Wednesday, 24 June 2026

T.K.A. Padmanabhan vs Abhiyan Cooperative Group Housing Society Limited . - A claim for compensation for delayed possession necessarily arises from the period prior to the actual delivery of possession. The subsequent receipt of possession cannot, by itself, extinguish the right of the allottee to seek adjudication of a claim for compensation for the alleged delay.

 SCI (2026.06.04) in T.K.A. Padmanabhan vs Abhiyan Cooperative Group Housing Society Limited . [CIVIL APPEAL NO(S). 10724/2016] held that;

  • A claim for compensation for delayed possession necessarily arises from the period prior to the actual delivery of possession. The subsequent receipt of possession cannot, by itself, extinguish the right of the allottee to seek adjudication of a claim for compensation for the alleged delay.


Excerpts of the Order;

# 1. Permission to appear and argue in person is granted to the appellant.


# 2. The present civil appeal arises from the judgment and order dated 04.01.2016 passed by the National Consumer Disputes Redressal Commission, New Delhi [In short “National Commission” ] in Revision Petition No. 1942 of 2013.


# 3. The appellant, T.K.A. Padmanabhan, had instituted Consumer Complaint No. 579 of 2005 before the District Consumer Forum-VII, New Delhi [In short “District Forum”] against the respondent, Abhiyan Cooperative Group Housing Society Limited, alleging deficiency in service on account of delay in handing over possession of Flat No. 232.


# 4. The District Forum, by order dated 27.07.2009, referred the parties to arbitration. The said order was affirmed by the Delhi State Consumer Disputes Redressal Commission [In short “State Commission”] by order dated 26.02.2013. The appellant’s revision petition against the same came to be dismissed by the National Commission by the impugned order dated 04.01.2016.


# 5. The facts giving rise to the present appeal are as follows:

5.1. The appellant became a member of the respondent society in January 2003. He claims to have paid the full amount towards allotment of a flat in the respondent society.

5.2. Flat No. 232 was allotted to the appellant and an agreement was entered into between the parties on 27.02.2004.

5.3. On 08.08.2005, the appellant filed Consumer Complaint No. 579 of 2005 before the District Forum claiming compensation for the alleged delay in handing over possession of the flat. 

5.4. The complaint was admitted and notice was issued to the respondent. Thereafter, the respondent filed an application under Section 8 of the Arbitration and Conciliation Act, 1996, seeking reference of the dispute to arbitration.

5.5. By order dated 21.09.2005, the District Forum rejected the said application, inter alia, on the ground that the remedy under the Consumer Protection Act, 1986, was in addition to any other remedy available to an aggrieved party. 

5.6. The respondent challenged the said order before the High Court of Delhi in C.M.(M) No. 2405 of 2005. By order dated 30.03.2007, the High Court set aside the order dated 21.09.2005 and directed the District Forum to reconsider the issue by passing a reasoned order.

5.7. The respondent thereafter approached this Court in Special Leave Petition (Civil) No. 9962 of 2007, which was dismissed on 28.07.2008.

5.8. Upon reconsideration, the District Forum, by order dated 27.07.2009, allowed the respondent’s application under Section 8 of the Arbitration and Conciliation Act, 1996, and referred the parties to arbitration.

5.9. The appellant challenged the said order before the State Commission in First Appeal No. 680 of 2009. By order dated 26.02.2013, the State Commission dismissed the appeal and affirmed the order passed by the District Forum.

5.10. The appellant then filed Revision Petition No. 1942 of 2013 before the National Commission. By the impugned order dated 04.01.2016, the National Commission dismissed the revision petition. Hence, the present appeal.


# 6. We have heard the appellant, who appears in person, and learned counsel appearing for the respondent society.


# 7. The appellant has submitted that the consumer complaint could not have been referred to arbitration merely on the basis of an arbitration clause in the agreement between the parties. According to him, the complaint had already been admitted and notice had been issued to the respondent. It is therefore submitted that the District Forum ought to have decided the complaint on merits in accordance with the Consumer Protection Act, 1986.


# 8. Learned counsel for the respondent, on the other hand, has supported the orders passed by the District Forum, the State Commission and the National Commission. It is submitted that the agreement between the parties contained an arbitration clause and, therefore, the consumer fora committed no error in relegating the parties to arbitration.


# 9. In view of the above, the question which arises for our consideration is whether the consumer complaint filed by the appellant could have been referred to arbitration  without adjudication on merits, and whether the National Commission was justified in dismissing the revision petition on the ground that the appellant was not a consumer.


RELEVANT STATUTORY FRAMEWORK

# 10. Before we examine the correctness of the orders passed by the consumer fora, it is necessary to state the relevant provisions of the Consumer Protection Act, 19864 applicable to the present case.


# 11. Section 2(1)(d) of the 1986 Act defines the term “consumer”. Insofar as the present case is concerned, the relevant part of the provision reads as under:

  • “consumer” means any person who hires or avails of any services for a consideration which has been paid or promised or partly paid and partly promised, or under any system of deferred payment, and includes any beneficiary of such services other than the person who hires or avails of the services for consideration paid or promised, or partly paid and partly promised, or under any system of deferred payment, when such services are availed of with the approval of the first mentioned person.” In short “the 1986 Act”


# 12. Section 2(1)(o) of the 1986 Act defines the term “service”. The said provision, insofar as relevant, has been reproduced hereunder:

  • “service” means service of any description which is made available to potential users and includes, but is not limited to, the provision of facilities in connection with banking, financing, insurance, transport, processing, supply of electrical or other energy, board or lodging or both, housing construction, entertainment, amusement or the purveying of news or other information, but does not include the rendering of any service free of charge or under a contract of personal service.”


