that case he is entitled to and must be paid interest for every month of delay till the handing over of the possession.

  • It is upto the allottee to proceed either under Section 18(1) or under proviso to Section 18(1).

  • If an allottee chooses to remain in the project and in case the allottee seeks refund then he is entitled for interest on the deposited amount and/or compensation in accordance with the provisions of the Act 2016, which in our considered view will be in accordance with the principles of equity as well.


Excerpts of the Order;

# 1. By means of this appeal, Abha Khanna (hereinafter referred to as appellant) has challenged the order dated 10.02.2020 (hereinafter referred to as “impugned order”) passed by the Regulatory Authority in complaint No. LKO162/05/0188/2019 (Abha Khanna Vs. M/s KVG Realtech Private Limited) whereby the Regulatory Authority has passed the following directions:- (a) Respondent (M/s KVG Realtech Private Limited) is directed to obtain OC/CC and ensure possession of the unit to the complainant (appellant herein) within 45 days after execution of registry and receiving stamp fee and balance of payment from the complainant. (b) Pay delay interest @ MCLR+1% of SBI for the period from 30.07.2018 (promised date of possession as per agreement) till date of offering possession i.e. 20.09.2019. The amount of delay interest will be adjusted in the last payment due and if the amount of delay interest is more than the payable amount, the same will be returned/remitted to the complainant. 


# 2. The brief facts as culled out from the memo of appeal are that:- 

2.1 The appellant Abha Khanna booked a Shop Space No. 39 in Millennium Square, on 1st Floor admeasuring 14.11 sq. mt. in the commercial project launched by the respondent known as “Millennium Square” situated at Commercial-1, International Bay-II, Sushant Golf City, Sultanpur Road, Lucknow and the same was allotted by the respondent to the appellant vide allotment letter dated 28.04.2012. A Shop Buyer’s Agreement dated 13.09.2012 was signed between the parties. The cost of the unit as mentioned in the Shop Buyer’s Agreement was Rs 7,59,100/-. As per clause 16 of the said agreement, the respondent had to handover the physical possession of the shop within 36 months from the date of agreement i.e. on or before 13.09.2015. 

2.2 As per customer ledger, the total amount deposited by the appellant was Rs 7,59,508.71 till 15.01.2019 while the net value of the shop was increased to 8,50,192/- including the service tax and GST on the total cost of the shop without prior information to the appellant and this occurred due to delay in handing over of the shop by the respondent. 

2.3 At the time of booking, the respondent had promised that they had received all the sanctions/NOCs and required permissions from all the concerned authorities and the possession would be given as per the time period, mentioned in the agreement whereas later on the appellant received a letter from the respondent averring that they have got the sanction of the map of the building (project) “Millennium Square” from the Lucknow Development Authority via Permit No.-38580 dated 30.07.2015. Thus the respondent has violated Section 11 (3) of the Act 2016 for concealing the facts. 

2.4 The appellant had received offer of possession letter dated 20.09.2019 averring asking to clear the dues and complete necessary formalities for executing sale deed of the said unit on or before 20.10.2019. At the time of offering possession, the respondent had not received the OC/CC. There was a delay of around 4 years in giving the possession letter that too without obtaining the OC/CC. The appellant has further stated that offer of possession issued to the appellant was for the allottees of ‘Felix Square, Sushant Golf City, Lucknow whereas the appellant has booked the shop in the project named “Millennium Square”. In this offer of possession letter, the respondent has informed the appellant that the internal and external development in the “Felix Square Sushant Golf City Lucknow” will not be carried out by the third party. 

2.5 After coming of RERA Act into effect in the year 2016, the respondent fraudulently got itself registered with RERA on 04.08.2017 in the category of on-going project which mandates promoter to disclose all the information about the project but the respondent did not inform the Authority about the Shop Buyer’s Agreement. 

2.6 The respondent had not only misrepresented the appellant but also misguided the Authority. According to the respondent they have received the permit from Lucknow Development Authority on 30.07.2015 whereas as per the customer ledger they have already started construction which shows that in May 2015, they were on the start of 4th floor slab. 

2.7 The appellant seeks the compensation of financial loss, delay penalty, mental agony and discomfort caused due to the respondent. The appellant also demanded for the penalty for delay in handing over possession as per Section 18 read with Section 2 (za) of the Real Estate (Regulation and Development) Act, 2016. 

2.8 As per section 12 of Real Estate (Regulation and Development) Act, 2016, where any person makes an advance or a deposit on the wrong information contained in the notice, the advertisement or the prospectus and suffers a loss, harm or damage by reason of any incorrect information, he shall be compensated for the damages by the promoter. The appellant has booked a shop under the project which should have been handed over to the allottee within 36 months but the respondent has failed to do so, even though in the agreement they have mentioned that their township has been approved by the Lucknow Development Authority which is wrong and the appellant was misrepresented. Therefore, the appellant is liable to be compensated under the provisions of the section 12 of the Real Estate (Regulation and Development) Act, 2016. 

2.9 Moreover, the respondent has been enjoying the money paid to them for the last 8 years and they are liable to compensate to the complainant suitably for the mental torture, agony, business loss and sufferings because of them. 


# 3. Having been aggrieved from the impugned order, the appellant has approached this Tribunal on the following grounds:- BECAUSE, the Regulatory Authority has passed the impugned order dated 10.02.2020 without of application of mind, without appreciating the facts placed before them and without going through the records.

(1). BECAUSE the Learned RERA Authority has failed to consider the fact that the Appellant has prayed in her complaint only for immediate possession of the shop along with the delay interest for the period of 4 years i.e. from the date of possession as per the agreement i.e. 13.09.2015 till actual handing of the physical possession of the shop. 

(2). BECAUSE the learned authority erred in travelling beyond the scope of complaint preferred by the appellant. 

(3). BECAUSE the learned authority failed to appreciate that the Appellant was entitled for interest as may be prescribed in this behalf under the provisions of the Act of 2016 as the Respondent had delayed in delivering the possession of the shop as per the agreement as well as the possession of the shop was offered without obtaining the occupancy/completion certificate. 

(4). BECAUSE the learned authority has passed the impugned order for refund only between 30.07.2018 to 20.09.2019 whereas the Respondent should be liable for compensation from 13.09.2015(date as per agreement) till actual possession of the shop. 

(5). BECAUSE the Learned Authority has done injustice with the Appellant which is illegal in the eyes of law by overlooking the agreement that was signed between the parties and according to which the Respondent has received the sanction and has promised to handover the possession within 3 years i.e. 30.07.2015. 

(6). BECAUSE the impugned judgment and order passed by Learned Authority is cryptic, illegal and manifestly erroneous and is liable to be set aside. 

(7). BECAUSE Learned Authority has committed manifest error of law in not granting the reliefs as sought by the Appellant. 

(8). BECAUSE the Learned RERA Authority has failed to consider the fact that the Appellant has asked for physical possession and compensation for delay along with the financial loss suffered because of the Respondent. 

(9). BECAUSE the Learned RERA Authority has failed to consider the fact that as per Section 18 of Real Estate (Regulation and Development) Act 2016, the promoter is liable to pay for the delay made in handing over the possession as per the agreement. 

(10). BECAUSE it was submitted by the Appellant that the respondent had approached the Learned RERA Authority not with clean hands by not disclosing true and correct facts and by misrepresenting material facts. 

(11). BECAUSE it was submitted by the Appellant that the respondent has not made an offer of possession before filling the complaint and when the offer was made it was not with the occupancy certificate or occupancy certificate and thus there was a delay in handing over the physical possession of the shop. 

(12). BECAUSE it was submitted by the Appellant that the Respondent after many reminders and requests was not able to provide the possession on time and thus liable for losses which the Appellant has suffered. 

(13). BECAUSE it was submitted by the Appellant that the Respondent has cheated and misrepresented not only the appellant but also the Hon'ble Authority by registering its project under the RERA and hiding the fact that the Shop Buyer Agreement has been executed in the year 2012 while the Respondent has shown the original start date under the RERA as 21.01.2013. 

