Tuesday, 24 November 2026

Ravi Kumar Jangra & Anr. v. Union of India & Ors. - In our considered opinion, it is the bounden duty of the competent Court to first determine the nexus between the builder and the Bank authorities and examine whether the Bank disbursed the loan amount to the builder strictly in terms of the Tripartite Agreement. Unless a categorical finding is returned that the home buyers are in default, no interim direction regarding payment of installments can be issued against them. We, therefore, direct the Civil Court to not take any coercive action against the petitioners or similarly placed home buyers without first deciding the abovementioned issue.

 SCI (2026.11.19) in Ravi Kumar Jangra & Anr. v. Union of India & Ors. [Writ Petition (Civil) No. 1415 of 2026] held that; 

  • In our considered opinion, it is the bounden duty of the competent Court to first determine the nexus between the builder and the Bank authorities and examine whether the Bank disbursed the loan amount to the builder strictly in terms of the Tripartite Agreement. Unless a categorical finding is returned that the home buyers are in default, no interim direction regarding payment of installments can be issued against them. We, therefore, direct the Civil Court to not take any coercive action against the petitioners or similarly placed home buyers without first deciding the abovementioned issue.


Excerpts of the order;

# 1. The petitioners are home buyers in a project known as ‘Krishna Housing Scheme’, situated at Sector-14, Sohna, Gurugram. The project was launched by respondent No. 4, M/s Raheja Developers Limited private builder-cum-developer.


# 2. It appears that a Tripartite Agreement was executed between the petitioners, the State Bank of India and respondent No. 4 regarding housing loans availed by the petitioners. It is alleged that the builder-cum-developer failed to honor its commitment as per the Tripartite Agreement. Although, the disbursement of the loan was linked to construction progress, the Bank appears to have made payment to the builder without any corresponding progress in the construction. Meanwhile, respondent No. 4, builder-cumdeveloper was admitted into CIRP by the National Company Law Tribunal (for short, “NCLT”) on 21.08.2025. In CIRP proceedings, the builder-cum-developer had proposed to refund the amount deposited by home buyers in six monthly installments. 


# 3. Pending above proceedings, the State Bank of India filed recovery suits against the Petitioner-home buyers before Commercial Court, Saket Courts, New Delhi. Consequently, certain ad-interim directions were issued by the Civil Court regarding payment of installments by the petitioners to the State Bank of India. 


# 4. In our considered opinion, it is the bounden duty of the competent Court to first determine the nexus between the builder and the Bank authorities and examine whether the Bank disbursed the loan amount to the builder strictly in terms of the Tripartite Agreement. Unless a categorical finding is returned that the home buyers are in default, no interim direction regarding payment of installments can be issued against them. We, therefore, direct the Civil Court to not take any coercive action against the petitioners or similarly placed home buyers without first deciding the abovementioned issue.


# 5. It is clarified that we have not expressed any opinion on merits of the case and only an ad-interim protection has been granted to the home buyers against coercive means. All the issues pending before the NCLT/NCLAT and/or the Commercial Court shall be decided notwithstanding the observations made hereinabove and in accordance with law. The Commercial Court shall be at liberty to  modify the interim order/directions already issued by it after hearing the parties.


# 6. The Writ Petition stands disposed of, in the above terms.

# 7. Pending application(s), if any, shall stand closed.


----------------------------------------


Monday, 23 November 2026

Navneet Kumar Gupta Vs. Ansal Properties and Infrastructure Limited - In view of the foregoing considerations, we are of the view that the projects and assets situated in Uttar Pradesh and those situated in Rajasthan should be dealt with separately for the purposes of the resolution process. Accordingly, the resolution process in respect of the specified projects and assets situated in Uttar Pradesh shall be administered separately from the resolution process in respect of the specified assets situated in Rajasthan.

 NCLT ND-IV (2026.11.19) in Navneet Kumar Gupta Vs. Ansal Properties and Infrastructure Limited [I.A 131 ND 2026 IN C.P. IB 558 (ND) 2024] held that;

  • Constituting a separate CIRP and CoC for each project at this stage may lead to multiplicity of processes and practical difficulties in dealing with common assets, liabilities, infrastructure and inter-project transactions. The State-wise arrangement, while maintaining separate CoCs for the two geographical regions, would facilitate effective administration and accountability and would not preclude consideration of project-wise or group-wise resolution plans within each State, subject to the provisions of the Code and the applicable CIRP Regulations.

  •  In view of the foregoing considerations, we are of the view that the projects and assets situated in Uttar Pradesh and those situated in Rajasthan should be dealt with separately for the purposes of the resolution process.  Accordingly, the resolution process in respect of the specified projects and assets situated in Uttar Pradesh shall be administered separately from the resolution process in respect of the specified assets situated in Rajasthan.

Excerpts of the order;

# 1. The present Application has been filed by the Applicant under Rule 11 of the National Company Law Tribunal Rules, 2016 (“NCLT Rules, 2016”) seeking the following reliefs:

  • a. Allow the present Application;

  • b. Kindly take on record the Judgment / Order dated 07.01.2026 passed by the Hon'ble Appellate Tribunal in Company Appeal No. 502 of 2025 titled as "Pranav Ansal VS IL&FS Financial Services Limited and Company Appeal No. 500 of 2025 titled as "Gagan Tondon VS IL&FS Financial Services Limited":

  • c. Pass such other order(s) as may be deemed fit and proper in the facts and circumstances of the case.


# 2. The Financial Creditor, IL&FS Financial Services Limited, had filed an Application Company Petition bearing C.P. (IB) No. 558 of 2024 under Section 7 of the Insolvency and Bankruptcy Code, 2016 (hereinafter referred to as "Code") seeking initiation of CIRP against the Corporate Debtor, which was admitted by this Adjudicating Authority vide Order dated 25.02.2025 and Mr. Navneet Kumar Gupta i.e., Applicant herein was appointed as an Interim 

Resolution Professional of the Corporate Debtor and a moratorium under Section 14 of the Code came into force.


