Sunday, 4 January 2026

Punjab National Bank Vs. Mrs. Manasi Patro @ Panda & Others - The appellant-bank after taking recourse to Section 13(4) of the SARFAESI Act, more particularly having taken possession of the mortgaged project land, has certainly stepped into the shoes of the respondent no.2-promoter, who is the borrower, in relation to the secured asset.

 REAT Odisha (2025.11.24) in Punjab National Bank Vs. Mrs. Manasi Patro @ Panda & Others  [OREAT Appeal No.32/2024] held that; 

  • However the moment the bank or the financial institution takes recourse to any of the measures available in sub-section (4) of Section 13 of the SARFAESI Act, RERA authority would have jurisdiction to entertain the complaint filed by an aggrieved person.”

  • Order dated 14.02.2022 of the Hon’ble Supreme Court of India in the Petition for Special Leave to Appeal (Civil) Nos.1861-1871 of 2022 filed by the Union Bank of India. The appellant-bank after taking recourse to Section 13(4) of the SARFAESI Act, more particularly having taken possession of the mortgaged project land, has certainly stepped into the shoes of the respondent no.2-promoter, who is the borrower, in relation to the secured asset.

  • The settled law in the decision of Hon’ble Supreme Court of India in the case of Bikram Chatterji and Others versus Union of India and Others reported in (2019) 19 SCC-161 that, in the event of conflict between the RERA Act and the SARFAESI Act, the provisions contained in the RERA Act would prevail.

  • However, in dealing with the Hon’ble Supreme Court’s decision in the Bikram Chaterji case (Supra), the Hon’ble High Court of Rajasthan has put a rider by observing that, RERA would not apply in relation to the transaction between the borrower and the banks and financial institutions in cases where security interest has been created by mortgaging the property prior to the introduction of the Act unless and until it is found that the creation of such mortgage or such transaction is fraudulent or collusive.

Excerpts of the Order;

24.11.2025 The appeal is taken up through hybrid mode.


2) We have already heard Mr. P.K.Dasmohapatra, learned counsel appearing for the appellant, Ms.R.Jain, advocate appearing in behalf of Mr. P.Sahoo, learned counsel for the respondent no.1, Mr. D.M.Mishra, learned counsel appearing for the respondents no.2 and 3 and Mr. B.Nayak, learned counsel appearing for the respondent no.7-Regulatory Authority. The respondents no.4 to 6 are set ex parte vide order dtd. 6.11.2024 due to their non-appearance inspite of due service of notice on them.


3) Aggrieved over the order dtd. 10.01.2024 of the learned Odisha Real Estate Regulatory Authority passed in Complaint Case No.266/2022, the appellant who was the respondent no.6 therein has filed this appeal praying to set aside the impugned order dt. 10.1.2024 so far as the directions in para-15 (i), (iv) & (v) of it are concerned. The respondent no.1 of this appeal was the complainant and the respondent nos.2 to 6 were the respondents no. 1 to 5 in the said complaint case. The respondent no.7 is the learned Regulatory Authority who has passed the impugned order.


4) The facts and circumstances leading to the filing of the present appeal are as follows :