# 13. Section 3 of the 1986 Act expressly declares the nature of the remedy under the Act. It reads as follows:

  • “Act not in derogation of any other law.—The provisions of this Act shall be in addition to and not in derogation of the provisions of any other law for the time being in force.”


# 14. Section 12 of the 1986 Act assumes particular significance in the present case. It deals with the manner in which a complaint may be made before the District Forum. Sub- section (4) thereof is material and reads as under:

  • “Where a complaint is allowed to be proceeded with under sub-section (3), the District Forum may proceed with the complaint in the manner provided under this Act.

  • Provided that where a complaint has been admitted by the District Forum, it shall not be transferred to any other court or tribunal or any authority set up by or under any other law for the time being in force.”


# 15. The respondent had invoked Section 8 of the Arbitration and Conciliation Act, 1996, on the ground that the agreement between the parties contained an arbitration clause. The question, therefore, is whether the existence of such an arbitration clause could have displaced the statutory jurisdiction of the consumer forum in the facts of the present case.


ANALYSIS

# 16. At the outset, we must emphasize that the 1986 Act is a beneficial legislation intended to provide a simple, inexpensive and expeditious remedy to a consumer who complains of defect in goods or deficiency in service. Section 3 of the 1986 Act makes the position explicit by providing that the remedy under the Act is in addition to and not in derogation of any other remedy available under law. The existence of another forum or another mode of adjudication, therefore, does not by itself exclude the jurisdiction of the consumer fora.


# 17. This principle has been consistently recognised by this Court. In Fair Air Engineers Pvt. Ltd. v. N.K. Modi5  [(1996) 6 SCC 385], this Court held that the remedy under the 1986 Act is an additional remedy and that the existence of an arbitration clause would not automatically oust the jurisdiction of the consumer forum. The same principle was reiterated in Secretary, Thirumurugan Cooperative Agricultural Credit Society v. M. Lalitha [(2004) 1 SCC 305], where this Court held that the remedy under the 1986 Act is available notwithstanding the existence of remedies under the cooperative societies law. Again, in National Seeds Corporation Ltd. v. M. Madhusudhan Reddy [(2012) 2 SCC 506], this Court emphasised that the availability of an alternative statutory remedy is not a bar to the maintainability of a consumer complaint.


# 18. The position has been put beyond doubt in Emaar MGF Land Ltd. v. Aftab Singh [(2019) 12 SCC 751]. In the said decision, this Court held that even where an agreement contains an arbitration clause, the consumer forum is not denuded of its jurisdiction to entertain and decide a consumer complaint. The reason is that the 1986 Act creates a special and additional remedy for consumers and the  jurisdiction so conferred cannot be displaced merely by reference to an arbitration agreement between the parties.


# 19. The legal position upheld in the precedents above is of direct relevance in the present case. The appellant’s complaint was not a civil suit simpliciter. It was a complaint under the 1986 Act alleging deficiency in service on account of delay in handing over possession of a flat. The fact that the agreement between the parties contained an arbitration clause could not, by itself, be treated as sufficient to non-suit the appellant before the consumer forum.


# 20. The matter must also be examined in the light of Section 12(4) of the 1986 Act. Section 12 of the 1986 Act contemplates a statutory sequence. At the threshold, the District Forum is required to consider whether the complaint deserves to be admitted or rejected. Once the complaint is admitted and allowed to be proceeded with, the forum is required to deal with it in the manner provided under the Act. The proviso to Section 12(4) contains a clear legislative restraint. It provides that where a complaint has been admitted by the District Forum, it shall not be transferred to any other court, tribunal or authority set up by or under any other law for the time being in force.


# 21. The significance of the proviso lies not merely in its text, but also in the statutory policy which it reflects. The 1986 Act creates a special adjudicatory mechanism for consumer disputes. Once that mechanism is validly invoked and the complaint is admitted, the consumer cannot be driven out of that forum merely because the agreement between the parties contains an arbitration clause. A private contractual clause cannot be permitted to defeat the continued operation of a statutory remedy which Parliament has expressly made additional to other remedies under Section 3 of the 1986 Act.


# 22. Section 12(4) therefore has to be read harmoniously with Section 3 of the 1986 Act. Section 3 preserves the additional character of the consumer remedy. Section 12(4), after admission of the complaint, gives procedural effect to that protection by requiring the consumer forum to proceed under the Act and by preventing diversion of the complaint to another forum. The provision is intended to ensure that a consumer complaint, once admitted, is not rendered illusory by compelling the consumer to begin afresh before another forum or authority.


# 23. In the present case, the complaint had been admitted and notice had been issued to the respondent. The respondent thereafter filed an application under Section 8 of the Arbitration and Conciliation Act, 1996. The District Forum  initially rejected the application by noticing that the remedy under the 1986 Act is in addition to other remedies. However, after the matter was remitted by the High Court for reconsideration, the District Forum referred the parties to arbitration. The State Commission affirmed that view. In our opinion, this approach did not give due effect to the scheme of the 1986 Act and to the settled principle that an arbitration clause does not, by itself, oust the jurisdiction of the consumer forum.