# 3. In the interim the suspended board of director qua the Corporate Debtor Mr. Pranav Bansal filed an appeal bearing Company Appeal No. 502 of 2025 titled as "Pranav Ansal VS IL&FS Financial Services Limited on 05.03.2025 and one Mr. Gagan Tandon on 20.03.2025 also filed an appeal bearing Company Appeal No. 500 of 2025 titled as "Gagan Tondon VS IL&FS Financial Services Limited ("Appeals") before the Hon'ble NCLAT assailing the order dated 25.02.2025 challenging the initiation of CIRP qua the Corporate Debtor.


# 4. Subsequently, the Hon'ble NCLAT vide order dated 25.04.2025 passed an interim order in favour of the Appellants and stayed the issuance of FORM-G qua the Corporate Debtor.


# 5. Thereafter, the Hon'ble NCLAT, vide its final judgment and order dated 07.01.2026, disposed of the aforesaid Appeals with specific directions, while upholding the admission of the Corporate Debtor into CIRP, subject to the directions contained therein. The said judgment/order dated 07.01.2026 has a direct bearing on the ongoing CIRP proceedings and is therefore being placed on record before this Adjudicating Authority for consideration.


# 6. The Hon’ble NCLAT vide order dated 07.01.2026 issued the following directions:

  • “100. In view of the foregoing facts, we dispose of both the Appeal(s) in following manner: 

  • (1) The order dated 25.02.2025 passed by National Company Law Tribunal, New Delhi Bench Court-IV admitting Section 7 application is upheld, subject to following directions:

  • (a) The CIRP against the CD is confined to CD's projects at Lucknow Mother City and Mother City Extension at Lucknow, Golf Plots at Lucknow and the assets of the CD in the State of Rajasthan and builtup properties at Ajmer, Jodhpur and Jaipur in the State of Rajasthan (as detailed in Schedule-B of Settlement Agreement dated 03.03.2022 at Sl. No.5, 6 & 7).

  • (b) The Adjudicating Authority to consider the mode and manner to proceed with project wise resolution of the CD as per initiation of CIRP against a real estate company to the extent as indicated above. 

  • (c) Further steps in the CIRP of the CD shall be taken as per directions of the Adjudicating Authority indicated above. The Adjudicating Authority shall also consider with respect to resolution of the CD's project at Lucknow, as to whether as per MoU and Development Agreements entered between the CD and Lucknow Development Authority, the Lucknow Development Authority is to be directed to complete the projects of the CD. 

  • (d) UP Awas Evam Vikas Parishad shall be entitled to pursue its application before the Adjudicating Authority for excluding the assets claimed by it, from the CIRP of the CD, which may be considered and decided in accordance with law.

  • (e) The date of commencement of the CIRP of the CD has to be treated as 25.02.2025 and further steps in the CIRP be taken as per the directions of the Adjudicating Authority to be made hereinafter.

  • (f) The Lucknow Development Authority be made party to the CIRP process and it be given opportunity to file its affidavit. 

  • (g) The Homebuyers and other Applicants, who have filed IAs in these Appeal(s) are at liberty to file Intervention Petitions before the Adjudicating Authority in C.P.(IB) 558(ND)/2024.


# 7. The Financial Creditor, IL&FS Financial Services Limited, which had filed C.P. (IB) No. 558/ND/2024, preferred Civil Appeal Nos. 807-808 of 2026, IL&FS Financial Services Ltd. v. Pranav Ansal & Ors., before the Hon'ble Supreme Court assailing the Judgment dated 07.01.2026 passed by the Hon'ble Appellate Tribunal. By Order dated 16.04.2026, the Hon'ble Supreme Court declined to interfere with the impugned Judgment and disposed of the Civil Appeals, while upholding the Order passed by Hon’ble NCLAT.


# 8. We have considered the submissions of the Resolution Professional pursuant to the order dated 08.10.2026 and have perused the judgment dated 07.01.2026 passed by the Hon’ble National Company Law Appellate Tribunal (NCLAT) in Company Appeal (AT) (Ins.) Nos. 500 and 502 of 2025, the subsequent clarification dated 25.05.2026 and the order dated 16.04.2026 passed by the Hon’ble Supreme Court.


# 9. We have perused the order dated 07.01.2026 by the Hon’ble NCLAT and the same is taken on record. As per the order of the Hon’ble NCLAT, this Adjudicating Authority is to pass an order regarding the mode and manner to proceed with the resolution of the Corporate Debtor as per initiation of CIRP against a real estate company. Therefore, by this order, we are passing order regarding the mode and manner of the CIRP.


# 10. The Hon’ble NCLAT, while upholding the admission of the Corporate Debtor into CIRP, confined the CIRP to the projects of the Corporate Debtor at Lucknow, including Mother City, Mother City Extension and Sushant Golf City, as well as the assets of the Corporate Debtor situated in Rajasthan, including the built-up properties at Ajmer, Jodhpur and Jaipur. The Hon’ble NCLAT has expressly left the mode and manner of resolution of these projects and assets to be determined by this Adjudicating Authority. It has further directed that the CIRP shall proceed with effect from the commencement date of 25.02.2025 and that the question of completion of the Lucknow projects by the Lucknow Development Authority (LDA), in terms of the relevant Memorandum of Understanding and Development Agreements, shall also be considered.


# 11. Vide order dated 08.10.2026 passed in I.A. 2711 ND 2026, the order dated 25.05.2026 passed by the Hon’ble NCLAT in IA/3559/ND/2026 in Company Appeal (AT) (Insolvency) No. 500 of 2025 was taken on record wherein it was clarified that in addition to the projects namely Mother City Lucknow and Mother City Extension Lucknow, the CIRP shall also extend to and remain confined to the Corporate Debtor's projects situated in Sushant Golf City as well as the assets of the Corporate Debtor in the State of Rajasthan.


# 12. The issue before us is, therefore, not whether the CIRP is to continue, as the admission order already stands upheld by the Hon’ble NCLAT and the Hon’ble Supreme Court has declined to interfere with the same. The question that arises for consideration is the mode and manner in which the CIRP is to be operationalised in respect of the projects and assets specifically identified by the Hon’ble NCLAT. The mechanism adopted must give effect to the aforesaid directions, facilitate value maximisation, protect the interests of the stakeholders and ensure that the CIRP progresses expeditiously in accordance with the provisions of the Code.