On 24.8.2022 the respondent no.1 of this appeal as complainant filed the aforesaid complaint case before the learned Regulatory Authority stating that, intending to purchase a land in Bhubaneswar she approached the respondent no.2 who made a proposal to the complainant to purchase a piece of land in mouza-Raghunathpur Jali facing Nandankanan road measuring 2000 sq. feet for a sum of Rs.10,00,000/- from the respondent no.3. The respondent no.2 had also proposed the complainant to pay a sum of Rs.23,00,000/- in cash towards development, conversion, construction of approach road etc. of the said land. The respondent no.2 further assured that he shall give one flat having super built up area of 2000 sq. feet and plinth area around 1600 sq. feet after construction of the residential project which will be constructed over the patch of lands including the plot of the complainant. Accordingly, the complainant paid a sum of Rs.2,50,0000/- on 4.3.2015 and Rs.7,50,000/- on 1.7.2015 through cheques to the respondent no.3 who as a token of receipt issued money receipts of the said amount. The complainant also paid Rs. 23,00,000/- to the respondent no.2 by cash and received money receipt to that effect. A memorandum of understanding was also executed between the complainant and the respondent no.3 on 2.7.2015 in which the respondent no.3 admitted to have received Rs.10,00,000/- for 2000 sq. feet super built up area (approximately 1600 sq. feet built up area) of the apartment with a car parking space. It was agreed in the said MoU that the respondent no.3 will issue allotment letter and execute agreement for sale within 12 to 24 months from the date of MoU. It was further agreed upon that the apartment shall be handed over to the complainant within 60 months from the date of MoU. However, in October, 2017, the respondent no.2 informed the complainant that the respondent no.3 would not be able to honour his commitment and another promoter i.e. respondent no.4 will register a plot in the same Tahasil measuring 2000 sq. feet in favour of the complainant instead of respondent no.3, to whom the complainant had already paid an amount of Rs.10,00,000/- towards the cost of the land. In view of the new development, the respondent no.3 refunded the amount to the complainant, who in turn paid the same to the Respondent no.4 on 25.10.2017. On 31.10.2017, the respondent no.4 executed a sale deed in favour of the complainant in respect of a land measuring Ac.0.046 under Plot No.1273 in Khata no.28 of mouza Raghunathpur Jali. However, subsequently in August, 2020, the respondent no.2 informed the complainant that he could not acquire sufficient land for construction of multi-storied apartment and accordingly he could not fulfil his commitment. The respondent no.2 then approached the complainant to register Flat No.72 of 2088 sq. feet in the project ‘Ganapati Homes’, Sum Hospital Road, Sampur developed by Odyssa Homes & Commercial Pvt. Ltd. in exchange of the land purchased by the complainant with a suggestion to transfer it directly to his nominee Bhubaneswar Aquatech & Agro Products Pvt. Ltd (respondent no.4). Finding no other alternative the complainant agreed to it and accordingly an agreement for sale was executed followed by a letter of allotment issued by the respondent no.1. A Memorandum of Understanding was executed between the respondent no.2 and the complainant on 18.8.2020. The complainant on receipt of Rs.10,00,000/- from the respondent no.5 on 2.9.2020 paid the same to the respondent no. 1 so as to complete the transaction of Rs.33,00,000/- for the Flat No.72. On execution of another memorandum of understanding on 5.9.2020 between the complainant and respondent no.2 containing the detail particulars of earlier transactions including the exchange of the plot for the flat, a fresh allotment letter was issued to the complainant by the respondent no.1 signed by respondent no.2 on 6.9.2020 followed by an agreement for sale on the same day. Despite such allotment letter and agreement to sell, the respondent no.1 failed to deliver the flat and kept on delaying the same on some pretext or other. The complainant further alleged that while the matter stood thus, on 8.8.2022 he came to know from the paper publication that an e-auction notice was floated by Punjab National Bank (respondent no.6), in support of the entire property of respondent no.1 including the land under Khata No.233/144, Plot No.788/1444, mouza-Sampur, Tahasil-Bhubaneswar and was put to auction on 12.8.2022. As the respondents no.1 and 2 failed to deliver possession of the flat to the complainant, she is entitled to the refund of her money with interest. With the aforesaid claims and allegations, the complainant approached the learned Authority praying to direct the respondent no.1 to deliver the possession of the flat no.72 (Type-B) on the 7th floor of the project after complying with all the statutory requirements within stipulated time and pay interest for the delay in delivery of possession in accordance with law from the date of initial deposit till the delivery of possession. Further prayers were also made to direct the respondent no.6-Bank not to auction or create thirty party interest in Flat No.72 (Type-B) in the 7th Floor of the project and to impose penalty on the respondent no.1 under Sections 59 to 62 of the RERA Act.


Pursuant to the summons issued by the learned Regulatory Authority, the respondents no.1,2,3,5 and 6 appeared through their respective counsels and filed their separate show cause, whereas respondent no. 4 did not appear inspite of due service of notice on him and accordingly was set ex parte.