(14). BECAUSE impugned order passed by the Learned RERA Authority is bad in law and was passed without following procedure of the Act therefore impugned order granting the delay penalty only from 30.07.2018 to 20.09.2019 is liable to be set-aside by this Hon'ble Tribunal in the interest of justice and appeal filed by the appellant is liable to be allowed. The Respondent is liable for delay penalty from 30.07.2015 till the actual possession along with the execution of sale deed as per section 17 of the Real Estate (Regulation & Development) Act, 2016. 

(15). BECAUSE the Learned RERA Authority has failed to consider the fact that there is legitimate grievance that the Appellant can have against the respondent which comes under the ambit of the Real Estate (Regulation and Development) Act, 2016 and prevailing UPRERA Rules viz. 'The Uttar Pradesh Real Estate (Regulation and Development) Rules 2016. 


# 4. The appellant has sought the following reliefs:- 

  • (i) In the interest of justice, this Hon'ble Tribunal may be pleased to set aside the impugned Order of granting the delay penalty from 30.07.2018 to 20.09.2019 at the rate of MCLR+1%. 

  • (ii) In the Interest of Justice, this Hon'ble Tribunal may order or direct the Respondent to pay the delay interest at the rate of 18% p.a as would have been charged by the respondent in case of delay from 30.07.2015(date as per agreement) till actual handing of the possession. 

  • (iii) Issue an order or direction to the Respondent to hand over the immediate possession of the shop along with the execution of the sale deed as per section 17 of Real Estate (Regulation & Development) Act, 2016. 

  • (iv) Issue an order or direction to the respondent to compensate the appellant, as per provisions under RERA Act, for the harassment, mental agony and financial loss suffered by the Complainant due to delay in possession of commercial shop by the Respondent. 


# 5. Learned counsel for the respondent filed its objections denying the averments made by the applicant in the appeal and narrated the relevant facts involved in the present appeal as under:- 

5.1 In clause 16 of the Builder-Buyer Agreement it is clearly mentioned “that the developer shall make endeavour to offer possession of complex within 36 months from the date of sanction of building plans by the authorities subject to force majeure circumstances and on receipt of complete payment”. Here the appellant is trying to mislead the Tribunal by falsely mentioning the stipulated time period of 36 months from the date of agreement. Whereas, as per clause 16 of the agreement, it is clear that the possession will be offered by the respondent within 36 months from the date of sanction of building plans by the authorities. The sanction was given on 30.07.2015 and thus the project was to be completed on or before 30.07.2018. The possession was offered on 30.09.2019. Hence the delay in offering possession is of around one year and two months which has also been held by the Regulatory Authority in their impugned order dated 10.02.2020. The claim of the appellant that the delay is of more than four years is absolutely frivolous and done to harass and arm twist the respondent for monetary gains and must be dismissed with cost in the interest of justice. 

5.2 The appellant has defaulted in payment and even after many reminders, the appellant paid no attention whereas in clause of 10 of BBA, it is clearly mentioned that timely payment as and when demanded by the respondent is must, therefore, the appellant has clearly violated the terms of agreement. The default in making payment by the allottee is a compensatory in nature, under section 19 (6) of the Act 2016 wherein it is provided that allottee is under obligation to make payment as per terms and conditions of the agreement, further Section 19 (7) of the Act 2016 envisages levying of the interest for the period of delay in making payment to the builder. In the given case the appellant at one side has failed to fulfil its obligations of making payment in time and on the other side the appellant is misusing the process of law in order to arm twist the respondent for vested interests. 

5.3 RERA is not retrospective in nature as alleged by the appellant in her averments. The booking was made in 2012 much before the commencement of U.P. Real Estate Regulatory Authority and in “Neelkamal Realtors Suburban Private Limited Vs Union of India” it has been specifically held that the provisions of RERA are not retrospective in nature. 

5.4 The RERA came into force with effect from 01.05.2017 and thereafter on 04.08.2017 the project got registered under it. The respondent has produced all mandatory documents to get the project registered with RERA and the averments of the appellant in this respect are false and fabricated. 

5.5 The delay in completion of the project occurred due to FSI signed with Ansal API where it was duty of Ansal to get the land use converted by the competent authority. Therefore, it was not in the hands of the respondent. Further the force majeure circumstances caused delay and were not in the control of the respondent. 

5.6 The respondent has submitted that the BBA was signed with open eyes, by the own sweet will of the appellant and without any pressure from the respondent, hence wrongful quote of malafide intention of respondent and allegation of providing wrong information wilfully, are deliberately misleading and false, therefore, highly objected. 


# 6. The appellant in her replication/rejoinder has denied the averments made by the respondent in his objections and reiterated/repeated her averments made in the memo of appeal. 


# 7. Heard Sri Abhishek Khare, learned counsel for the appellant and Sri Saurabh Mishra, learned counsel for the respondent. 


# 8. The appellant is only aggrieved by direction no. 2 of the impugned order dated 10.02.2020 passed by the Regulatory Authority whereby delay interest has been granted from 30.07.2018 (date of possession as per agreement) to 20.09.2019 (date of offer of possession) at the rate of MCLR+1% whereas, according to her, she is entitled to delay interest from 30.07.2015 till actual handing over of the possession of the unit, with interest at the rate of 18% per annum. 


# 9. In order to examine the issue involved in the instant appeal and on the basis of pleadings on record as well as submissions of both sides, we deem it proper to frame the following questions:-- 

  • (1) Whether it is necessary and mandatory for the Promoter to have first Completion Certificate (C.C.) and Occupation Certificate (O.C.) under the provisions of the Act of 2016 and Rules of 2016, read with the U.P. Apartments (Promotion of Construction, Ownership and Maintenance) Act 2010 before offering possession as well as asking the allottee to settle the account and satisfy the final demand

  • (2) Whether the appellant is entitled for interest for the delay in completion of the Project under the scheme of Act, 2016 and if yes, what rate of interest is required to be paid by the Promoter to the allottee? 


# 10. Issue No. (1) is as to whether offer of possession can be given by a promoter without completion and occupation certificate or is it necessary and mandatory to obtain the same before offering possession and asking the allottee to settle the account and satisfy the final demand, under the scheme of Act & Rules 2016, read with U.P. Apartments Act 2010. 

10.1 In order to appreciate the issue, we examine Section 2(q) and Section 2(zf) of the Act of 2016, which defines Completion & Occupancy Certificate, the same are extracted as follows:- 

  • “Section 2:- Definitions - In this Act, unless the context otherwise requires,- 

  • XXXX 

  • “Section 2 (q) "completion certificate" means the completion certificate, or such other certificate, by whatever name called, issued by the competent authority certifying that the real estate project has been developed according to the sanctioned plan, layout plan and specifications, as approved by the competent authority under the local laws;” 

  • “Section 2 (zf) "occupancy certificate" means the occupancy certificate, or such other certificate by whatever name called, issued by the competent authority permitting occupation of any building, as provided under local laws, which has provision for civic infrastructure such as water, sanitation and electricity;” 

10.2 On examination of the provisions of Section 2 (q) and Section 2(zf), we find that completion certificate is basically a certificate issued by the competent authority certifying that the Real Estate Project has been developed according to the sanctioned plan, lay out plan and specifications, as approved by the competent authority under the local laws. On the other hand, the occupancy certificate is issued by the competent authority permitting occupation of any building, as provided under local laws, which has provision for civic infrastructure such as water, sanitation and electricity etc. 

10.3 Similarly, Section 4(5) of the U.P. Apartments Act, 2010 prescribes for Completion Certificate, which reads as follows:- 

  • “Section 4(5) of the U.P. Apartments Act, 2010:-An apartment may be transferred by the promoter to any person only after obtaining the completion certificate from the prescribed sanctioning authority concerned as per building bye-laws. The completion certificate shall be obtained by promoter from prescribed authority [within the period specified for completion of the project in the development permit or the building permit as the case may be] 

  • Provided that if the construction work is not completed within the stipulated period, with the permission of the prescribed authority; 

  • Provided further that if the completion certificate is not issued by the prescribed sanctioning authority within three months of submission of the application by the promoter complete with all certificates and other documents required, the same shall be deemed to have been issued after the expiry of three months. 

  • Explanation: For the purposes of this sub-section "completion" means the completion of the construction works of a building as a whole or the completion of an independent block of such building, as the case may be.” 