# 13. During the course of the proceedings, certain homebuyers filed I.A. 5159/ND/2026 seeking, inter alia, separate CIRPs and separate Committees of Creditors (CoCs) for each project of the Corporate Debtor. Vide order dated 28.10.2026, this Adjudicating Authority recorded the submission of the learned Counsel appearing on behalf of the applicants. The applicants contended that a project-wise CIRP and separate CoCs for each project were necessary to safeguard the interests of homebuyers associated with different projects. Having considered the said submission, this Adjudicating Authority observed that the issue regarding the mode and manner of the CIRP raised by the Applicant, including the request for separate project-wise CIRPs and CoCs, would be considered while deciding the present Application.


# 14. The Hon’ble NCLAT, vide its judgment dated 07.01.2026, confined the CIRP to the specified projects of the Corporate Debtor situated in the State of Uttar Pradesh, namely, Mother City, Mother City Extension and the projects situated in Sushant Golf City, Lucknow, together with the assets of the Corporate Debtor situated in the State of Rajasthan, including the built-up properties at Ajmer, Jodhpur and Jaipur. Thus, the assets falling within the scope of the CIRP are situated in two distinct geographical regions, namely, Uttar Pradesh and Rajasthan. The nature and location of these assets, the separate project requirements and the need for effective coordination with the respective local authorities warrant consideration while determining the appropriate mechanism for resolution.


# 15. We are of the considered view that administering all the aforesaid projects and assets through a single CIRP and a common Resolution Professional may give rise to practical difficulties in the identification and segregation of projectspecific assets and liabilities, determination of the claims attributable to each geographical region, management of project-specific funds and formulation and implementation of viable resolution proposals. Further, a common Committee of Creditors (CoC), comprising stakeholders whose interests may be confined to different projects and geographical regions, may complicate the determination of voting shares and the assessment of resolution proposals in relation to the respective projects and assets. These considerations assume particular significance in the present case, wherein the scope of the CIRP has expressly been restricted by the Hon’ble NCLAT to specified projects and assets, rather than the entire Corporate Debtor as a whole.


# 16. The geographical separation of the assets between Uttar Pradesh and Rajasthan, coupled with the need for independent project-wise assessment, effective supervision and accountability, constitutes a relevant consideration in determining the mode and manner of resolution. A separate Resolution Professional for each region would facilitate the identification and management of the assets situated therein, verification of the claims and liabilities attributable to the respective projects, maintenance of appropriate financial records and coordination with the concerned authorities and stakeholders. It would also facilitate the formulation and consideration of resolution proposals suited to the particular circumstances of the projects and assets falling within each region. We have also considered the concerns raised by the homebuyers in I.A 5159 of 2026. Constituting a separate CIRP and CoC for each project at this stage may lead to multiplicity of processes and practical difficulties in dealing with common assets, liabilities, infrastructure and inter-project transactions. The State-wise arrangement, while maintaining separate CoCs for the two geographical regions, would facilitate effective administration and accountability and would not preclude consideration of project-wise or group-wise resolution plans within each State, subject to the provisions of the Code and the applicable CIRP Regulations.


# 17. In view of the foregoing considerations, we are of the view that the projects and assets situated in Uttar Pradesh and those situated in Rajasthan should be dealt with separately for the purposes of the resolution process.  Accordingly, the resolution process in respect of the specified projects and assets situated in Uttar Pradesh shall be administered separately from the resolution process in respect of the specified assets situated in Rajasthan. For this purpose, a separate Resolution Professional shall be appointed for each of the two processes. We hereby appoint the following Resolution Professionals:


A. Rajasthan: For projects in Rajasthan, we retain the present Resolution Professional to discharge functions in accordance with the Code and Regulations thereunder. The details of the Resolution Professional are as follows:

Name: Mr. Navneet Kumar Gupta

Registration No. : IBBI/IPA-001/IP-P00001/2016-2017/10009

E-mail : navneet[at]minervaresolutions[dot]com


B. Uttar Pradesh: For projects situated in Uttar Pradesh, we hereby appoint Mr. Surendra Raj Gang as the Resolution Professional to discharge function in accordance with the Code and Regulation thereunder. The details of the Resolution Professional are as follows:

Name: Mr. Surendra Raj Gang

Registration No. : IBBI/IPA-001/IP-P01066/2017-2018/11773

E-mail : surendra[dot]Raj[at]in[dot]gt[dot]com


The RP so appointed shall file consent in Form-2, a valid AFA and  disclosure about non-initiation of any disciplinary proceedings against him, within three working days (3) of pronouncement of this order. 


# 18. Each Resolution Professional shall be responsible for the identification, verification and management of the assets and liabilities falling within the respective geographical scope, as well as for undertaking the steps necessary for resolution in accordance with law.


# 19. The first resolution process shall be confined to the Corporate Debtor’s projects situated in Uttar Pradesh, namely, Mother City, Mother City Extension including projects situated in Sushant Golf City, Lucknow, together with the assets and liabilities attributable to those projects. The second resolution process shall be confined to the assets of the Corporate Debtor situated in Rajasthan, including the built-up properties at Ajmer, Jodhpur and Jaipur, as specified at Serial Nos. 5, 6 and 7 of Schedule-B to the Settlement Agreement dated 03.03.2022. Neither process shall extend to any other project, asset or undertaking of the Corporate Debtor beyond the scope identified by the Hon’ble NCLAT.


# 20. For implementing the aforesaid arrangement, the existing Resolution Professional shall cooperate in the transition and hand over the relevant records, claims, financial information and project-specific particulars of the Projects in Uttar Pradesh to the Resolution Professional appointed for Uttar Pradesh within 4 weeks from the date of pronouncement of this order.


# 21. In addition to the aforesaid arrangement, we deem it appropriate to appoint one common Supervisor for both the resolution processes to ensure effective coordination, monitoring and uniformity in the administration of the two processes. The Supervisor shall oversee the functioning of both Resolution Professionals, monitor the progress of the respective resolution processes and facilitate coordination between them, wherever required, without interfering with their independent statutory functions and responsibilities under the Code and the Regulations framed thereunder. 