The respondent no.6 in its show cause submitted that the Bank is the true owner of the project land as the memorandum of understanding and sale agreement between the complainant and the respondent no.1-promoter are unregistered ones and the complainant has not disputed the mortgage of the project land and the loan advanced by the respondent no.6. Moreover, the complainant has no right, title and interest over the project property as no sale deed in respect of it has so far been executed in her favour by the respondent no.1. It is claimed by the respondent no.6-bank that it has sanctioned a term loan of Rs. 460 lakhs for construction of a house building project (Ganapati Homes) on the project land in favour of the respondent no.1 subject to certain terms and conditions and as per the said terms, the respondent no.1 has created a valid equitable mortgage in favour of the respondent no.6 in respect of the project land on 8.2.2014. The respondent no.6 has claimed that it being a secured creditor has every right to put the secured asset i.e. the project land to auction for recovery of the loan dues. The respondent no.6 further contended that after the loan amount was declared NPA on 29.11.2016 it issued a demand notice u/s 13 (2) of the SARFAESI Act,2002 on 5.12.2016 to the respondent no.1 asking it to pay Rs. 4,09,59,761.95 within a period of sixty days from the date of the notice, but inspite of the receipt of the said demand notice, the respondent no.1 failed to pay the outstanding dues resulting in the respondent no.6 issuing possession notice u/sec. 13 (4) of the SARFAESI Act, 2002 and publishing the same in the daily news paper. The bank also filed a recovery suit under the RDB Act, 1993 against the respondent no.1 and others vide O.A. No.166 of 2018 in the Debts Recovery Tribunal, Cuttack on 28.2.2018 for recovery of a due of Rs.3,72,37,455.90 and other reliefs and the same is pending for hearing. Claiming that it has already taken physical possession of the project land pursuant to the order dated 24.6.2019 passed by the District Magistrate and Collector, Khordha in BMC No.41/2017 under section 14 of the SARFAESI Act and that the said order has still not been challenged by the aggrieved party, the respondent no.6 has reiterated its claim that the agreement between the complainant and the respondent no.1 being an unregistered one and no sale deed having been executed and registered in her favour in respect of the flat in question, the complainant has no right, title and interest over the mortgaged property and as such the relief claimed against the respondent no.6 is not at all tenable in the eye of law. Further claiming that it being the secured creditor and the mortgagee in respect of the project land is authorized to sell it for realization of the loan dues, that the proceedings initiated so far by it under the SARFAESI Act have not been challenged either by the complainant or by the respondent no.1-promoter, that Section 35 of the SARFAESI Act, 2002 will override the provision of the RERA Act, 2016, that the dues of the Bank being secured debt will have priority over the mortgaged property, that the DRT, Cuttack only has the exclusive jurisdiction to adjudicate the issue involved and that other courts and tribunals have no jurisdiction to decide the validity and legality of the mortgage, the respondent no.6 has prayed for dismissal of the complaint with costs.


The respondents no.1 and 2 in their show cause have denied the multiple transactions claimed by the complainant in the complaint except the agreements dtd. 11.8.2020 and 6.9.2020. It is submitted that, the transactions entered into between the respondent no.2 and the complainant were purely on the personal capacity of the former and not as a director of respondent no.1. The transactions with respondents no.3,4 and 5 as alleged by the complainant are in no way connected with the agreements for sale dtd. 11.8.2020 and 6.9.2020 as those are personal and separate transactions between them. While admitting the complainant to be an allottee of the flat no.72 of the project in question the respondent no.1 has made it clear that, though the respondent no.2 is one of the directors of respondent no.1, but it is the director Mr. Saroj Kumar Panda, who is authorize to sign all the papers on behalf of the respondent no.1 accordingly it was Mr. Saroj Kumar Panda, who had signed the agreement for sale dated 11.8.2020. The respondent no.1 has claimed to be no way connected to the transaction dt.2.7.2015. It is further claimed that, the documents relied on by the complainant in Annexure-1 which are the money receipts of 2015 are issued by M/s. Shree Sidhi Vinayak Buildcon (P) Ltd. i.e. the respondent no.3 and hence the respondent no.1 has no nexus to it. The respondent no.1 has claimed that the MoU dtd. 18.8.2020 executed between the complainant and the respondent no.2 has been executed in their personal capacity and the respondent no.1 is not responsible for the same, as he is not a party to the same. The Respondent no.1 has though admitted the agreement for sale and allotment letter dtd. 11.8.2020 but claimed that there is nothing mentioned in the allotment with regard to prior payment of the complainant. Claiming that no document has been produced by the complainant showing payment of Rs.33 lakhs to the respondent no.2, the respondent no.1 has pointed out that the MoU dtd. 5.9.2020 clearly reveals that the complainant has paid Rs.10 lakhs. The respondent no.1 has asserted to have never and nowhere acknowledged any payment claimed to have been made by the complainant. It is further submitted that para-10 of the agreement for sale dtd. 6.9.2020 clearly stipulates that, ‘the buyer hereby agrees to pay all the amount payable as per the terms of the agreement as and when the same or any of them would become due and payable’. As the complainant has not made any payment except Rs.10 lakh, she is not entitled to get the relief as claimed by her. It is also submitted that the respondent no.6-bank has taken possession of the property by invoking the provisions of the SARFAESI Act, 2002. However, the respondent no.1 is in talks with the said bank for repayment of the loan and recall of its action. Respondent no.1 has further submitted that it has no objection if the complainant wants to withdraw from the project but as per her claim for refund of money, she is entitled to receive only Rs. 10 lakh which she has paid. With the aforesaid pleas, the respondent no.1 prayed to dismiss the complaint case.