10.4 Section 4(5) of the U.P. Apartments Act 2010 clearly lays down that an apartment may be transferred by the Promoter to any person (allottee) only after obtaining the C.C. from the prescribed sanctioning authority concerned as per building by-laws. The C.C. is required to be obtained by the Promoter, meaning thereby that Allottee has no role to play in obtaining C.C. from the prescribed authority. A Promoter is required to first obtain C.C./O.C. from the prescribed authority, only thereafter register conveyance deed of the real estate in favour of the Allottee(s) and a legal & habitable possession can be offered to the Allottees. 

10.5 The issue of offering handing over possession prior to obtaining occupancy certificate was also examined by the Hon’ble Supreme Court in Civil Appeal Nos. 1232 and 1443-1444 of 2019 R.V. Prasannakumaar and ors. Vs. Mantri Castles Pvt. Ltd. and ors.decided on 11.02.2019 wherein it has been observed that possession cannot be handed over prior to obtaining occupancy certificate. 

10.6 In view of the aforesaid analysis, we are of the considered view that as per the provisions of the U.P. Apartments Act, 2010 read with the provisions of Act, 2016 a Promoter is required to offer legal and habitable possession to the allottees only after obtaining OC/CC and ask for clearing dues by raising final demand. In the instant case the offer of possession was given by the respondent to the appellant on 20.09.2019 without obtaining OC/CC. Issue no. (1) is answered accordingly. 


# 11. Question No (2) relates to the entitlement of the appellant for the interest on account of delay in completion of the Project under the scheme of Act, 2016 and the rate of interest required to be paid by the Promoter to the allottee for delay. 

11.1 Section 18 (1) of the Act clearly provides that if an Allottee wishes to withdraw from the Project on the ground that the Promoter is unable to give possession in accordance with the Agreement for Sale within the date specified therein, then the Promoter shall return the amount received from the Allottee in respect of that property with interest and compensation, on the Allottees’ demand. The power of exercising the option of either staying in the Project or for withdrawing from it lies only with the Allottees under the provisions of Section 18 (1) of the Act. Further, Section 19(4) of the Act 2016 gives right to the allottees to claim refund along with interest and/or compensation in case the Promoter fails to give possession of the apartment in accordance with the terms and conditions of Agreement for sale. 

11.2 The Hon’ble Bombay High Court in the case of Neelkamal Realtors Suburban Pvt. Ltd. And others Vs. Union of India (2018)1 Bom R 558 observed as under:-- 

  • "Section 18(1)(b) lays down that if the promoter fails to complete or is unable to give possession of an apartment due to discontinuance of his business as a developer on account of suspension or revocation of the registration under the Act or for any other reason, he is liable on demand to the allottees, in case the allottee wishes to withdraw from the project, without prejudice in this behalf including compensation. If the allottee does not intend to withdraw from the project he shall be paid by the promoter interest for every month's delay till handing over of the possession. The requirement to pay interest is not a penalty as the payment of interest is compensatory in nature in the light of the delay suffered by the allottee who has paid for his apartment but has not received possession of it. The obligation imposed on the promoter to pay interest till such time as the apartment is handed over to him is not unreasonable. The interest is merely compensation for use of money"

11.3 Subsequently, in Wg. Cdr. Arifur Rahman Khan & Others Vs. DLF Southern Homes Pvt. Ltd., reported in (2020) SCC Online 667 affirming the view taken in the Judgment in Pioneer’s case (Supra) the Hon’ble Supreme Court held that the term of the agreement authored by the Developer does not maintain a level platform between the Developer and the flat purchaser. The stringent terms imposed on the flat purchaser are not in consonance with the obligation of the Developer to meet the timelines for construction and handing over possession, and do not reflect an even bargain. The failure of the Developer to comply with the contractual obligation to provide the flat within the contractually stipulated period, would amount to a deficiency of service. Given the one-sided nature of the Apartment Buyer’s Agreement, the consumer fora had the jurisdiction to award just and reasonable compensation as an incident of the power to direct removal of deficiency in service. 

11.4 The Hon’ble Supreme Court, while dealing with the provisions of Section 18 of the Act, 2016, in the case of M/S Imperia Structures Ltd. Vs. Anil Patni and another, Civil Appeal Nos. 3581-3590 of 2020, decided on 02.11.2020, vide para 23, was pleased to observe that the right so given to the allottee is unqualified and if availed, the money deposited by the allottee has to be refunded with interest at such rate as may be prescribed and the proviso to Section 18(1) contemplates a situation where the allottee does not intend to withdraw from the Project. In that case he is entitled to and must be paid interest for every month of delay till the handing over of the possession. It is upto the allottee to proceed either under Section 18(1) or under proviso to Section 18(1). 

11.5 U.P. Government framed "Uttar Pradesh Real Estate (Regulation and Development) (Agreement for Sale/Lease) Rules, 2018" (hereinafter referred to as Rules, 2018), wherein under Rule 9.2(ii) and 9.3(i), the rate of interest payable by the promoter or by the allottee respectively are defined in case of default by either of the party. These Rules are extracted below :- 

  • Rule 9.2(ii) The Allottee shall have the option of terminating the Agreement in which case the Promoter shall be liable to refund the entire money paid by the Allottee under any head whatsoever towards the purchase of the apartment, along with interest at the rate equal to MCLR (Marginal Cost of Lending Rate) on home loan of State Bank of India + 1% unless provided otherwise under the Rules, within forty-five days of receiving the termination notice: 

  • Provided that where an Allottee does not intend to withdraw from the Project or terminate the Agreement, he shall be paid, by the Promoter, interest at the rate prescribed in the Rules, for every month of delay till the handing over of the possession of the Apartment/Plot, which shall be paid by the Promoter to the Allottee within forty-five days of it becoming due. 

  • Rule 9.3 The Allottee shall be considered under a condition of Default, on the occurrence of the following events : 

  • Rule 9.3(i) In case the Allottee fails to make payments for 2(two) consecutive demands made by the Promoter as per the Payment Plan annexed hereto, despite having been issued notice in that regard the Allottee shall be liable to pay interest to the promoter on the unpaid amount at the rate equal to MCLR (Marginal Cost of Lending Rate) on home loan of State Bank of India + 1% unless provided otherwise under the Rules. The Promoter must not be in default to take this benefit. 

11.6 On examination, we find that these Rules-2018 notified by U.P. Government are in consonance with the definition of interest as provided in Section 2(za) of the Act, in as much as that the interest chargeable from the allottee by the promoter, in case of default in payment as per demand, is equal to the rate of interest which the promoter is liable to pay to the allottee, in case of default/delayed possession on the part of promoter. 

11.7 This Tribunal came across various orders of the Regulatory Authority wherein it had granted interest at the rate of MCLR+1% per annum in case of delayed projects and had an occasion to examine the issue of rate of interest at MCLR+1% awarded by the Regulatory Authority in Appeal No. 295 of 2019 (U.P. Avas Vikas Parishad Vs. Devesh Kumar Tiwari) decided on 20.02.2020 and held as under:-- 

  • “We feel that this imbalance is on account of the fact that the buyer/allottee has much less bargaining power as compared to the seller in the real estate market and therefore the buyers/allottees have no choice but to sign on such "dotted line", "one sided, unfair and unreasonable" terms and conditions/Agreements. We are therefore of the view that the rate of MCLR +1% , as prescribed by the Government and as being ordered by the Regulatory Authority, be payable from the date of deposit of money in case the allottee wishes to withdraw from the project; and from the specified/expected date of possession in case the allottee wishes to stay in the project, would balance the equities and are just and fair and will fall within the term "interest at such rate as may be prescribed" as used in Sections 12, 18 & 19.........” 

It is our considered view that drawing light from the Rules of 2018, and the fact that often an allottee/buyer has to supplement his savings by taking loan at the MCLR percent interest (compound), the simple rate of interest at MCLR+1 percent balances the equities and is in line with the word and spirit of the Act and can be taken as “interest at such rate as may be prescribed” as mentioned in Sections 12,18 and 19 of the Act, till the rate of interest for the purpose is notified by the State Government. 