# 22. The remuneration of the Ld. Supervisor shall be fixed at Rs. 2,00,000/- (Rupees Two Lakhs only) per month, along with reimbursement of other expenses incurred in the discharge of his duties on an actual basis. The aforesaid remuneration and expenses shall be borne and paid by the Committee of Creditors (CoC) constituted in respect of the Uttar Pradesh projects. Both Resolution Professionals shall extend full cooperation and provide such information and assistance as may be required by the Ld. Supervisor. The Ld. Supervisor shall file a consolidated progress report before this Adjudicating Authority every 90 days. We hereby appoint the following to supervise the 2 Resolution Processes:


Name: Mr. Mukul Singhal

E-mail: mukulsinghal2@gmail.com

Contact No. : 8765179988

The Ld. Supervisor shall file his consent within 3 working days from the date of pronouncement of this order.


# 23. The Resolution Professionals shall prepare and file before this Adjudicating Authority a comprehensive project-wise assessment of the assets, liabilities and financial affairs attributable to the projects and assets falling within the scope of the CIRP in which they are appointed. The assessment shall include details of movable and immovable assets, project-wise liabilities and admitted claims, receivables, loans and borrowings, securities and encumbrances, bank accounts and balances, funds received and utilised, and any interproject transfers or common expenses. Wherever any asset, liability, fund, receivable or expenditure pertains to more than one project or cannot be directly attributed to a particular project, the Resolution Professional shall identify the same and provide a reasoned pro rata allocation, specifying the basis and methodology adopted.


# 24. The Resolution Professionals shall also identify common infrastructure, shared resources and cross-collateralisation of assets, wherever applicable, and clearly distinguish project-specific assets and liabilities from those which are common to multiple projects. The assessment shall be supported by relevant records and documents and shall provide a clear account of the assets and liabilities attributable to the respective geographical regions. The aforesaid assessment shall be filed by way of an affidavit within 4 weeks from the transition and handover as mentioned in Para 20 of this order. The Resolution Professionals shall not, merely by reason of the proposed geographical segregation, transfer, appropriate or exclude any asset or liability without due verification and compliance with the applicable provisions of law.


# 25. In order to have clarity, it is stated that there would be 2 CoCs i.e. one for the UP Projects and one for the Rajasthan Projects. The existence of different CoCs (one for UP and one for Rajasthan) does not preclude consideration of separate resolution plans for individual projects or groups of projects within each state. The Resolution Professionals appointed for the respective resolution processes are directed to verify and collate the claims of the creditors pertaining to the projects and assets falling within their respective jurisdictions and constitute  the CoCs for the respective processes in accordance with the provisions of the Code and the applicable CIRP Regulations. The respective Resolution Professionals shall conduct the CIRPs in accordance with the provisions of the Code and the applicable CIRP Regulations. The RP and the CoC of both processes may consider a composite plan or project-wise/group-wise plans in accordance with the Code and the applicable CIRP Regulations, including Regulation 36A.


# 26. In the event any Resolution Professional identifies any asset, liability, receivable, bank account or transaction that appears to have been incorrectly included within or excluded from the scope of the respective CIRPs, the RP shall place the relevant particulars before this Adjudicating Authority and seek appropriate directions before taking any consequential action.


# 27. The question concerning the take-over of the Lucknow projects by the Lucknow Development Authority (LDA) form subject matter of in I.A. 4747/2026 filed by LDA and therefore shall be considered separately in I.A. 747/2026, after affording an opportunity of hearing to the LDA, the RP and  other concerned parties. No final opinion is expressed on the merits of the issue at this stage.


# 28. The RPs shall proceed with the CIRP expeditiously and in accordance with the directions of the Hon’ble Supreme Court and the Hon’ble NCLAT, as well as the applicable provisions of the Code and the CIRP Regulations. 


# 29. The application filed by the Uttar Pradesh Awas Evam Vikas Parishad (UPAVP), if any, seeking exclusion of the assets claimed by it from the scope  of the CIRP shall be considered separately in accordance with the directions of the Hon’ble NCLAT and provisions of law.


# 30. A copy of the order shall be communicated to the Resolution Professionals and the Ld. Supervisor above named, by the Registry.


# 31. In addition, a copy of the order shall also be forwarded to IBBI for its records. 

# 32. The present Application bearing I.A. 131 ND 2026 is disposed of in the above Terms.

------------------------------------------------


Thursday, 19 November 2026

P.Patel vs The Karnataka Real Estate Regulatory Authority & Ors. - we are of the considered view that this Tribunal, in an appropriate case, is competent to issue necessary directions to protect an allottee from adverse consequences affecting his creditworthiness and CIBIL score arising out of disputes emanating from a real estate transaction of this nature.

 REAT Karnataka (2026.11.03) in P.Patel vs The Karnataka Real Estate Regulatory Authority & Ors.  [APPEAL No.(K-REAT) 41/2025] held that; 

  • Having regard to the powers conferred upon this Tribunal under sub-sections (3) and (6) of Section 44 of the Act, we are of the considered view that this Tribunal is competent to suitably mould the relief, provided that such exercise does not introduce an altogether new cause of action or occasion prejudice to the opposite party.

  • The manner in which the third respondent is resisting the present appeal makes it abundantly clear that, taking undue advantage of the terms of the tripartite agreement, it is making every endeavour to exert pressure upon the allottee to repay the entire loan amount, notwithstanding the fact that the allottee has not derived any benefit whatsoever from the loan proceeds, which were disbursed for the benefit of the second respondent/promoter.

  • we are of the considered view that this Tribunal, in an appropriate case, is competent to issue necessary directions to protect an allottee from adverse consequences affecting his creditworthiness and CIBIL score arising out of disputes emanating from a real estate transaction of this nature.