# 24. The order of the National Commission suffers from an additional infirmity. The principal issue before the National Commission was whether the District Forum and the State Commission were justified in referring the complaint to arbitration. The National Commission, however, dismissed the revision petition on the ground that the appellant was not a consumer at the time of filing of the complaint, since he had already taken possession of the flat without protest. In doing so, the National Commission failed to address the central jurisdictional question arising from the orders passed by the District Forum and the State Commission.


# 25. The reasoning adopted by the National Commission cannot be sustained. The appellant’s complaint was not for delivery of possession simpliciter. His grievance was that there had been delay in handing over possession of  the flat and that he was entitled to compensation for such delay. A claim for compensation for delayed possession necessarily arises from the period prior to the actual delivery of possession. The subsequent receipt of possession cannot, by itself, extinguish the right of the allottee to seek adjudication of a claim for compensation for the alleged delay.


# 26. Whether there was in fact any delay, whether such delay was attributable to the respondent, whether the appellant had accepted possession unconditionally, and whether any compensation is payable are all matters which require adjudication on merits. The consumer complaint has not been adjudicated on merits at any stage. The claim of the appellant for compensation on account of alleged delay in handing over possession has neither been accepted nor rejected after evidence. Equally, the defence of the respondent society has also not been examined on merits. These issues could not have been concluded at the threshold by holding that the appellant ceased to be a consumer merely because possession had been delivered before the complaint was filed. In such circumstances, it would not be appropriate for this Court to record any finding on the factual controversy between the parties.


# 27. The proper course, therefore, is to restore the consumer complaint for adjudication on merits. The parties must be  afforded due opportunity of hearing and of leading evidence. All questions relating to deficiency in service, delay, waiver, acceptance of possession, entitlement to compensation, and all other issues on merits shall remain open to be considered by the competent consumer forum in accordance with law.


# 28. During the intermediary period, the District Consumer Disputes Redressal Commission has been set up at Dwarka. It is also stated before us that both parties are staying in Dwarka. In view of the same, and in order to avoid any further inconvenience and delay, it would be appropriate to direct that the complaint be placed before the District Consumer Disputes Redressal Commission, Dwarka.


CONCLUSION

# 29. For the reasons recorded above, the appeal is allowed.


# 30. The judgment and order dated 04.01.2016 passed by the National Commission in Revision Petition No. 1942 of 2013, the order dated 26.02.2013 passed by the State Commission in First Appeal No. 680 of 2009, and the order dated 27.07.2009 passed by the District Forum are set aside.


# 31. Consumer Complaint No. 579 of 2005, stated to have been renumbered as Complaint No. 712 of 2007, is restored and  shall be placed before the District Consumer Disputes Redressal Commission, Dwarka, for decision on merits.


# 32. The District Consumer Disputes Redressal Commission, Dwarka, shall decide the complaint after affording due opportunity of hearing and of leading evidence to both parties.


# 33. Since the complaint is of the year 2005, the District Consumer Disputes Redressal Commission, Dwarka, shall make an endeavour to decide the same preferably within a period of one year from the date of receipt of a copy of this order.


# 34. Pending application(s), if any, shall stand disposed of.

----------------------------------------------



Sunday, 21 June 2026

Shree Sankalp Associates Vs. Mr. Vishal Jugalkishor Pallod - In view of the above settled position of law, statutory right to claim relief of interest under Section 18 of the RERA Act, 2016 is indefensible and unconditional right that cannot be defeated for any reasons. Therefore, in our view the impugned order is sustainable in the eyes of law and does not warrant any interference in this appeal.

 REAT Maharashtra (2026.06.09) Shree Sankalp Associates Vs. Mr. Vishal Jugalkishor Pallod [Appeal No. ATO5 100276 of 2026 Along with Misc. Application No.294 of 2026 (Stay)] held that;

  • Thus, it is clear that during the reconciliation, the issue of possession was settled. However, there is no discussion or record in the minutes of the conciliation that the complainant has waived off its right to receive interest under Section 18 of the RERA Act, 2016 on account of delay in possession. Therefore, we are of the considered view that the contention of the appellant/promoter that the said settlement arrived at before the Conciliation Forum constitutes full and final resolution of the claims relating to both possession and interest is not tenable.

  •  In view of the above settled position of law, statutory right to claim relief of interest under Section 18 of the RERA Act, 2016 is indefensible and unconditional right that cannot be defeated for any reasons. Therefore, in our view the impugned order is sustainable in the eyes of law and does not warrant any interference in this appeal.


Excerpts of the Order;

# 1. The captioned appeal arises from the order dated 17.12.2025 passed by the learned Member-I, Maharashtra Real Estate Regulatory Authority (for short "the AuthorityJ in the captioned complaint filed by the respondent herein/allottee. 


# 2. The appellant is the promoter of the project in the name and style as "The Legend Phase II" bearing MahaRERA Project Registration No. P52100025986 located at Hinjewadi, Mulshi, Dist. Pune. 