11.8 It is important to mention herein that the Hon’ble Supreme Court in Civil Appeal No. 4910-4941/2019 DLF Homes Panchkula Pvt. Ltd. Versus D. S. Dhanda etc. etc. while examining the issue of compensation, was pleased to observe as under;- 

  • “If compensation comprises of two parts, (i) by way of interest on the deposited amount from the assured date (milestone date) of completing construction and handling over possession to the actual date of handling over possession, and, (ii) lumpsum amount, we find nothing wrong in it. We do not agree with the builder co.’s contentions that interest on the deposited amount should not be provided since it is not a case of refund but a case of delay in possession. The interest on the deposited amount has to be viewed in the light of the purpose for which it is intended. It is but a way of computing compensation for delay in possession that is commensurate with the amount deposited by the complainant, and here it has been computed after adopting a milestone date as per the builder co.’s own (unfair and deceptive) letter of 05.06.2013. There can be and is no question of not agreeing to an endorsing the award of interest from the said milestone date. Here we may however add that the rate of interest also cannot be arbitrary or whimsical, some reasonable and acceptable rationale has to be evident, subjectivity has to be minimized, a logical correlation has to be established. Albeit detailed arithmetic or algebra is not required. Logical (to the extent feasible) objective parameters should be adopted. Rounding off simplification etc. to make the computation doable could be adopted. We feel it appropriate that, considering that the subject units in question are dwelling units, in a residential housing project, the rate of interest for house building loan for the corresponding period in a scheduled nationalized bank (take, State Bank of India) would be appropriate and logical, and , if ‘floating’/ varying/different rates of interest were/ are prescribed, the higher rate of interest should be taken for this instant computation.” 

11.9 Further, an allottee deposits amount under the hope and trust that he/she will get the flat within the time schedule advertised at the initial stage. There may be certain cases where allottees might be residing in rented houses and they might have managed their financial position in such a manner that after deposit of amount, they will get flats of their own and thereafter they will be free from payment of rent as then they will shift from rented houses to allotted flats but on account of inordinate delay in delivery of possession of allotted flats, their financial calculations and legitimate expectations stand frustrated causing various types of financial losses to them. On the other hand once the promoter/builder made offers and same are accepted by the allottees with legitimate expectation, the obligation cast upon the promoter/builder is to complete the same within the time schedule mentioned in the offer and if they fail to discharge the same the affected allottees are entitled to the interest and/or compensation for delayed delivery of possession, as the allottees have parted with money which was earning interest. If an allottee chooses to remain in the project and in case the allottee seeks refund then he is entitled for interest on the deposited amount and/or compensation in accordance with the provisions of the Act 2016, which in our considered view will be in accordance with the principles of equity as well. 

11.10 On the basis of aforesaid analysis we are of the considered view that the appellant is entitled to delay interest at the rate of MCLR+1% and not 18% as prayed for by her. Issue no. (2) is answered accordingly. 


# 12. The appellant has sought delay interest from 30.07.2015. According to the appellant, as per Clause 16 of the Shop Buyer’s Agreement dated 13.09.2012, the respondent had to hand over physical possession of the shop within 36 months from the date of agreement i.e. on or before 13.09.2015. Clause 16 of the said agreement reads as under:-- 

  • “The developer shall make endeavour to offer possession of complex within 36 months from the date of sanction of building plans by the authorities subject to force majeure circumstances and receipt of complete payment.” The said clause 16 makes it crystal clear the respondent had to hand over possession of the shop within 36 months from the date of sanction of building plans by the authorities and not from the date of agreement as claimed by the appellant. The building plan was sanctioned by the authorities on 30.07.2015 and thus the possession of the shop in question was to be handed over by the respondent to the appellant by 30.07.2018, as rightly held by the Regulatory Authority. Thus the appellant is entitled to delay interest from 30.07.2018 till the date of actual possession along with OC/CC. 


# 13. In view of the aforesaid analysis the appeal is partly allowed. The direction no. 2 of the impugned order dated 10.02.2020 is modified to the extent that the respondent is directed to pay delay interest @ MCLR+1% of SBI for the period from 30.07.2018 till the date of delivery of actual possession along with OC/CC. The amount of delay interest will be adjusted towards final payment and if the amount of interest exceeds the amount due, the excess amount shall be returned to the complainant/appellant. 


# 14. No order as to costs. 

-----------------------------------------------


Wednesday, 25 September 2024

Malkeet Singh G. Matharu HUF Vs. Mount Mary Builders and Anr. - The provisions of Section 18 of RERA can equally be invoked in terms of oral or formal agreement executed by the Promoter/ Developer such as booking application form/ formal letter/ allotment letter/ letter of intent/ correspondence, etc. capable of being construed as an agreement,

 REAT Mumbai (2024.09.09) in Malkeet Singh G. Matharu HUF Vs. Mount Mary Builders and Anr. [(2024) ibclaw.in 136 REAT, Appeal No. AT00600000063797/22 in Complaint No. CC006000000196424] held that; 

  • When a claim is raised in respect of a real estate project by a flat purchaser, all promoters become jointly liable qua that flat purchasers, irrespective of whether there is privity of contract with each of the promoters or not. This is the scheme of RERA and mere absence of privity of contract with a particular promoter does not relieve such promoter in respect of the liabilities under RERA".

  • In the absence of formal agreement executed by the parties, the date of possession can be deciphered from any documents such as allotment letter, brochure, pamphlet, email communication, etc

  • That if the date of possession is not mentioned in the agreement, the Promoter is expected to handover the possession of the unit within a reasonable time and the period of three years held to be reasonable time.

  • We are of the view that mere non-execution of the agreement for sale, Allottees are not precluded from invoking Section 18 of RERA. The provisions of Section 18 of RERA can equally be invoked in terms of oral or formal agreement executed by the Promoter/ Developer such as booking application form/ formal letter/ allotment letter/ letter of intent/ correspondence, etc. capable of being construed as an agreement,

  • However, since the Appellant has not sought relief of compensation in the complaints, the same cannot be granted in the Appeals


Excerpts of the Order;

1). The captioned Appeals arise from common Order dated 22.02.2022 passed by learned Member I, MahaRERA (for short "the Authority') in Complaint Nos.CC006000000t96427 and CC0060000000L96424 whereby the Authority directed Respondent No.1 to execute and register agreements for sale with Appellant as per provisions of Section 13 of RERA Act, 2016 (for short "RERA') within a period of 30 days, failing which the monies paid by the Appellant to be refunded without interest within the period of next three months. 


2).  Respondent No.1 is a sole proprietorship concern and is involved in real estate business and is the promoter of a project named "Green World" situated at Airoli, district Thane (for short "the said Project), Respondent No.2 is incorporated under the provisions of the Companies Act, 1956 and is involved in business of real estate and Co-Promoter of the said project vide a joint venture agreement dated 15.04.2010 registered between them at the Sub-Registrar of Assurances at Thane. By the joint venture agreement dated 15.04.2010 executed between the Respondents, Respondent No.1 has assigned, transferred and assured to Respondent No,2, the development rights in respect of the said project. The Respondents have jointly launched the said project. 


3). For the sake of convenience, parties to the Appeals hereinafter will be referred to as "Appellant/Complainant" and "Respondents/Promoters" respectively. Since the captioned Appeals arise out of the same Order having identical facts, relief sought and law points involved and parties are the same, therefore, these Appeals are disposed of by this common judgment. 


4).  The brief facts gathered from the pleadings, documents on record, and impugned Order are that flats bearing no,1301 and 1302 admeasuring 913 sq. ft, carpet area each on 13th floor in F Wing of the said project have been booked by Mr. Malkeet Slngh Gulzar Singh Matharu for a total consideration of Rs.90,51,625 leach. At the time of booking, an amount of Rs.5,00,000/- each was paid to the Promoter/ Respondent No.1. Subsequently, the Promoter/ Respondent No.1 issued allotment letters dated 22.09.2014 and 23.09.2014 for the respective flats. At the time of booking, Promoter/ Respondents No 1 promised possession of the said flats in 2016. The Promoter/ Respondent No.1 has received total amount of Rs.65,20,791/- and Rs.64,05,887/- for the respective flats as per the demand letters raised by Respondent No.1. Mr. Malkeet Singh Gulzar Singh Matharu expired on 25.10.2016 and Karta rights automatically devolved upon his son Mr. Kunvarjit Singh Malkeet Singh Matharu, who is the Appellant in both the Appeals. 