Excerpts of the order;

The facts leading to this appeal, in brief, are as follows:

The appellant, hereinafter referred to as the ‘allottee’ for the  sake of convenience, had booked two flats bearing Nos. C- 1209 and C-1309 in the project known as ‘Aloha’, developed by the second respondent-promoter and entered into an Agreement to Sell dated 11.04.2018 for a total sale consideration of Rs.1,70,59,584/-, pursuant to which he paid an advance amount of Rs.37,00,000/-. The promoter persuaded the allottee to approach the third respondent for availing a home loan to meet the balance sale consideration. Accordingly, on 28.11.2018, the allottee, the second respondent-promoter and the third respondent entered into a Tripartite Agreement in respect of the aforesaid flats. Upon sanction of the loan, the third respondent disbursed a sum of Rs.1,13,80,672/- directly to the promoter. Thus, the allottee claims to have paid a total sum of Rs.1,50,80,672/- towards the sale consideration. As per the Agreement to Sell, the promoter had undertaken to execute and register the sale deeds in favour of the allottee and hand over possession of the flats, along with the occupancy certificate, on or before 30.09.2018. However, the promoter failed to honour the contractual obligations and continued to defer the execution and registration of the sale deeds as well as the delivery of possession. It is the specific grievance of the allottee that, despite having received a substantial portion of the sale consideration, the promoter proceeded to sell the very same flats to third parties. It is further contended that, while sanctioning the home loan, the third respondent had stipulated that only  pre-EMI interest would be payable until the registration of the flats and that the regular EMI, involving repayment of the principal amount, would commence only thereafter. Since the sale deeds have not been executed and registered till date, the third respondent has continued to levy monthly pre-EMI interest of Rs.82,561/-, without any corresponding reduction in the principal loan amount, thereby causing substantial and recurring financial loss to the allottee. Aggrieved by the aforesaid acts and omissions of the promoter, the allottee initially approached the first respondent-Authority seeking a direction to the promoter to execute and register the sale deeds in respect of the two flats in his favour. Subsequently, however, he amended the relief sought in the complaint and sought refund of the amount paid, together with interest.


# 2. Despite service of summons, respondents Nos. 2 and 3 failed to appear before the Authority and contest the complaint. Upon hearing the allottee, the Authority allowed the complaint and directed the promoter to refund a sum of Rs.63,42,993/- to the allottee, together with interest calculated at the rate of SBI MCLR plus 2% per annum from 11.04.2018 to 12.03.2025, within sixty days from the date of the order. It was further directed that the interest accruing from 13.03.2025 till the date of actual payment shall also be calculated at the same rate and paid to the allottee. In addition thereto, the promoter was directed to foreclose the outstanding loan liability of the allottee with respondent No.3 in Loan Account No.632107789, by clearing the entire outstanding amount, including all pending EMIs, interest, penalties and other charges, and thereafter obtain and furnish a No Objection Certificate to the allottee.


# 3. Being aggrieved by the impugned order dated 19.03.2025, the allottee has preferred the present appeal seeking modification of the same, contending that the Authority, while partly allowing the complaint, failed to consider the reliefs sought and properly appreciate the evidence placed on record regarding the alleged violations of the RERA Act and the Tripartite Agreement by respondents No.2 and 3. It is further contended that, despite the promoter’s failure to fulfill its contractual and statutory obligations, respondents No.2 and 3 have resorted to coercive recovery measures against the allottee and reported him as a defaulter to CIBIL, thereby adversely affecting his credit worthiness for no fault of his. According to the allottee, notwithstanding the specific directions issued by the Authority, the third respondent, instead of seeking recovery of the outstanding loan amount from the promoter, has continued to demand repayment from the allottee in respect of the very same flats which the promoter had allegedly sold to third parties. It is further contended that, despite the impugned order and repeated communications addressed by the allottee, the promoter has neither foreclosed the outstanding loan liability nor issued the requisite No Objection Certificate and has continued to demand payment, while the third respondent has failed to acknowledge or act upon the directions issued by the Authority and has continued to threaten adverse consequences to the allottee’s credit score. Hence, the allottee has sought modification of the impugned order by issuing appropriate directions to the third respondent to recover the outstanding loan amount from the promoter, desist from initiating any coercive recovery proceedings against the allottee, refrain from reporting any alleged default by the allottee in respect of Loan Account No.632107789 to CIBIL or any other credit information agency and ensure that his credit score is not adversely affected in any manner in connection with the said loan account.


# 4. In response to the notice issued by this Tribunal, respondents No.2 and 3 entered appearance through their respective counsel and respondent No.3 filed its statement  of objections contending that the allottee has no valid rounds to maintain the present appeal and has not  approached this Tribunal with clean hands. It is contended that the scope of appellate proceedings under the RERA Act is limited and cannot be misutilised to seek an altogether different or expanded relief by way of modification of the impugned order. The Authority has not recorded any adverse finding against respondent No.3 nor fastened any liability or issued any operative direction against it; on the contrary, the Authority has consciously directed only the promoter to refund the amount paid by the allottee, together with interest and other consequential reliefs. In the absence of any such direction against respondent No.3, the allottee cannot seek modification of the impugned order so as to impose fresh and independent obligations upon it. It is further contended that appellate proceedings cannot be utilised to seek reliefs which were neither sought before nor adjudicated upon by the original Authority. The provisions of the RERA Act do not contemplate adjudication of disputes between a borrower and a lending financial institution concerning repayment of loans, recovery proceedings or credit reporting, nor does this Tribunal possess jurisdiction to issue mandatory, prohibitory or coercive directions against a financial institution in matters governed by separate banking and regulatory enactments. Respondent No.3, being a financial institution, does not fall within the category of entities regulated under the RERA Act and consequently, no relief can be sought or granted against it under the said enactment. It is further contended that, instead of initiating appropriate execution proceedings against the promoter for enforcement of the impugned order, the allottee has improperly attempted to shift the burden of recovery upon respondent No.3, which is wholly impermissible. The allottee is admittedly a borrower under a valid and subsisting loan agreement and has unilaterally discontinued payment of the EMIs, thereby committing a breach of his contractual obligations, which cannot absolve him of his liability to repay the loan. There is no contractual or statutory obligation cast upon respondent No. 3 to supervise the construction, monitor the progress of the project, ensure its completion or guarantee delivery of possession of the flats, as the role and responsibilities of a ending financial institution are entirely distinct from those of a promoter or developer. The allottee cannot, under the guise of seeking modification of the impugned order, compel respondent No.3 to recover the outstanding loan amount from the promoter or restrain it from initiating lawful recovery proceedings against the borrower. On the aforesaid grounds, respondent No.3 has sought dismissal of the appeal.