# 3. For the sake of convenience, the parties to the appeal will be hereinafter referred to as “appellant/promoter" and "complainant/aIlottee" respectively. 


# 4. The brief facts gathered from the pleadings, impugned order, and the material placed on record reveal that the complainant/allottee is a sole proprietor of the marketing firm "Sun Publicity". Sometime in May, 2021 the promoter approached the complainant for seeking his marketing services and appointed him as Marketing Representative. It was agreed between the parties that in lieu of payment of professional fees, the title of one residential unit in the said project will be transferred to the complainant as consideration for the services rendered. Accordingly, the memorandum of understanding dated 05.05.2021 was signed between the parties, which also formed part of the agreement for sale signed between them. Out of the professional fees, Rs.15,00,000/- were adjusted as part of the consideration of the flat. The agreement for sale dated 28.03.2022 came to be executed and registered. As per the said agreement for sale, the due date of possession is 30.06.2024. However, the promoter failed to hand over possession of the said flat to the complainant by the said due date and withheld the possession even when the promoter obtained occupation certificate on 21.10.2024. Aggrieved by the above, the allottee/complainant filed the captioned complaint on 12.07.2024 before the Authority seeking relief of possession of the said flat along with interest on account of delay in possession and compensation under Section 18 of the Real Estate (Regulation and Development) Act, 2016 (for short 'the RERA Act, 2016). 


# 5. The promoter appeared in the said complaint and remonstrated the complaint contending that the possession of the flat has already been handed over to the complainant on 23.10.2024 and the possession letter is also executed. Hence, the claim sought by the complainant does not survive. 


# 6. It transpires that during the conciliation proceedings on 26.09.2024, the parties arrived at an amicable settlement, pursuant to which the complainant agreed to pay Rs.25,00,000/- of balance consideration amount and upon receipt thereof the promoter agreed to hand over possession of the flat to the complainant, which was subsequently handed over on 23.10.2024 upon receipt of the said balance consideration amount of Rs.25,00,000/- from the complainant. Thus, the settlement was acted upon by the parties and the dispute was amicably settled. 


# 7. Record reveals that the complainant made payments of the consideration amount as per the following details: 


Sr. No.

Amount

Payment date


15,00,000/-

01.07,2024 


23,00,000/-

03.10.2024 


2,00,000/-

18.10.2024


# 8. After hearing the parties, the Authority passed the impugned order. In the impugned order, the Authority observed that the due date of possession as per the said agreement for sale is 30.06.2024, whereas the occupation certificate was obtained on 21.10,2024 and possession was handed over on 23.10.2024. Therefore, the complainant is entitled to receive interest under Section 18 of the RERA Act, 2016  on account of delay in possession. Further, the promoter has not placed on record any justification for the delay in possession. With these observations, the Authority held that the complainant is entitled to interest under Section 18 of the RERA Act, 2016 from 01.07.2024 till the offer of possession with occupation certificate dated 21.10.2024 on the actual amount paid by the complainant towards the consideration. 


# 9. Aggrieved by the impugned order, the appellant promoter has filed the captioned appeal challenging the impugned order on the grounds set out in the memorandum of appeal, seeking the following reliefs 

  • a) Allow the appeal, 

  • b) Set aside the impugned order, 

  • c) Hold that the settlement arrived at before the Conciliation Forum constitutes full and final resolution of claims relating to possession and interest, 

  • d) Dismiss the complaint. 


# 10. We have heard the learned Advocate for the appellant. Record reveals that none appeared for respondent/allottee. Further, respondent neither filed any reply nor written submissions. Therefore, the averments of the appellant/promoter remained uncontroverted by the respondent/allottee. 


# 11. We have given due consideration to the submissions of the appellant and material on record. The submissions of the learned Advocate for the appellant are nothing but reiteration of the contents of the memorandum of appeal. Having examined the submissions of the appellant and the material on record, the following points arise for our consideration and we have recorded our findings thereon for the reasons to follow, as under. 


Sr. No.

Points

Findings


Whether the impugned order warrants interference in this appeal?

In the negative


What order?

As per final order.


REASONS 

Point No.1 

# 12. On ensemble of the facts as submitted by the appellant and the material on record, it is not in dispute that the respondent/allottee purchased the said flat vide an agreement for sale dated 28.03.2022. Out of total consideration amount, the respondent/allottee has paid Rs.15,00,00/- to the promoter. As per the said agreement for sale, the due date of possession is 30.06.2024. The promoter obtained occupation certificate of the building covering the subject flat on 21.10.2024. The promoter handed over the possession of the flat to the respondent/allottee on 23.10.2024 after receipt of the balance consideration amount of Rs.25,00,000/-. The complaint is filed on 12.07,2024. Thus, the amount paid by the respondent prior to filing of the complaint is Rs.15,00,000/-. As the due date of possession of the flat as per the said agreement for sale is 30,06.2024, whereas the promoter obtained occupation certificate on 21.10.2023. This sufficiently demonstrates that the promoter failed to hand over possession by the due date of possession as specified in the agreement for sale, 


# 13. Record reveals that vide roznama dated 05.08.2024, the complainant has sought the matter to be referred to for reconciliation to explore the possibility of amicable settlement. The roznama dated 26.09.2024 of the Conciliation records as under: 

  • "The respondent has committed to give possession of the flat post receiving outstanding payment along with GST amount from the complainant. The complainant has agreed to pay the outstanding amount of Rs.25,00,000/- plus GST amount to the respondent within 15 days from this hearing. The parties have resolved, and the matter is adjourned for a final hearing to document an amicable settlement." 