The respondent no.3 filed its show cause admitting the fact that the complainant had entered into a MoU with it on 2.7.2015 for purchase of a land measuring 2000 sq. ft in mouza-Raghunathpur Jali and accordingly had paid a sum of Rs.10,00,000/- in two phases. However, as the land could not procured for some reason, the project could not be started within the stipulated period of two years. Accordingly, the amount was refunded to the complainant through her bank account and hence there is no further liability of the respondent no.3. The respondent no.3 therefore prayed to dismiss the complaint.


The respondent no.5 in his show cause to the complaint has claimed that the complainant case is without any cause of action against him and hence is not maintainable. The entire averments in the complaint shows no role of the respondent no.5 in the alleged delay in delivery of possession of the flat in question to the complainant by the respondent no.1 and the process initiated by the respondent no.6 for auction sale of the project. The respondent no.5 has accordingly prayed for dismissal of the complaint.


The learned Regulatory Authority on perusal of the pleadings of the complainant and the respondents no.1,2,3,5 and 6 framed four points for consideration and on hearing both the parties as well as going through the documents filed by them passed the impugned order as follows :

  • “The case is allowed, in part, on contest against the respondent nos.1,2,3,5 and 6 and ex parte against the respondent no.4 without cost.

  • (i) The Respondent no.6 is directed to complete the construction of the project ‘Ganapati Homes’, obtain occupancy certificate from the competent authority, execute conveyance deed in respect of flat no.72 (Type-B) in the 7th floor of the project over plot no.788/1444, Sampur, Dist-Khurda in favour of the complainant on receiving the balance consideration amount of Rs.44,50,000/- from her and handover the occupancy certificate and other documents to her within a period of two months from the date of obtaining occupancy certificate.

  • (ii) The respondent no.1 is directed to pay interest @ 9.50% per annum on the amount of Rs.10,00,000/- payable from 1.7.2015 till the date of delivery of possession.

  • iii) The complainant is directed to pay the balance consideration amount of Rs.44,50,000/- to the respondent no.6 on the date of registration of the sale deed under section 17 (1) of the Act.

  • (iv) The respondent no.6 is directed not to auction flat no.72 in the 7th floor of the project ‘Ganapati Homes’ over Plot No.788/1444, Sampur, Dist-Khurda by not creating 3rd party interest.

  • v) The promoter-respondent no.6 is directed to register the project with ORERA under Sec. 3 of the Act within two months from the order.

  • The Respondents no.1 and 6 and the complainant are directed to comply the order as above failing which, the order shall be enforced as per law.”