5). The said project came to be registered with MahaRERA on 06.08.2017 with proposed date of completion of the said project as 31.12.2019. The Appellant/complainant by an email dated 05.10,2019 asked the Respondents/ Promoters for status of balance payment and Information on allotment of the said flats in the name of the Appellant. The Appellant on 27.01.2020 through his Advocate called upon the Respondent No.1/ Promoter to allot the said flats in the name of Appellant. The Appellant on 16.02.2020 through a legal notice by his Advocate called upon both the Respondents/ Promoters to allot the said flats. The Respondent No.1/ Promoter never replied to the said notice. Respondent No 2/ promoter replied to the said notice on 23.02.2021 denying the allotment by citing a reason that there is no privity of contract between the parties. After repeated efforts to call upon the Respondents to update him on the status of the project and to execute agreement for sale in respect of the subject flats, there was no response from Respondent No.1 and Respondent No.2 denied the allotment citing a reason that there is no privity of contract with the Appellant. 


6).  Distressed by the Respondents Action and inaction namely failure to execute agreement for sale for said flats and failure to handover possession of the said flats, the Appellant filed separate Complaints for the subject flats bearing numbers CC006000000196427 and CC0060000000196424 on 18.03.2021 before the Authority and sought relief of 

  • (i) direction to the Respondents to execute and register agreements for sale as per provisions of Section 13 of RERA in respect of the subject flats, 

  • (ii) direction to Respondents to handover possession of the subject flats with Occupation Certificate, 

  • (iii) direction to Respondents to jointly and severally refund the entire amount of Rs.65,20,791/- and Rs.64,05 ,BB7l- paid by the Appellant for the subject flats along with interest. 


7). The Appellant/ Complainant was heard by the Authority and passed the impugned Order dated 22.02.2022. The Authority in the said impugned Order has observed that both the parties have been lssued notice for the hearing and they are directed to file their respective written submissions. Accordingly, the Complainant appeared through his Advocate and made the submissions. However, the Respondents even though have been duly issued notices on several occasions, they have neither appeared nor filed any reply on the record of MahaRERA. It therefore shows that the Respondents are not willing to contest the claims of the Complainant. Thereafter, Respondent No.2 filed an application on 28.06.2021 and prayed to delete his name on the ground that the Complainant has purchased the said flats from Respondent No.1. The Complainant opposed the application on the ground that both Respondents are jointly responsible in view of the joint venture agreement dated 15.04.2010 between them, whereby the Respondent No.1 has transferred/ assigned its development rights to Respondent No.2, Therefore, both the Respondents are jointly and severally liable for the project. The Authority observed that Respondent Nos.1 and 2 are Co-Promoters having area sharing' arrangements in the said project, Although both the Respondents are Promoters of the said project, they have the right to sell flats from their own shares. Respondent No.2 is not responsible for any allotment made by Respondent No.1 from its own share and therefore Respondent No.2 is not a necessary party and directed to delete the name of Respondent No.2 by his Order dated 04.10.2018. Further, the Authority rejected the claim of the Complainant of interest for delayed possession under Section 18 of RERA on the ground that Respondent No.1 has not agreed to any specific date for handing over possession of the subject flats in the allotment letters and there is no registered agreement for sale signed by both the parties indicating any agreed date of possession. The Authority directed Respondent No.1 to execute and register the agreement for sale for the subject flats as per provisions of Section 13 of RERA within the period of 30 days, failing which, the monies paid by the Complainant be refunded without any interest within the period of next 3 months. 


8).  Aggrieved by the impugned Order dated 22.02.2022, the Appellant has filed the captioned Appeals separately for each of the subject flats i,e, 1301 and 1302 and challenged the impugned Order on the following grounds: 

(i) the learned Authority failed to appreciate that by virtue of the agreement dated 15.04.2010 entered between the Respondents, which is a joint venture agreement, Respondent responsible to allot the subject flats in the name of the Appellant and execute and register the agreement for sale for the subject flats,

(ii) the learned Authority come to an erroneous conclusion that there is 'area sharing' arrangement between Respondent No.1 and Respondent No.2 and pursuant to which the Respondent No.2 is not responsible for any allotment made by Respondent No. 1 from its own share.

(iii) the learned Authority failed to appreciate that on 04.12.2017 MahaRERA had issued Circular brining maximum transparency, awareness and removal of doubts of word "co promoter" and that there is no difference made out between the landowner promoter and/ or and investor Promoter and that they shall be jointly liable for the functions and responsibilities specified under RERA in the same manner as the Promoter who obtains building permissions and carries out construction. 

(iv) the learned Authority failed to appreciate that by virtue of joint venture, both the Respondents must comply with the terms of the contract, and they will be jointly and severally liable for any breach of the terms and conditions of the contract. Hence, Respondent No.2 cannot escape the responsibility of allotment made by Respondent No.1. (v) the learned Authority erroneously concluded that there is no joint liability between Respondent Nos.1 and 2 when admittedly Respondent No.2 has neither appeared nor filed any reply to the Complaint. This being the admitted position, the doctrine of non-traverse as laid down under Order VIII Rule 5 of the Code of Civil Procedure fairly and squarely applies to the facts of this case. The learned Authority erred in holding that on the webpage information uploaded by Respondent No.2 while registering the project with MahaRERA, the name of Respondent No.1 appears to be shown as Co-Promoter having area sharing arrangement in the project, thereby drawing the conclusion that Respondent Nos. 1 and 2 have rights to sale the flat from their own share. 

(vi) the learned Authority failed to appreciate that the Respondents have neither appeared nor filed any such agreement at the time of hearings claiming its stance on area sharing. The learned Authority failed to take into consideration the letters of allotment and the correspondence shared between the parties thereafter. 

(vii) the learned Authority erred in holding that Respondent No.2 is not a necessary party in the Complaints filed by Appellant and SINCE Respondent Nos.l and 2 were CoPromoters, both had the right to sale the flat from their own share. 

(viii) the learned Authority overlooked the fact that Appellant had prayed for directions that the Respondents not only execute the registered agreement for sale but also hand over possession of the flat. The learned Authority while granting the prayer for execution and registering the agreement for sale by , Respondent No.1 did not grant any relief of handing over the possession to the Appellant, 

(ix) the learned Authority failed to appreciate that rights accrued upon Allottees once the terms of allotment are recorded in letter of allotment or otherwise agreed between the parties, is deemed to be certain and concluded contract, and that such rights cannot be scuttled merely by the absence of agreement for sale. 

(x) the learned Authority failed to appreciate that there is binding agreement between the parties in terms of the letters of allotment and emails. Further, since the parties have acted in furtherance of the said documents which is evident from the fact that the Respondents have accepted the payment in respect of the subject flats. 

(xi) the learned Authority has failed to correctly apply the provisions of RERA by erroneously interpreting Section 18 of the Act to read that relief under the said provision depends upon factum of execution of agreement for sale. The learned Authority has failed to consider that the Respondents are in breach of Section 4 of MOFA which casts an obligation upon the Respondents to enter into written agreement for sale and register the same before accepting any money as advance payment or deposit above 20% of the purchase price. Furthermore, the learned Authority has failed to consider that under Section 13 of RERA, the Respondents were obligated to execute and register the agreement for sale before accepting any payment more than l0% of the sale consideration. 

(xii) The Appellant has always made timely payment of the sale consideration of the subject flats and acted based on agreement between the parties in terms of the allotment letters. Accordingly, the impugned Order, to the extent it denies compensation for the delay in handover of the possession, suffers from material infirmity and therefore ought to be set aside. 


9). On the abovementioned grounds, the Appellant has sought the following relief in the Appeals. 

  • (i) Direction of quashing and setting aside the impugned Order, thereby directing the Respondents to jointly and severally handover the possession of the subject flats with Occupation Certificate to the Appellant. 

  • (ii) Direction that the Respondents to duly execute and register the agreement for sale, 

  • (iii) Direction to refund the entire amount of Rs.65,20,791/- and 64,05,8871- paid by the Appellant towards the consideration of the subject flats along with the interest. 