# 14.When the matter was finally heard by the Authority, the Authority in the impugned order recorded that though the issue of possession was subsequently resolved during the pendency of the complaint, the MahaRERA is required to adjudicate the substantive issue of interest and compensation sought by the complainant under Section 18 of the RERA Act, 2016. Thus, it is clear that during the reconciliation, the issue of possession was settled. However, there is no discussion or record in the minutes of the conciliation that the complainant has waived off its right to receive interest under Section 18 of the RERA Act, 2016 on account of delay in possession. Therefore, we are of the considered view that the contention of the appellant/promoter that the said settlement arrived at before the Conciliation Forum constitutes full and final resolution of the claims relating to both possession and interest is not tenable. 


# 15. As we have already observed, the due date of possession is 30.06.2024, whereas the promoter obtained occupation certificate on 21.10.2024. This sufficiently demonstrates that the promoter failed to hand over possession of the flat by the due date of possession as specified in the agreement for sale, Therefore, the complainant is entitled to relief of interest under Section 18 of the RERA Act, 2016, on account of delay in possession. We also note that the Authority has observed that the promoter has failed to place on record any justified reasons for delay in handing over possession of the said flat as per the agreed date of possession in the agreement for sale. 


# 16. While explaining the scope of Section 18 of RERA, the Hon'ble Supreme Court in M/s. Newtech Promoter and Developers Pvt, Ltd. V/s, State of Uttar Pradesh 1202t SCC Online 10441 dated 11 November, 2021 held that;

  •  "Para 25, The unqualified right of the allottee to seek refund referred under Section 18(1)(a) and Section 19(4) of the Act is not dependent on any contingencies or stipulations thereof. It appears that the legislature has consciously provided this right of refund on demand as an unconditional absolute right to the allottee, if the promoter fails to give possession of the apartment, plot or building within the time stipulated under the terms of the agreement regardless of unforeseen events or stay orders of the Court/Tribunal, which is in either way not attributable to the allottee/home buyer, the promoter is under an obligation to refund the amount on demand with interest at the rate prescribed by the State Government including compensation in the manner provided under the Act with the proviso that if the allottee does not wish to withdraw from the project, he shall be entitled for interest for the period of delay till handing over possession at the rate prescribed." 


# 17. In view of the above settled position of law, statutory right to claim relief of interest under Section 18 of the RERA Act, 2016 is indefensible and unconditional right that cannot be defeated for any reasons. Therefore, in our view the impugned order is sustainable in the eyes of law and does not warrant any interference in this appeal. Accordingly, we answer point no.1 in the negative. 


# 18. It is pertinent that the complainant has paid only Rs.15,00,000/- prior to filing of the complaint. Further, the outstanding amount of Rs. 25,00,000/- has been paid after obtaining of the occupation certificate and before taking possession. Hence, the complainant is entitled to interest under section 18 of the RERA Act, 2016 only on the amount of Rs.15,00,000/- with effect from 01.07.2024 till 23.10,2024. The impugned order is required to be clarified to this extent in order to bring clarity to the operative part of the impugned order. 


# 19. Accordingly, we pass the following order. 

ORDER 

  • 1. The captioned Appeal No.AT05/00276 of 2026 in complaint no. CC00500000047 L2B4 is dismissed. 

  • 2. The impugned order is confirmed. However, it is clarified that the respondent/complainant is entitled to interest under section 18 of the RERA Act, 2015 on account of delay in possession only on the amount of Rs.15,00,000/- with interest rate at the SBI's Highest Marginal Cost Lending Rate plus 2% from 01.07.2024 till 23.10.2024, which the promoter/appellant shall pay to the respondent/allottee within 30 days of this order, failing which the promoter shall pay further interest on the said amount outstanding as on 09.07.2026 with the same rate of interest as prescribed above till the amount is realized to the respondent/allottee. 

  • 3. In view of disposal of the appeal nothing survives for our consideration in Misc. Application No.294 of 2026 (Stay) and hence, same is also disposed of. 

  • 4. Parties to bear their own costs 

  • 5. Accordingly, the appeal stands disposed of in above terms. 

  • 6. Copy of this Order be communicated to the Authority and the respective parties as per Section 44(4) of RERA Act, 2016.

------------------------------------------------------------


Thursday, 18 June 2026

Vandana Garg, RP of Raguleela Builders Pvt. Ltd. Vs Mysore Petro Chemicals Ltd. - We consider that ideally, the appellant, as a resolution professional, even as he rejected the claim made by the respondent, still could have investigated and accepted the claim based on the original investment made by the respondent for the purchase of the commercial unit in lieu of the claim the respondent had made.

 NCLAT (2026.05.27)  in Vandana Garg, RP of Raguleela Builders Pvt. Ltd. Vs Mysore Petro Chemicals Ltd. [(2026) ibclaw.in 732 NCLAT, Company Appeal (AT) (Ins) No. 361 of 2024] held that;-

  •  “Section 14 of the IBC prescribes a moratorium on the initiation of CIRP proceedings and its effects. One of the purposes of the moratorium is to keep the assets of the corporate debtor together during the insolvency resolution process and to facilitate orderly completion of the processes envisaged under the statute.”