# 5. We have heard the arguments advanced by the learned counsel appearing for the allottee and respondent No. 3. Despite granting sufficient opportunity, the learned counsel appearing for the promoter failed to address arguments on behalf of the promoter. Accordingly, the arguments of the learned counsel for the allottee and respondent No. 3 have been considered, and the matter is taken up for consideration on the basis of the pleadings and materials available on record.


# 6. In view of the rival contentions advanced by the parties and upon perusal of the pleadings and material available on record, the following points arise for our consideration:

  • 1. Whether the Allottee proves that the impugned order passed by the Authority warrants interference and modification by granting the ancillary reliefs sought for in the appeal?

  • 2. What order?


# 7. Our findings on the above points are as under: 

  • Point No.1 : In the Affirmative

  • Point No.2 : As per final order, for the following:


REASONS

# 8.Point No.1: Before proceeding to evaluate the point in controversy, it would be expedient to recapitulate certain undisputed facts. A perusal of the pleadings, the impugned order and the records secured from the office of the Authority would reveal that the allottee, with the intention of purchasing two flats bearing Nos.C-1209 and C-1309 for valuable consideration, entered into an Agreement to Sell with the promoter on 11.04.2018, agreeing to pay a total  sale consideration of Rs.1,70,59,584/-. Pursuant thereto, he paid a sum of Rs.37,00,000/- towards his own contribution. In respect of the remaining sale consideration, at the instance of the promoter, the allottee entered into a Tripartite Agreement with the promoter and the third respondent-financier on 28.11.2018. Pursuant to the said Tripartite Agreement, the third respondent disbursed a sum of Rs.1,13,80,672/- to the promoter, who thereby received an aggregate amount of Rs.1,50,80,672/- towards the sale consideration. As per the terms of the Agreement to Sell, the promoter was obligated to execute the sale deeds in favour of the allottee on or before 30.09.2018. However, having failed to fulfill the contractual obligation within the stipulated period, the allottee approached the Authority by filing a complaint seeking a direction to the promoter to execute the sale deeds in respect of the aforesaid flats in his favour in accordance with the terms of the Agreement to Sell. In the meanwhile, it came to the knowledge of the allottee that the promoter, with an intention to defeat his legitimate rights and  defraud him, had alienated the very same flats in favour of Mrs.Dharavath Laxmi Banjara and Sri.Algond K.Biradar under two separate sale deeds dated 08.12.2021 and 19.02.2022 respectively. In view of the subsequent developments and the impossibility of securing the originally sought relief, the allottee sought modification of the reliefs claimed in the complaint and consequently prayed for refund of the amount paid by him, together with interest thereon.


# 9. Initially, the third respondent was not arrayed as a party to the proceedings before the Authority and was subsequently impleaded as respondent No.2. However, for the reasons best known to them, neither the promoter nor the financier chose to appear before the Authority or contest the claim made by the allottee. Consequently, the Authority, placing reliance upon the assertions made by the allottee, the memo of calculation furnished by him and the principles laid down by the High Court of Delhi in Ashish Tiwari Vs. Union of India [(WP(C) 10223/2021] and by the Hon’ble Apex   Court in Union of India Vs. Rajasthan Real Estate Regulatory Authority and Others [2022 liveLaw (SC) 171] and Bikram Chatterji Vs. Union of India and Others [(2019) 19 SCC 161], proceeded to allow the complaint. Accordingly, the promoter was directed to refund the amount received towards the sale consideration from the allottee, together with interest thereon at the rate of SBI MCLR plus 2%, calculated from the respective dates of payment until the date of actual realisation. 


# 10. Even after disposal of the complaint, the allottee appears to have been confronted with further difficulties, in as much as the third respondent, allegedly taking undue advantage of the terms and conditions of the Tripartite Agreement executed between the parties, has been making coercive attempts to compel him to repay the loan amount, notwithstanding the fact that the loan proceeds were neither received nor utilised by the allottee but were disbursed directly for the benefit of the promoter. The allottee further apprehends that such coercive measures may adversely affect his creditworthiness and consequently impair his CIBIL score, thereby exposing him to further prejudice and financial hardship.


# 11. Aggrieved by the aforesaid circumstances and reiterating the difficulties being faced by him, the allottee has preferred the present appeal seeking modification of the impugned order and consequential directions to the third respondent to recover the outstanding loan amount from the promoter, who is the actual beneficiary of the loan proceeds and to desist from initiating or continuing any coercive recovery measures against him, including reporting him as a defaulter to the credit information agencies. He has further sought a direction to the third respondent not to report his loan account as a default account or take any steps that would adversely affect his creditworthiness or CIBIL score in any manner whatsoever. In support of the reliefs sought in the present appeal, the learned counsel appearing for the allottee placed reliance upon the decision of the Hon’ble Apex Court in Himanshu Singh and Others Vs. Union of India and Others [2025 LiveLaw (SC) 574]. The sum and substance of the principles laid down in the said decision may be summarised as follows:

  • “Tripartite Agreement – Subvention scheme – Home buyers alleged collusion between builders, banks, and Housing Finance Companies (HFCs) in subvention schemes, where builders promised to pay EMIs until possession but defaulted, leaving buyers liable for EMIs despite incomplete projects. Held a prima facie “unholy nexus” existed between builders, banks and HFCs, indicating a systematic failure by statutory and government authorities to perform their duties. The Court noted circumvention of the regulatory framework by banks and HFCs, with coercive actions taken against homebuyers despite incomplete units and no valid offer of possession.”


# 12. Further, the learned counsel for the allottee placed reliance upon the decision of the Hon’ble High Court of Karnataka in Mudit Saxena Vs. Union of India [ (2023) 2 KCCR 1296]. In the said decision, the High Court dealt with the issue of coercive recovery of housing loan dues by PNB Housing Finance Limited in transactions involving Tripartite Agreements executed between home buyers and developers. The Court, while examining the circumstances surrounding such transactions, restrained coercive recovery measures and issued appropriate directions to the concerned authorities to consider the claims relating to correction of the CIBIL score and issuance of a No Due Certificate. Placing reliance upon the aforesaid decision, the learned counsel contended that the third respondent/financier cannot unjustly subject the allottee to coercive recovery proceedings or adversely affect his creditworthiness when the loan proceeds were disbursed for the benefit of the promoter.