  • (iv) Direction to Respondents to jointly and severally pay to the Appellant compensation for the delay In handing over the possession of the subject flats as per provisions of Section 18 of RERA. 


10). We have heard learned Advocate Mr. Mayur Patel for Appellant and Advocate Ms. Jayshree Gilra for Respondent No,1. 


11). The submissions advanced by learned Advocate for Appellant are nothing but reiteration of the contents of the memorandum of appeal and written arguments. The learned Advocate has submitted that the Appellant is a Hindu Undivided Family represented by its Karta Mr. Kunvarjit Singh Malkeet Singh Matharu and Appellant is an allottee as per Section 2(d) of RERA. The appellant is legal heir of the original Karta Mr. Malkeet Singh Gulzar Singh Mathura who expired on 25.10.2016 and in whose name the allotment letters were issued by the Respondent No.1. Learned Advocate submitted that in spite of email correspondence dated 05.12.2019 addressed to Respondent No.1 and legal notice served on Respondent Nos. 1 and 2 asking for allotment of the subject flats, Respondent no. 1 never responded to the said email and notice. Respondent No.2, however, replied to the notice and denied its liability to allot the subject flats citing the reason that there was no privity of contract with the Appellant, Learned Advocate further submitted that the captioned Complaints were heard by the Authority where none of the Respondents appeared, no written or oral arguments were submitted by either of the Respondents. Learned Advocate submitted that there was binding agreement between the parties in terms of letters of allotment dated 22.09.2014 and 23.09.2014 and further email correspondence in furtherance of the said documents, Further, the Respondents have accepted the payments in respect of the subject flats. Despite payment of substantial amounts towards consideration of the subject flats, the Respondents failed to execute and register the agreement for sale for the subject flats in violation of Section 4 of MOFA as well as Section 13 of RERA. Learned Advocate further submitted that the Appellant is entitled to seek relief of interest for delayed possession as well as handover of possession of the said flats, Section 18 of RERA does not distinguish between the agreement for sale and letter of allotment when the question of payment of interest is to be determined. Consequently, the Appellant has right under Section 18 of RERA to receive interest on account of Respondents'failure to handover the possession of the subject flats in terms of allotment letter and oral promise by the Respondents that the possession will be handed over by 2016. 


12). With these submissions the Appellant prayed for allowing the Appeals. Since the Appellant has sought both the reliefs of seeking interest on account of delay in possession as well as refund of the amount paid to the Promoters with interest, both of which cannot be considered at the same time, therefore the Appellant during the proceedings before this Tribunal pressed for relief of refund with interest as well as compensation and waived the relief of execution of agreement for sale, handover of possession of the subject flats and interest on account of delay in possession. Advocate for Appellant has placed reliance on the following citations. 

  • i, Fortune Infrastructure (Now known as Hicon Infrastructure... Vs. Trevor D'lima & Ors.) [2018 (5) SCC 442

  • ii Experion Developers Pvt. Ltd. Vs. Sushma Ashok Shiroor 12022 (t5) SCC 2861 

  • iii, Wadhwa Group Housing Private Limited Vs. Mr. Vijay Choksi and SSS Escatics Private Limited 2024:BHCAS:931 

  • iv. Mrs. Amrita Kaur & Ors. Vs. East & West Builders Appeal No,4T0060000000 10997 


13). It is pertinent to note that Respondent No.1 did not appear before the Authority despite several chances, nor filed any written submissions or reply to the Complaint. Further, Respondent No,2 did not file any reply or written submissions. However, Respondent No,2 only submitted an application before the Authority for deletion of its name, which was decided by the Authority ex-parte. From the proceedings of this Tribunal, it transpires that Appeals have been proceed ex-parte against the Respondent No.2. Despite ample opportunities, Respondent No.1 has not filed a reply to the Appeals and hence the Appeals have been proceeded without reply of Respondent No,1, We have heard Advocate Jayshree Girla l/b Adv. Sanjay Chaturvedi for Respondent No.1. Learned Advocate submitted that the Appeals are not maintainable and prayed for dismissal of the Appeals. 


t4). After having considered submissions of the respective parties, supported by various documents on record, following points that arise for our consideration and finding thereon for the reasons to follow are as under:


Sr. No.

Points

Findings 


Whether Respondent Nos,1 and 2 are jointly and severally liable to discharge functions and obligations of the Promoters under RERA?

In the affirmative


Whether the Appellant is entitled for relief of direction to the Respondent Nos 1 and 2 to jointly and severally refund the amount paid by the Appellant with interest under section 18 of RERA?

In the affirmative


Whether the impugned Order Warrants interference in these Appeals?

In the affirmative


What Order?

As per final Order


REASONS 

Point No 1 

15). On ensembling the facts submitted above by the parties, it is not in dispute that subject flats bearing no.1301 and 1302 were booked in the name of Mr. Malkeet Singh Gulzar Singh Matharu for consideration of Rs.90,51,625/- each. It is also not in dispute that Respondent No.1 issued allotment letters on 22.09.2014 and 23.09.2014 for the respective flats to Mr. Malkeet Singh Gulzar received the payment of the amount of Rs,65,20,7911- and 64,05,8871- for the respective flats as per the demand letter issued by Respondent No.1. Mr. Malkeet Singh Gulzar Singh Matharu expired on 25.10.2016 and his son Kunwarjeet Singh Malkeet Slngh Matharu became karta of the family and being legal heir has filed the captioned Complaints and these Appeals. The subject project also registered wlth MahaRERA on 06.08.2017 with proposed date of completion of the project as 31.12.2019. is It is also on record that by email dated 05,12.2019 the Appellant had asked for status of balance payment and information on allotment of subject flats to Respondent No.1 and Respondent No,2. Further, the Appellant also served legal notice through his Advocate on 17.01.2020 calling upon Respondent No.2 to allot the subject flats. Appellant also served the legal notlce upon both Respondent Nos.1 and 2 on well as the legal notices were never responded to by Respondent No.1. However, Respondent No,2 replied to the notice on 23.02.2021 denying the allotment citing the reason that there is no privity of contract with the Appellant since allotment letters have been issued by Respondent No.1 and payment have been also received by Respondent No.1. Thus, despite substantial payment failed to execute and register the agreement for sale and handover possession of the subject flats in terms of allotment letters. Although the Appellant has sought relief of execution of agreement for sale, handover possession of the subject flats to Appellant, relief of interest on account of the delayed possession, the Appellant during the course of the proceedings in this Tribunal stuck to the prayers of relief of refund of the amount paid to the Respondents along with interest and compensation and gave up claims on other reliefs namely execution of agreement for sale, handover possession of the subject flats to Appellant, relief of Interest on the delayed possession. 


16) In the Complaint proceedings, Respondent No.2 had filed an application to delete his name from the Complaint on the ground that there is no privity of contract between Respondent No.2 and Appellant. While responding to the notice from the Appellant dated 23.02.2021, the Respondent No.2 has mentioned that the subject flats was booked by the Appellant which comes under the share of Respondent No.1 and consideration amount has been paid by Appellant to Respondent No.1. Therefore, there is no privity of contract, and Respondent No.2 has not received any consideration amount from the Appellant and hence Respondent No.2 shall not be held liable for any action mentioned in the notice. Therefore, the moot question for our determination is whether Respondent Nos.1 and 2 are jointly and severally liable to discharge the obligations of the Promoter under RERA Act, 2016. 