5) In the hearing of the appeal, the learned counsel for the appellant has submitted that, the learned Regulatory Authority has erred in directing the appellant-bank to act as the promoter in place of respondent no.2 ignoring the provisions of the SARFAESI Act, 2002. It is further submitted that the learned Regulatory Authority while passing the impugned order dt. 10.1.2024 in CC No.266/2022 has ignored the order dt. 15.12.2023 passed in an identical case i.e. CC No.1/2022 direction has been given to the respondents no.2 and 3 to complete the construction of project ‘Ganapati Homes, obtain occupancy certificate from the competent authority and execute the conveyance deed in respect of the flat in favour of the complainants on receiving the balance consideration amount from them and handover the occupancy certificate as well as other documents to them. It is further submitted that, the learned Regulatory Authority have not applied their mind while deciding that RERA would have retrospective effect as in the case of Union of India Vrs Rajasthan Real Estate Regulatory Authority, the Hon’ble Apex Court have held that, RERA would not apply unless and until it is found that creation of such mortgage or transaction prior to the introduction of the Act is fraudulent or collusive. In the present case no such fraud or collusion has been averred in the complaint petition by the respondent no.1. It is further submitted that the appellant-bank has prior charge over the property as Section 26 (E) of the SARFAESI Act, 2002 came into force on 1.9.2016, whereas Section 89 of the RERA Act came into force on 1.5.2016. It is further submitted that, the mortgage was created on 8.2.2014 and therefore the RERA Act coming into force on 1.5.2017 and having no retrospective effect, is not applicable to the present case and the complaint should have been dismissed on this ground. It is further submitted that, the appellant being a public financial institution, the direction to it to act as promoter, collect money from allottees and construct the flats is practically not possible. Further submitting that, the appellant being neither a promoter, nor an allottee nor a real estate agent, the learned Regulatory Authority have no jurisdiction to restrain the appellant from putting the project land in auction sale, the learned counsel for the appellant has made the prayer as mentioned earlier in para-3.


6) On the other hand, the learned counsel for the respondent no.1 has stuck to the averments made in the complaint petition. It is submitted that, as the respondent no.2-promoter failed to clear the loan which it had taken by mortgaging the project land, the appellant bank proceeded against it under section 13 (4) of the SARFAESI Act, 2002 without any information or notice to the respondent no.1. The learned counsel for the respondent no.1 has drawn the attention of this tribunal to the decision of Hon’ble Apex Court in the case of Bikram Chaterji V. Union of India wherein it is held that, in cases of conflict between the SARFAESI Act and the RERA Act, the provisions contained in RERA Act would prevail. The learned counsel for the respondent no.1 has also drawn the tribunal’s attention to the decision of Hon’ble Supreme Court in the case of Union Bank of India versus Rajasthan Real Estate Regulatory Authority reported in 2022 SCC Online Sc-1885, wherein it is held that, ORERA has jurisdiction to entertain a complaint by an aggrieved person against the bank as a secured creditor of the bank takes recourse to any of the provisions contained in Sec. 13 (4) of the SARFAESI Act. It is further submitted that the appellant bank has taken over the possession of the property under the SARFAESI Act and as the possession over the project continued after the RERA Act came into force, it is adversely affect the interest of respondent no.1. Further, contending that, the mortgage through was created in favour of the appellant bank on 8.2.2014 but the construction of the project has gone beyond the date of commencement of the RERA Act and hence the Act is applicable to the project, the learned counsel for the respondent no.1 terming the impugned order passed by the learned Regulatory Authority in C.C. No.266/2022 as just and legal, has prayed for dismissal of the appeal.


The learned counsel for the respondents no.2 and 3 have contended that, though the respondent no.1 is the allottee of Flat No.72 (Type-B) having an area of 2088 Sq. ft on the 7th floor of the project situated at mouza-Sampur and as per the sale agreement dtd. 11.8.2020 the consideration price of the said flat was fixed at Rs.54.50 lakh, but no payment was made in accordance with the said agreement by the respondent no.1. It is further contended that due to reasons beyond the control of the respondent no.2 including the arrest and remand of the directors of the respondent no.2 inside the jail custody, the project work was suspended and after their release from custody the respondent no.2 is trying to sort out the issues. It is further submitted that the respondent no.2 availed a loan of Rs.460 lakh by mortgaging the project land with the appellant in order to complete the project in time but as there was cost overrun and non receipt of timely payments from the allottees, the respondent no.2 defaulted in timely repayment of EMIs to the bank and the bank initiated recovery proceeding under the SARFAESI Act in which it seized the entire project property by taking physical possession of the same. It is further submitted that the respondent no.2 had paid Rs.40 lakh to the appellant as per the OTS approval, but due to arrest and remand of its directors it could not repay the loan in full. The respondent no.2-promoter has however claimed to be endeavouring to sort out all the issues including settlement of the dues of the appellant-bank and to complete the project as soon as possible. While making it clear that he does not contest the impugned order as he has no intention to deprive the allottees from their rightful claim, the respondent no.2-promoter has also chosen not to comment anything on the grounds of appeal.