  • The judgement in ABG Shipyard case is set to the facts of that case, but what is significant is that Sec.14 does not permit or enable creation of any new liability against the corporate debtor from the date of commencement of CIRP, except those which are enabled by the Code to be treated as CIRP costs.

  •  If the case of the respondent is tested on the plane of this legislative philosophy on which Sec.14 of the Code is set, it would render ineffective the Order of the RERAA passed during the moratorium, creating a new liability on the CD. Necessarily, no claim based on the Order of the RERAA can be maintained.

  • We consider that ideally, the appellant, as a resolution professional, even as he rejected the claim made by the respondent, still could have investigated and accepted the claim based on the original investment made by the respondent for the purchase of the commercial unit in lieu of the claim the respondent had made.

Excerpts of the order;

This appeal is preferred by the Resolution Professional of the corporate debtor, in which he challenges the Order of the Adjudicating Authority dated 18.12.2023 allowing an application in I.A. 2725 of 2022 filed by the respondent herein for considering its claim of ₹ 5,20,22,000/- based on the Order of the Maharashtra Real Estate Regulatory Appellate Authority (for brevity would be referred to as RERAA). The RERAA has directed the CD to pay the respondent herein ₹5,20,22,000/-.


The Facts

# 2. The material facts are:

a) On 02.07.2015, the respondent had entered into an agreement for the purchase of a commercial unit with the CD. As per the agreement the unit was to be handed over to the respondent on 30.09.2015. The respondent has fully paid the consideration payable for the office unit to be purchased. The CD, however, did not deliver the unit as agreed upon.

b) The respondent, therefore, preferred a complaint with the RERA and vide its order dated 08.10.2020, the RERA dismissed the said complaint of the respondent. Challenging the said Order, on 17.12.2020, the respondent preferred an appeal to RERAA. Notice was ordered. According to the respondent, a notice was sent to the promoter of the project, the corporate debtor to be, through speed post, was served on it on 19.12.2020.

c) While the appeal preferred by the respondent was pending before the RERAA, CIRP commenced against the promoter of the project, vide the Order of the Adjudicatory Authority dated 04.10.2021. With that moratorium under Sec.14 of the Code came into force, IRP replaced the Board of the Corporate Debtor.

d) The IRP issued public notice inviting claims. The last date for preferring the claim was 05.11.2021. And the last date for filing belated claims in terms of Regulation 12 of the IBBI (CIRP) Regulations was 19.01.2022.

e) Be that as it may, on 30.06.2022, the RERAA allowed the appeal preferred by the respondent and directed the corporate debtor to pay a sum of. ₹5,28,22,000/- with interest at the rate of State Bank of India’s highest Marginal Cost Lending Rate plus 2% on the amount paid by the Respondent Company. On the following day, i.e., on 01.07.2022, the respondent e-mailed the appellant and informed them about the compensation ordered by the RERAA, and requested the appellant, the RP of the CD, to guide it to prefer the claim, and followed it with a reminder on 12.07.2022. Eventually, on 19.07.2022, the respondent preferred its claim in Form B.

f) The respondent, however, did not receive any information on the claim it had preferred, hence it moved the Adjudicating Authority with I.A.2725 of 2022 seeking a direction that its claim be considered. On 29.09.2022, the Adjudicating Authority passed an interim order and directed the appellant to consider the respondent’s claim.

g) Subsequent thereto, on 20.10.2022, the appellant rejected the claim of the appellant on two scores: (i) that the Order of the RERAA awarding compensation to the respondent was passed during the moratorium; and (b) that the claim was belated. (Regulation 13(1B) of the CIRP Regulation, enabling filing of claims till 7 days prior to the CoC voting on the resolution plan, came into effect only on 18.09.2023).


# 3. On 18.12.2023, the Adjudicating Authority has passed the final order in I.A.2725 of 2022 admitting the Claim of the respondent. It held: (i) that the respondent’s claim was not belated; and (ii) that the CD was bound by the judgement of the RERAA.


Arguments

# 4.1 The learned counsel for the appellant submitted:

a) The foundation of the claim of the respondent is an ex parte Order of the RERAA, dated 30.06.2022. However, this Order was passed after the moratorium was clamped under Sec.14 pursuant to the CD’s admission to CIRP vide the order of the Adjudicating Authority dated 04.10.2021. Law is settled vide the ratio in P. Mohanraj & Ors. v. Shah Brothers Ispat Pvt. Ltd. [(2021) ibclaw.in 24 SC] : [(2021) 6 SCC 258] and Real Estate Regulatory Authority Vs M/s D.B. Corp Ltd. [(2023) ibclaw.in 758 NCLAT] [CA (AT) (Ins) No. 1172- 1173 of 2022, dated 08.12.2023] where it has been held that any proceedings held during the period of moratorium is void and are incapable of creating enforceable rights.

b) If the Order passed initially by RERA is considered, it discloses that the respondent’s complaint has been the delay on the part of the CD in handing over possession of the office premises purchased. However, this complaint was dismissed by the RERA on 08.10.2020, on the ground that the delay in delivery was due to the delay in obtaining the Occupancy Certificate from the authorities. And, the agreement between the respondent and the CD provided for such a contingency, which binds the respondent herein, which the RERA had taken note of.