17) Section 4 of MOFA casts an obligation on the Promoters that they shall not accept sum of money as advance part price without entering into written agreement for sale and the agreement shall be registered under the Registration Act, 1908. Section 13 of RERA also casts a similar obligation on the part of Promoters that they shall not accept sum more than 10% of the purchase price from Allottee without first entering Into written agreement for sale and register the said agreement for sale. It is not in dispute that out of total consideration of Rs.90,51,6251- for each of the subject flats, the Respondent No.1 has received the payment of Rs.65,20,791l- and 64,05,8871- for the respective flats as per demand letter raised by Respondent No.1. Therefore, the Respondent No.1 has received more than 20% in case of provision of MOFA and 10% in case of provisions of RERA without executing and registering the agreements for sale. Therefore, Respondents/Promoters have violated the provisions of Section 4 of MOFA and Section 13 of RERA. The allotment letters also reveal that there is no specific date of possession mentioned. As per Section 4(1A)(aX)(ii) of MOFA, the Promoter is obligated to mention the date by which the possession of the flat is to be handed over to the purchaser. In view of this, there is also a violation of the said provision by the Respondents/Promoters on this count, 


18).  The Respondents by virtue of joint venture agreement are Promoter and Co-Promoter of the subject project. In the MahaRERA website, for the subject project Respondent No.1 has been shown as Promoter and Respondent No.2 as Co-Promoter. Therefore, the Respondents are Promoters within the meaning of definition of Promoter as contemplated under Section 2(zk) ot RERA Act, 2016, 


19).  While deliberating on the liability of the Promoters under RERA, it has been held by the Hon'ble Bombay High Court in Second Appeal (stamp) No. 21842 ot 2023 Wadhwa Group Housing Private Ltd. V/s. 1. Mr. Vijay Choksi 2. SSS Escatics Pvt. Ltd. That: 

  • "17. The project 'The Nest’ has been registered as an ongoing project under Section 3 of RERA Act. To decide liability of Appellant to refund amount paid for purchase of flat in the real estate project, it would be necessary to determine whether Appellant falls in the definition of the term 'promoter'. Section 2(zk) of RERA defines the term "Promoter" thus: 

  • (zk) "promoter" means, - (i) a person who constructs or causes to be constructed an independent building or a building consisting of apartments, or converts an existing building or a part thereof into apartments, for the purpose of selling all or some of the apartments to other persons and includes his assignees; 

  • (ii)or a person who develops land into a project, whether or not the person also constructs structures or any of the plots, for the purpose of selling to other persons all or some of the plots in the said project, whether with or without structures thereon; or 

  • (iii) any development authority or any other public body in respect of allottees of- 

  • (a) buildings or apartments, as the case may be, constructed by such authority or body on lands owned by them or placed at their disposal by the Government; 

  • (b) plots owned by such authority or body or placed at their disposal by the Government; 

  • (c) for the purpose of selling all or some of the apartments or plots,

  •  or 

  • (iv) an apex State level co-operative housing finance society and a primary co-operative housing society which constructs apartments or buildings for its Members or in respect of the allottees of such apartments or buildings; or 

  • (v) any other person who acts himself as a builder, colonizer, contractor, developer, estate developer or by any other name or claims to be acting as the holder of a power of attorney from the owner of the land on which the building or apartment is constructed or plot is developed for sale; or 

  • (vi) such other person who constructs any building or apartment for sale to the general pub/ic. 

  • Explanation.- For the purposes of this clause, where the Person who constructs or converts a building into apartments or develops a plot for sale and the person who sells apartments or plots are different personal both of them shall be deemed to be the promoters and shall be jointly liable as such for the functions and responsibilities specified under this Act or the rules and regulations made thereunder; 

  • Thus, definition of the term "Promoter" under Section 2(zk) of RERA is wide enough to include every person who is associated with construction of the building such as builder, colonizer, contractor, developer, estate developer or by any other name or even the one who claims to be acting as the holder of a power of attorney from the owner of the land. One of the principal objectives of RERA is to bring transparency in real estate sector and to protect the interests of the consumers in the real estate project. The term 'Promoter Has been so widely defined that it virtually includes every person associated with construction of the building. Thus, even a person who is merely an investor in the project along with the promoter and who is entitled to benefit in the real estate project is also covered by definition of the term 'Promoter'. In the present case, I need not delve deeper into the enquiry as to whether Appellant is covered by the expression ,promoter, or not. While registering the project as ongoing project under Section 3 of the RERA, Appellant's name has been included in the list of promoters. Therefore, Appellant cannot run away from the fact that it is the promoter in respect of the project 'The Nest'. Explanation to Section 2(zk) makes ail persons who construct or convert building into apartments or develop a plot for sale, as well as a person who sells apartments or plots to be promoters making them jointly liable as such for the functions and responsibilities specified under the Act or the Rules and Regulations made thereunder. Thus, a person who does not actually construct or causes to be constructed a building but merely takes part in the joint venture and sells flats, becomes a Promoter. Appellant admits that it is entitled to a share in the joint venture in the constructed area, which it is entitled to sell. Thus, the Appellant is entitled to sell flats in the project and accept consideration for such sale. There is therefore no doubt to the position that, both Appellant as we// as the second Respondent are promoters and are jointly liable in respect of the responsibilities under the RERA and Rules and Regulations made thereunder. 

  • 18. In my view therefore, mere falling of ftat in the share of the second Respondent under the loint Development Agreement, would not excuse the Appellant from the responsibilities and liabilities under the RERA, Rules and Regulations made thereunder qua that flat. RERA does not demarcate or restrict liabilities of different promoters in different areas. The liability is joint for all purposes under the Act Rules and Regulations. 

  • 19. Circular dated 4 December 2017, on which reliance is placed on behalf of the Appellant, far from assisting it, actually militates against the Appellant. The Circular is issued with a view to tackle a situation where several developers had entered into agreements with individuals/organizations like land owners or investors by which such individuals/organizations were also entitled to share in the total revenue generated out of sale of apartments. It was observed that such individuals/ organizations were not included in the online registration with MahaRERA. With a view to ensure their inclusion in the online registration with, the Circular dated 4 December 2017 is issued. Relevant part of the Circular reads thus: 

  • Whereas, during the online registration process, especially for ongoing projects, it was observed that several developers (who actually obtain building permissions and construct) of the real estate project, have entered into arrangement with individuals/organizations like land owners or investors, by which the said Individuals/organizations are entitled to a share of the total revenue generated from sale of apartments or share of the total area developed for sale which are also marketed and / or sold by such individuals/organizations. 

  • Whereas, a careful consideration of the aforesaid definition in the light of the true object and purpose of the said Act leaves no manner of doubt that such individuals/organizations are also covered and clearly fall within the aforesaid definition of the term 'Promoter And as such are Promoters within the meaning of the said terms for the purpose and for the implementation of the said Act and all the rules framed thereunder. They are therefore jointly liable for the functions and responsibilities specified in the Act in the same manner as the Promoter who actually obtains building permissions and carries out construction. 

  • Whereas, for the ease of filing online registration application and for the benefit of the consumers it is necessary to distinguish and / or identify whether such Promoter is the land owner, investor or is actually obtaining the building permissions for carrying out the construction and is in fact carrying out construction. 

  • Therefore, it is directed that 

  • (1) Such individuals/ organizations who fall within the aforesaid definition of the term 'Promoter' on account of being landowners or investors, shall be specified as such,, at the time of online registration With MahaRERA. 

  • (2) Though liabilities of such landowner Promoter or investor Promoter shall be as co-terminus with the written agreement / arrangement governing their rights in the real estate prolect, for the purpose of withdrawal from the designated bank account of a real estate project, the obligations and liabilities of all such Promoters shall be at par with each other. 

  • (3) A copy of the written agreement or arrangement between Promoters (whether landowner or investor) which clearly specifies and details the rights and shares of each Promoter, should be uploaded on the MahaRERA website, along with other details for public viewing. 

  • (4) Such landowner Promoter and investor Promoter should also submit declaration in Form B of Maharashtra Real Estate (Regulation and Development) (Registration of Real Estate Projects, Registration of Real Estate Agent, rates of Interest and Disclosures on website) Rules, 2017. 

  • (5) Further each such landowner Promoter or investor Promoter, who is entitled to a share of the total area developed, should also open separate bank account for deposit of 70% of the sale proceeds realized from the allottees of their share. 

  • 20. Thus, the Circular dated 4 December 2017 also makes it abundantly clear that even the entities who are entitled to share in the revenue generated from sale of flats are jointly responsible/liable for functions and responsibilities specified under the Act as if they are Promoters themselves. " 


20). Therefore, we are of the view that Respondent No.1 and Respondent No.2 being Promoters are equally liable for functions and responsibilities specified under RERA Act, 2016 and hence they are jointly and severally liable for discharging their liabilities under section 18 of RERA. 