7) The undisputed facts amongst the parties emerging from their pleadings in the complaint case and documents relied on by them such as the copies of the memorandum of understanding dtd.5.9.2020, the allotment letter dtd. 6.9.2020, the sale agreement dtd. 6.9.2020, money receipts, letter of sanction of term loan, notice u/sec. 13 (2) of the SARFAESI Act and order dated 24.6.2019 of the District Magistrate, Khurda u/Sec. 14 of the SARFAESI Act are :

  • i)The respondent no.1-allottee and the respondent no.2-promoter had entered into sale agreements in respect of flat no.72 (Type-B) in the 7th floor of the project over plot no.788/1444, Sampur, Dist-Khurda, Bhubaneswar on 11.8.2020 and 6.9.2020.

  • ii) The cost of the flat agreed to was Rs.54,50,000/- in the sale agreement dtd. 11.8.2020.

  • iii)The respondent no.1 also agreed to pay all statutory taxes including service tax as and when applicable and also pay registration charges at the time of registration.

  • iv)The respondent no.1 has paid Rs.10,00,000/- towards part consideration price of the aforesaid flat on 3.9.2020.

  • v) The project is still not complete for the respondent no.1 to take delivery of possession of the flat in question from the respondent no.2.

  • vi) The respondent no.2-promoter has mortgaged the project land to the appellant-bank on 8.2.2014 for a loan of Rs.460.00 lakhs.

  • vii) Due to failure on the part of the respondent no.2- promoter to repay the outstanding loan amount of Rs.40959761.95 , the appellant-bank after declaring the loan account as non-performing asset and issuing notice to it u/sec. 13 (2) of the SARFAESI Act, 2002 has taken recourse to Section 13 (4) of the said Act by obtaining permission of the District Magistrate & Collector, Khordha u/sec. 14 of the said Act vide order No.278 dated 24.6.2019 in BMC No.41/2017 for taking physical possession of the project land and publishing the auction sale notice in respect of the project land in the English daily newspaper ‘The Statesman’ dated 7.3.2020.

  • viii) The project being not completed till now is certainly covered under the RERA Act.


8) The transaction between the respondent no.1 and the respondent no.2 relating to the flat in question is mainly based on the sale agreement dtd.6.9.2020. In the MoU dtd. 5.9.2020 it is agreed that respondent no.2 has received Rs.10,00,000/- towards part consideration of the flat. Though the respondent no.1 has claimed to have paid an amount of Rs.33,00,000/- in total towards part cost of the flat, but has not explained as to why she agreed to execute the MoU dtd. 5.9.2020, allotment letter dtd. 6.9.2020 and sale agreement dtd. 6.9.2020 admitting to have paid only Rs.10,00,000/- out of the total cost. We are therefore of the opinion that, the latest admitted transactions between the respondent no.1 and respondent no.2 i.e. MoU dtd. 5.9.2020, the allotment letter dtd. 6.9.2020 and the agreement for sale dtd. 6.9.2020 shall prevail over any other transactions and the same confirm the fact that out of the total agreed cost of Rs.54,50,000/- as per the agreement dtd. 11.8.2020, the respondent no.1 has so far paid Rs.10,00,000/- to the respondent no.2. Having failed to complete the project and unable to give possession of the flat to the respondent no.1, the respondent no.2-promoter is undoubtedly liable to pay interest to the respondent no.1, who does not exclusively intend to withdraw from the project, on the payments received from her, for every month of delay, till the handing over of the possession, in accordance with the proviso to section 18 (1) (b) of the RERA Act, at the rate prescribed in Rule 16 of the ORERA Rules, 2017 i.e. SBI highest Marginal Cost of Lending Rate plus two per cent.