c) The next aspect is that on the admission of the CD to CIRP, the appellant duly issued a public notice through paper publication dated 21.10.2021 and invited claims from the creditors to be submitted by 05.11.2021. It was submitted that publication in newspapers in terms of Regulation 6 constituted a deemed notice to all creditors, including the respondent, terms of the dictum in M/s RPS Infrastructure Ltd. Vs Mukul Kumar & another [(2023) ibclaw.in 102 SC] : [(2023) 10 SCC 718]. But the appellant has filed its claim only on 19.07.2022 with a delay of about 198 days. By that time, the Information Memorandum had already been finalized and circulated to Prospective Resolution Applicants, and therefore entertaining such belated claims would derail the CIRP process.

d) Another aspect that flows directly from the effect of the public notice is that when the respondent has notice about the commencement of the CIRP and the moratorium on continuing with its appeal. However, the respondent not only suppressed the commencement of the CIRP but also continued serving notices on the erstwhile management of the CD instead of its Resolution Professional. Its effect is that the RP has been kept in the dark about the proceedings before the RERAA. This aspect has to be appreciated in the context of the fact that the erstwhile management of the CD has been least helpful in sharing the information and, the appellant was constrained to initiate a proceeding against them under Sec.19 IBC.

e) The appellant had acted with utmost diligence, hence no adverse inference can be drawn against him. Reliance was placed on M/s RPS Infrastructure (supra).


4.2 Concluding the arguments, the learned counsel submitted that the Adjudicating Authority, however, has erred in relying on the judgement in Power Grid Corporation of India Ltd. Vs Jyoti Structures Ltd. [(2017) ibclaw.in 12 HC] : [2017 SCC OnLine Del 12189 : (2018) 246 DLT 485] and disregarding the later judgment of the Hon’ble Supreme Court in P. Mohanraj case [(2021) 6 SCC 258]. In the process, the Adjudicating Authority has also overlooked the overriding effect of Sec.238 of the Code.


# 5. Per contra, the learned counsel for the respondent contended:

a) The respondent had instituted its appeal to the RERAA as early as December 2020, much prior to the commencement of CIRP against the Corporate Debtor on 04.10.2021. The notice of the appeal was duly served on the Corporate Debtor through multiple notices, e-mails, and reminders regarding the hearing dates were also issued. Despite such service, neither the corporate debtor nor the RP chose to appear before RERAA, therefore the CD is bound by the judgment dated 30.06.2022 passed therein.

b) On the aspect that the Order of the RERAA, as it was passed during the subsistence of moratorium, in ABG Shipyard Liquidator Vs Central Board of Indirect Taxes & Customs [(2022) ibclaw.in 103 SC]: [(2023) 1 SCC 472], the Hon’ble Supreme Court has held that any adjudicatory proceedings may continue during moratorium and that only recovery is prohibited. Therefore, the order passed by the RERAA is valid and binding upon the Corporate Debtor as well as the RP.

c) So far as the allegation that the claim was preferred belatedly is concerned, the respondent could not have filed its claim prior to the adjudication of the proceedings before the RERAA, since the claim crystallised only upon the order dated 30.06.2022 directing payment of interest to the Respondent. Immediately thereafter, the Respondent informed the RP by email dated 01.07.2022 and sought guidance for filing its claim under the Code, and subsequently filed its claim in Form B on 19.07.2022 at the earliest possible opportunity. Hence, there was no delay attributable to the Respondent in lodging its claim.

d) At any rate, Sections 18, 25 and 29 of the IBC read with Regulation 36 of the CIRP Regulations create a statutory obligation on the IRP or the RP, as the case may be, to collect and collate all claims against the corporate debtor and to keep itself apprised of all pending litigation involving the CD. The Information Memorandum was also required to disclose all material litigation and disputes concerning the CD. Consequently, the RP cannot evade its statutory responsibility by contending that it lacked information regarding the proceedings before RERAA. Indeed, these provisions taken along with Regulation 14(2) statutorily obligate an IRP or a RP to revise admitted claims whenever additional information comes to light. It was submitted that the CIRP framework itself contemplates revision and up-dation of claims during the CIRP process, therefore rejection of the Respondent’s claim solely on the ground of delay is contrary to the scheme of the Code and Regulations.

e) At any rate, the timeline fixed for collation of claims is only directory as held in State Tax Officer Vs Rainbow Papers Limited [(2022) ibclaw.in 107 SC]: [(2023) 9 SCC 545] and hence, claims cannot be rejected merely on account of delay where the resolution plan has not attained finality. Indeed, where a claim is discernible from the records of the corporate debtor, and the resolution plan has not been approved, then a delay in submitting the claim cannot be held against the creditor of the corporate debtor.

f) So far as the application of Sec.238 of the Code goes, in Pioneer Urban Land and Infrastructure Ltd. Vs Union of India [(2019) ibclaw.in 13 SC] : [AIR 2019 SC 4055], it is held that the remedies under the RERAA and the IBC are concurrent and complementary in nature, and hence there exists no inconsistency warranting the invocation of Section 238 of the Code.

g) The appellant did not challenge the interim Order of the Adjudicating Authority, dated 29.09.2022, and had considered the Claim. Having considered the claim, which, according to the appellant, was preferred belatedly, the argument that the claim was belatedly filed loses much of its sheen. Indeed, the appellant is estopped from contending about the delay in preferring the claim.