# 13. Per contra, the learned counsel appearing for the third respondent, while challenging the maintainability of the present appeal, contended that the impugned order passed by the Authority does not contain any adverse finding against the third respondent, nor does it fasten any liability upon it or issue any operative direction whatsoever against it. In the absence of any such finding, direction or liability, the allottee cannot seek modification of the impugned order by way of the present appeal. It was further contended that the reliefs now sought by the allottee were neither claimed before the Authority nor considered or adjudicated upon by it. As such, the allottee cannot be permitted to introduce entirely new reliefs or seek modification of the impugned order in respect of matters which were neither the subject matter of the original complaint nor adjudicated upon by the Authority. In support of his contentions, the learned counsel placed reliance upon the decision of the Hon’ble Apex Court in Bachhaj Nahar Vs. Nilima Mandal  [AIR 2009 SC 1103] and submitted that the relevant principles laid down therein are applicable to the facts of the present case. The relevant portion of the said decision reads as follows:

  • “… The High Court, in this case, in its obvious zeal to cut delays and hardships that may ensue by relegating the plaintiffs to one more round of litigation, has rendered a judgment which violates several fundamental rules of civil procedure. The rules breached are:

  • (i) No amount of evidence can be investigated, upon a plea which was never put forward in the pleadings. A question which did arise from the pleadings, and which was not the subject matter of an issue, cannot be decided by the court.

  • (ii) A court cannot make out a case not pleaded. The court should confine its decision to the question raised in pleadings. Nor can it grant the relief, which is not claimed, and which does not flow from the facts and 

  • (iii) A factual issue cannot be raised or considered for the first time in a second appeal”


# 14. Upon examining the law laid down by the Hon’ble Apex Court in the aforesaid decisions, it is evident that, in Bikram Chatterji Vs. Union of India and Others, the Hon’ble Apex Court held that, in the event of any conflict between the provisions of the RERA Act and the SARFAESI Act, the provisions of the RERA Act would prevail. Further, in Union of India Vs. Rajasthan Real Estate Regulatory Authority and Others, the Hon’ble Apex Court held that the RERA Authority is empowered to entertain a complaint by an aggrieved person against a bank or financial institution, in its capacity as a secured creditor, where such secured creditor takes recourse to any of the measures contemplated under Section 13(4) of the SARFAESI Act. However, the Apex Court clarified that the provisions of the RERA Act would not ordinarily govern transactions between a borrower and a bank or financial nstitution where the security interest had been created by  way of mortgage prior to the commencement of the RERA Act, unless it is established that the creation of such mortgage or the underlying transaction was fraudulent or collusive.


# 15. A copy of the Tripartite Agreement dated 28.11.2018 has been placed on record along with the Memorandum of Appeal and the date of its execution is not in dispute. Having regard to the nature of the transaction and the principles laid down by the Hon’ble Apex Court in the aforesaid decisions, it is evident that the provisions of the RERA Act are applicable to the transaction in question and to the extent of any inconsistency with the provisions of the SARFAESI Act, the former would prevail. Consequently, the Authority is vested with the jurisdiction to entertain and adjudicate upon the complaint lodged by the allottee.


# 16. Upon careful examination of the recitals and terms incorporated in the Tripartite Agreement, the respective rights, duties and obligations of the allottee, the promoter and the financier are clearly discernible. In order to appreciate the nature and extent of the contractual obligations undertaken by each of the parties and to arrive at a just and proper conclusion in the matter, it would be appropriate to extract and reproduce the relevant clauses of the said agreement. The two material clauses, which have a direct bearing on the controversy involved in the present appeal, are extracted hereunder: 

  • “HDFC will release the loan amount based on the demand raised by builder duly endorsed and authorised by borrower in writing and based on the progress of construction of the project and on the terms and conditions agreed by the all three parties in this Tripartite Agreement.”

  • “In the event of cancelation of allotment/booking/allocation of the flat by borrower or builder for whatsoever reason or in event of builder not executing-registering the sale deed in favour of borrower within the stipulated time or in the event of litigation affecting the property/flat, builder undertakes to promptly and immediately refund the entire flat sale consideration amount received by builder (from both, borrower and HDFC) to HDFC., notwithstanding whether the flat is resold or not. Borrower hereby irrevocably authorise builder to directly pay the said flat sale consideration amount to HDFC without requiring any further consent or authorization for the same.” (Underlined by us for emphasis)


# 17. Further, the observations made by the Authority in paragraph 18 of the impugned order are of considerable relevance and significance for the purpose of adjudicating the controversy involved in the present appeal. Hence, it would be appropriate to reproduce the said observations verbatim for ready reference:

  • “The 1st respondent –promoter has collected substantial amount by entering into an Agreement of Sale dated 11.04.2018. The 2nd Respondent – banker without even ascertaining the stages of construction in the said project, has disbursed the amount and the same is clearly evident from loan account statement for Loan Account No.632107789 produced by the complainant. The 1st respondent – promoter has not only miserably failed to perform its promise under the agreement to sale but has also severely violated the provisions of the Act by executing sale deeds (document No.4931/2021-22 on 08.12.2021 and 6265/2021-22 on 19.02.2022) respectively in favour of Third parties. Despite existing Agreement of Sale dated 11.04.2018 and Tripartite Agreement dated 28.11.2018 and received substantial consideration, the respondent no.1 has not intimated or cancelled regarding the same.”


# 18. In the impugned order, the Authority has categorically observed that the third respondent-financier had disbursed the loan amount without even ascertaining the stage of construction of the project. Such disbursement, without verifying the progress of construction, is also borne out by the loan account statement produced by the allottee before the Authority. 