21). With regard to absence of privity of contract between the Appellant and Respondent No.2 is concerned, the Hon'ble Bombay High Court in Second Appeal (stamp) No. 2t842 of 2023 Wadhwa Group Housing Private Ltd. V/s. 1. Mr. Vijay Choksi 2. SSS Escatics Pvt. Ltd has held that: 

  • "24. The Appellant's contention about absence of privity of contract between it and the Complainant is tota//y misplaced. Definition of the term 'promoter' under Section 2(zk) ot the RERA would indicate that even persons/entities with whom a flat purchaser does not enter into contract are also covered by definition of the term 'promoter. Therefore, it is not necessary that there has to be an agreement between every Promoter and the flat purchaser. As observed above, it is a matter of indoor management between the promoters and the flat purchaser who is not supposed to know the intricacies of the arrangements made between several promoters amongst themselves. When a claim is raised in respect of a real estate project by a flat purchaser, all promoters become jointly liable qua that flat purchasers, irrespective of whether there is privity of contract with each of the promoters or not. This is the scheme of RERA and mere absence of privity of contract with a particular promoter does not relieve such promoter in respect of the liabilities under RERA"


22). Therefore, from the dictum and ratio laid down in above judgment by Hon'ble High Court, we are of the view that Respondent No.2 cannot escape its liability or obligation as Promoter under the provisions of RERA and hence Respondent Nos.1 and 2 are jointly and severally liable in respect of the responsibilities and liabilities under the RERA and Rules and Regulations made thereunder. We, therefore, answer point number 1 accordingly. 


Point No.2 

23).  It is pertinent to note that the allotment letters issued by Respondent No.1 do not disclose date of possession although they reveal all the necessary ingredients of a contract such as total consideration, payment schedule and other terms and conditions. In the absence of formal agreement executed by the parties, the date of possession can be deciphered from any documents such as allotment letter, brochure, pamphlet, email communication, etc. In this case, the allotment letters are the only documents available, which however do not disclose the agreed date of possession. In the case of Fortune Infrastructure (Now Known as M/s Hicon Infrastructure) & Anr. Vs. Trevor D'Lima & Ors. [(2018) 5 SCR 273] the Hon'ble Apex Court has held that if the date of possession is not mentioned in the agreement, the Promoter is expected to handover the possession of the unit within a reasonable time and the period of three years held to be reasonable time. In the instant case, the Appellant has booked the subject flats on 22.09.2014 and 23.09.2014 respectively. Therefore, we conclude that the date of possession would be on or before 22.09.2017 and 23.09.2017 respectively for the subject flats. 


24). It is worthy to note that it is not in dispute that the Respondents have failed to handover possession of the subject flats to the Appellant by the date of possession as mentioned above. There is no material on record to show that the Appellant is responsible for the delay in completing the subject project. The ratio laid down by the Hon'ble Supreme Court in M/s. Imperia Structures Ltd. Vs. Anil Patni & Ors. [in Civil Appeal No.3581- 3590 of 20201 is that- 

  • " In terms of Section 18 of the RERA Act, if a promoter falls to complete or is unable to give possession of an apartment duly completed by the date specified in the agreement, the Promoter would be liable on demand, to return the amount received by him in respect of that apartment if the allottee wishes to withdraw from the project. Such right of an allottee is specifically made "without prejudice to any other remedy available to him". The right so given to the allottee is unqualified and if availed, the money deposited by the allottee has to be refunded with interest at such rate as may be prescribed. The proviso to Section 18(1) contemplates a situation where the allottee does not intend to withdraw from the project. In that case he is entitled to and must be paid interest for every month of delay till the handing over of the possession. It is upto the allottee to proceed either under Section 18(l) or under proviso to Section 1B(1)." 


25). While explaining the scope of Section 18 of RERA, the Hon'ble Supreme Court in M/s. Newtech Promoter and Developers Pvt. Ltd. V/s. State of Uttar Pradesh [2021 SCC Online 10441 dated 11 November, 2021 held that; 

  • "Para 25. The unqualified right of the allottee to seek refund referred under Section 18(1)(a) and Section 19(4) of the Act is not dependent on any contingencies or stipulations thereof. It appears that the legislature has consciously provided this right of refund on demand as an unconditional absolute right to the allottee, If the promoter fails to give possession of the apartment, plot or building within the time stipulated under the terms of the agreement regardless of unforeseen events or stay orders of the Court/Tribunal, which is in either way not attributable to the allottee/home buyer, the promoter is under an obligation to refund the amount on demand with interest at the rate prescribed by the State Government including compensation in the manner provided under the Act with the proviso that if the allottee does not wish to withdraw from the project| he shall be entitled for interest for the period of de/ay till handing over possession at the rate prescribed. 


26).  In the light of the discussion above, we are of the view that mere non-execution of the agreement for sale, Allottees are not precluded from invoking Section 18 of RERA. The provisions of Section 18 of RERA can equally be invoked in terms of oral or formal agreement executed by the Promoter/ Developer such as booking application form/ formal letter/ allotment letter/ letter of intent/ correspondence, etc. capable of being construed as an agreement, Admittedly, the subject project is an ongoing project. As per the view taken by this Tribunal in catena of cases, provisions of RERA are applicable to this project. Accordingly, the allotment letters issued by the Respondents to the Appellant prior to RERA are enforceable under Section 18 of RERA. 


27). Section 18 of the Act spells out the consequences that, if Promoter fails to complete or is unable to give possession of an apartment by the dates specified in the agreement for sale, the Allottee holds an unqualified right to seek refund of the amount with interest at such rate as may be prescribed in this behalf including compensation in the manner as provided in RERA. We have already observed that the Promoter has violated the provisions of Section 4 of MOFA and Section 13 of RERA by not executing and registering agreements for sale for the subject flats even after having received more than 20?% of the sale price. Therefore, we are of the view that the Appellant is entitled to seek relief of refund with interest under Section 18 of RERA. However, since the Appellant has not sought relief of compensation in the complaints, the same cannot be granted in the Appeals. As both the Respondents are jointly and severally liable to discharge their obligations as Promoters under RERA, we hold that Respondent Nos.1 and 2 are jointly and severally liable to refund the amount paid by the Appellant in respect of the subject flats along with interest under Section 18 of RERA. Accordingly, we answer Point No.2 in the affirmative. 


Point No.3 

28).  While passing the impugned Order, the Authority has observed that Respondent No.2 is not responsible for any allotment made by Respondent No.1 on the ground that there is no privity of contract between Appellant and Respondent No. 2 and therefore Respondent No.2 is not a necessary party and directed to delete the name of Respondent No.2 by its Order dated 04.10.2018. Further, the Authority rejected the claim of the Complainant under Section 18 of RERA on the ground that Respondent No.1 has not agreed to any specific date for handing over possession of the subject flats in the allotment letters and there is no registered agreement for sale signed by both the parties indicating any agreed date of possession. From the discussion and observations hereinabove, the view taken by the Authority is contrary to the provisions of RERA and also to the ratio laid down by Hon'ble Apex Court as mentioned above. Thus, the same is found unsustainable in the eyes of law and hence calls for interference in these Appeals' We therefore answer Point No.3 in the affirmative. Consequently, we proceed to pass the following Order. 


ORDER 

(i) Appeal Nos.AT006000000063797 and AT006000000063798 are partly allowed with the following directions. 

  • a. The impugned Order dated 22.02.2022 passed in Complaints Nos.CC006000000196424 and CC006000000196427 is set aside. 

  • b, The Respondent Nos.1 and 2 are directed to refund jointly and severally the amount of Rs.65,20,791l- and Rs.64,05,887/- paid by the Appellants to the Respondent No,1 towards consideration of the subject flats together with interest on the paid amounts as per SBI's highest Marginal Cost Lending Rate (MCLR) plus 2% from the date of payments within 30 days from the date of this order, failing which the Respondents shall also pay interest at this prescribed rate on the total amount due and outstanding as on 19th October 2024 till its realization. 

  • c. Parties shall bear their own costs. 

  • d. Copy of this Order be communicated to the Authority and the respective parties as per Section 44(4) ot RERA, 2016. 

-----------------------------------------------