Discussion & Decision

# 6.1 The core issue, which is critical to the outcome of this appeal, is about the maintainability of the Claim, which undisputably is founded on an Order of the RERAA passed during the operation of the moratorium. It instantly relegates the alleged failure of the respondent to notify the appellant about the pendency of its appeal before the RERAA to insignificance. After all, even if the RP had been notified about the appeal, given the fact that Sec.14(1)(a) of the code prohibits ‘the continuation of pending suits or proceedings against the corporate debtor including execution of the judgement, decree or order in any court of law, tribunal or beneficial interest therein”, the Order of the RERAA will necessarily come under the scanner of the Code. The idea behind moratorium, as contemplated under Sec.14, is to freeze the assets and liabilities of the CD during CIRP for optimizing the value of the assets of CD to enable a successful resolution process and pay off the liabilities of the CD out of the proceeds of the resolution process in the manner contemplated under Sec.53 of the Code. In ABG shipyard case [(2023) 1 SCC 472], the Hon’ble Supreme Court has observed (paragraph 38), “Section 14 of the IBC prescribes a moratorium on the initiation of CIRP proceedings and its effects. One of the purposes of the moratorium is to keep the assets of the corporate debtor together during the insolvency resolution process and to facilitate orderly completion of the processes envisaged under the statute.


6.2 Turning to the effect of the moratorium in P. Mohanraj case [(2021) 6 SCC 258], the Supreme Court has held that the moratorium operates absolutely on all pending suits or proceedings (though the Court drew a distinction between suit and proceedings) and they will come to a standstill. This view was later followed in Anjali Rathi & Others Vs Today Homes & Infrastructure Pvt., Ltd., & others [(2021) ibclaw.in 152 SC] : [(2021 SCC OnLine SC 729]. However, the respondent has contended that the Order of the RERAA is not invalidated in terms of the dictum in ABG Shipyard case [(2023)1 SCC 472]. In that case, the Supreme Court has held that while the Customs Officials may assess or determine the quantum of customs duty payable by the CD during the period of moratorium, it may not still be permissible for it to take steps to recover the same during moratorium, and that issuance of any demand notices during the subsistence of moratorium is hit by Sec.14 of the Code. The judgement in ABG Shipyard case is set to the facts of that case, but what is significant is that Sec.14 does not permit or enable creation of any new liability against the corporate debtor from the date of commencement of CIRP, except those which are enabled by the Code to be treated as CIRP costs.


6.3 If the case of the respondent is tested on the plane of this legislative philosophy on which Sec.14 of the Code is set, it would render ineffective the Order of the RERAA passed during the moratorium, creating a new liability on the CD. Necessarily, no claim based on the Order of the RERAA can be maintained.


# 7. If the claim is not maintainable, then it does not matter whether it is filed within time or belated. Therefore, we do not propose to deal with that issue.


# 8. Having stated thus, there is another angle to the issue of the respondent’s entitlement to a claim. Admittedly, the respondent invested in a built-up commercial space and claims to have paid the entire sale consideration of ₹12,93,60,000/-. If the RP has replaced the Board of the CD, and if he is aware of the projects that the CD had undertaken, then it will not be difficult for the resolution professional to ascertain and identify the allottees and the amounts they had paid. It may be that when, on 21.10.2021, the RP issued a public notice in terms of Sec.15, Regulation 6A of the IBBI(CIRP) Regulations was not there, but when the RP is required to prepare a list of assets and liabilities of the CD in discharge of his duty under Sec.18(1), will it not be appropriate for him to include investments innocently and bona fide made even though they may not have preferred a claim? On going through the reply of the RP to the application of the respondent herein before the Adjudicating authority, he has not disputed the claim of allotment made to the respondent. Indeed, the fact that RERA and RERAA have considered the complaint of the respondent establishes that an allotment indeed has been made by the corporate debtor. In our opinion, RP should have realized that IBC is neither designed as a statute for the divestiture of individual rights, nor is it fashioned as an expropriatory statute. On the other hand, IBC is keen to recognize every right to claim a debt, which it defines as debt, even though it holds no promise to any creditor that the debt due to him will be paid. Here we are at the point of recognizing the right of the respondent at least to the money it has invested for the purchase of a commercial unit from the Corporate Debtor. In that sense, a claim is but a notice to the resolution professional that the corporate debtor is liable to repay a debt to a certain creditor. But if that debt could be ascertained without a formal claim, would it not be appropriate and fair for the RP to ascertain the same and seek the one to whom the debt is due from the corporate debtor? We consider that ideally, the appellant, as a resolution professional, even as he rejected the claim made by the respondent, still could have investigated and accepted the claim based on the original investment made by the respondent for the purchase of the commercial unit in lieu of the claim the respondent had made.


# 9. In conclusion, we dispose of the appeal with a direction to the resolution professional to verify if the respondent had made any payment of consideration to the corporate debtor as claimed by it and to include its claim.

-------------------------------------------------------------