# 19. A careful examination of the material on record would make it evident that the promoter had agreed to sell the aforesaid two flats in favour of the allottee for the total sale consideration stipulated in the Agreement to Sell and had received a sum of Rs.37,00,000/- directly from the allottee, besides procuring a further sum of Rs.1,13,80,672/- by way of a loan obtained in the name of the allottee through the Tripartite Agreement. However, despite having received substantial consideration from these sources, the promoter, allegedly with the intention of defrauding the allottee, proceeded to alienate the very same flats in favour of third parties. The said alienations are evident from the copies of the sale deeds produced by the allottee along with the memorandum of appeal. It is further significant to note that, while seeking alteration of the reliefs originally claimed in the complaint, the allottee had specifically brought these developments to the notice of the Authority. Though the third respondent-financier was subsequently impleaded as an additional respondent and the aforesaid allegations were brought to its notice, neither the third respondent nor the second respondent-promoter chose to appear before the Authority or controvert the specific averments made by the allottee. In these circumstances, it is evident that the third respondent/financier had notice, at least during the proceedings before the Authority, that the second respondent-promoter had failed to honour the terms of the Agreement to Sell and had alienated the very same flats in favour of third parties, in contravention of its contractual obligations towards the allottee.


# 20. It is pertinent to note that the Tripartite Agreement cast a specific obligation upon the third respondent-financier to obtain the prior written consent of the allottee before disbursing any loan amount in favour of the promoter. Admittedly, it is nobody’s case that the third respondent had obtained such written consent from the allottee at the time of releasing the loan proceeds to the promoter. In the absence of compliance with this express contractual stipulation, the disbursement of the loan amount without obtaining the allottee’s written consent assumes considerable significance. It is in this background that the Authority, in paragraph 18 of the impugned order, was constrained to record its observations regarding the lapses and lack of due diligence on the part of the third respondent-financier.


# 21. Notwithstanding the aforesaid serious lapses and deficiencies on its part, the third respondent-financier continues to reiterate its stand that the allottee, being the borrower under the loan transaction, is solely liable to repay the loan amount. However, such a contention, when examined in the light of the material available on record, appears to be wholly untenable and contrary to the very principles of fairness, due diligence and responsible lending that financial institutions are expected to observe while extending financial assistance in transactions involving tripartite agreements between the allottee, promoter and financier.


# 22. As rightly contended by the third respondent, the reliefs now sought by the allottee by way of modification were not specifically claimed in the original complaint before the Authority. Having regard to the settled principles of law and the law laid down by the Hon’ble Apex Court in Bachhaj Nahar Vs. Nilima Mandal, it is well settled that a party cannot ordinarily seek altogether new reliefs at the appellate stage, which were neither pleaded nor adjudicated upon by the original forum. It is true that the allottee had not specifically sought the aforesaid reliefs before the Regulatory Authority. However, the mere omission to incorporate a specific prayer in the original complaint would not, by itself, preclude this Tribunal from granting appropriate consequential or ancillary relief in an appeal preferred under Section 44 of the Act, particularly when such relief is intrinsically connected with the principal relief originally claimed and arises out of the same set of facts and circumstances. Having regard to the powers conferred upon this Tribunal under sub-sections (3) and (6) of Section 44 of the Act, we are of the considered view that this Tribunal is competent to suitably mould the relief, provided that such exercise does not introduce an altogether new cause of action or occasion prejudice to the opposite party. Accordingly, notwithstanding the absence of a specific prayer before the Authority, the request made by the allottee deserves to be examined and considered on its own merits.


# 23. In the light of the foregoing discussion, it is evident that the modifications sought by the allottee in the present appeal are merely ancillary and consequential to the principal relief originally sought before the Authority and do not constitute an altogether new or independent

cause of action. Added to this, the allottee had specifically pleaded the relevant facts and circumstances before the Authority in support of the very reliefs now sought by way of modification in the present appeal. Therefore, it cannot be said that the third respondent was taken by surprise or deprived of an opportunity to meet the case sought to be advanced by the allottee. In such circumstances, we are of the considered view that the principles laid down by the Hon’ble Apex Court in Bachhaj Nahar Vs. Nilima Mandal are distinguishable on facts and have no application to the case on hand.


# 24. The manner in which the third respondent is resisting the present appeal makes it abundantly clear that, taking undue advantage of the terms of the tripartite agreement, it is making every endeavour to exert pressure upon the allottee to repay the entire loan amount, notwithstanding the fact that the allottee has not derived any benefit whatsoever from the loan proceeds, which were disbursed for the benefit of the second respondent/promoter. In the circumstances, the appropriate remedy available to the third respondent-financier is to recover the loan amount from the second respondent-promoter, who is the actual beneficiary of the loan proceeds and, if any valid mortgage or security interest has been created in its favour in respect of the aforesaid flats, to enforce its rights against he secured property in accordance with law, rather than  subjecting the allottee to coercive recovery measures. Having regard to the principles laid down by the Hon’ble Apex Court in the aforesaid decisions and the decision of the Hon’ble High Court of Karnataka in Mudit Saxena v. Union of India, we are of the considered view that this Tribunal, in an appropriate case, is competent to issue necessary directions to protect an allottee from adverse consequences affecting his creditworthiness and CIBIL score arising out of disputes emanating from a real estate transaction of this nature. For the foregoing reasons, we are constrained to hold that the present appeal is maintainable and that the allottee is entitled to the consequential modification of the impugned order, as  prayed for. Accordingly, we answer Point No.1 in the affirmative and proceed to pass the following order: 


ORDER

  • (a) The appeal is hereby allowed;

  • (b) The impugned order dated 19.03.2026 passed by the 1st Respondent –Authority in Complaint No. CMP/211116/0008580 is hereby confirmed. However, the allottee is held entitled to the following ancillary reliefs:

  • (c) The third respondent is hereby directed to recover the outstanding loan amount, if any, from the second respondent - Promoter and to forthwith cease all coercive recovery measures against the appellant, including reporting any default in respect of the aforesaid loan account.

  • (d) The third respondent is further directed not to report, adversely affect or cause any adverse entry in the appellant’s credit information report or credit score, in any manner whatsoever, in connection with the Loan Account No.632107789.

  • (e) In view of disposal of the main appeal, pending I.As., if any, shall stand disposed of, as they do not survive for consideration;

  • (f) Registry is directed to comply with the provisions of Section 44(4) of the Act and to return the records to RERA, if any received.


There is no order as to costs.

----------------------------------------