In normal circumstance, on adjudicating a complaint involving grievance of an allottee with regard to the promoter’s failure to complete and deliver possession of his/her allotted apartment flat as per the terms of the sale agreement, the Regulatory Authority on proof of such failure would have passed a simple order directing the promoter to deliver possession of the flat to the allottee together with interest at the aforesaid prescribed rate for every month of delay on the amount received by him in respect of the flat till the delivery of its possession. However, in the present case the project having been mortgaged by the respondent no.2-promoter to the appellant-bank and it having failed to repay the loan, the mortgagee i.e the appellant-bank has taken over the possession of the project land and has also taken step for its auction sale by advertisement in the daily news paper. So, it is for this reason, the learned Regulatory Authority in the impugned order dated 10.01.2024 has placed the appellant-bank as promoter in the place of respondent no.2 to discharge all the responsibilities of the promoter to complete the project and to secure the interest of the respondent no.1 and other allottees including the directions in the para-15 (i) & (iv) of the impugned order. The learned Regulatory Authority in the impugned order has held that, by virtue of the order of the DRT, Cuttack, the appellant-bank has taken possession of the mortgaged property and as a secure creditor is to realise the loan amount by putting the property into auction, and hence the appellant Bank has become the promoter of the project. The appellant-bank has challenged this finding of the learned Regulatory Authority on the ground that, it being the secured creditor is within its right to enforce its security under the provisions of the SARFAESI Act to recover its dues against the respondent no.2-promoter and taking possession of the secured asset is one of the provisions of law to which the appellant is entitled. The appellant-bank has therefore claimed that, it has not become the promoter of the project in place of respondent no.2.


In order to ascertain what has been the legal effect of the mortgage transaction dtd. 8.2.2014 between the respondent no.2 and the appellant, the case of Union Bank of India versus Rajasthan Real Estate Regulatory Authority and Others decided on 14.12.2021, is relevant. The Division Bench of the Hon’ble High Court of Rajasthan in this case have discussed Section 13 of the SARFAESI Act, 2002 in detail and held as follows:-

  • “33. In terms of the SARFAESI Act and particularly sec. 13, once a borrower is unable to repay the debt and the asset is classified as non-performing asset, it is open for the secured creditor to enforce the rights without intervention of the court. After issuance of notice under sec. 13 (2) and disposing of objections of the borrower in terms of Section 13 (3A), a secured creditor could proceed to take steps as envisaged in sub-section (4). These measures which a secured creditor can take include taking possession of the secured asset including right to transfer by way of lease, assignment or sale for realising the secured asset, to take over the management of the business of the borrower including the right to transfer by way of lease, assignment or sale for realising the secured asset........”

  • 35.Clauses (a), (b) and (c) of sub-section (4) of Section 13 vest power in the secured creditor to take all steps as the borrower himself could take in relation to the secured asset. Clause (d) goes a step further and enables the bank to recover its dues directly from a debtor or the borrower who has acquired any of the secured assets. For all purposes thus the secured creditor steps in the shoes of the borrower in relation to the secured asset. This is thus a case of assignment of rights of the borrower in the secured creditor by operation of law. In other words the moment the bank takes recourse to any of the measures under sub-section (4) of Section 13, it triggers statutory assignment of right of the borrower in the secured creditor. Till this stage arises the bank or financial institutions in whose favour secured interest may have been created may not be in isolation in absence of the borrower be amenable to the jurisdiction of RERA. However the moment the bank or the financial institution takes recourse to any of the measures available in sub-section (4) of Section 13 of the SARFAESI Act, RERA authority would have jurisdiction to entertain the complaint filed by an aggrieved person.”


The above mentioned observation of the Hon’ble High Court of Rajasthan finds approval from the order dated 14.02.2022 of the Hon’ble Supreme Court of India in the Petition for Special Leave to Appeal (Civil) Nos.1861-1871 of 2022 filed by the Union Bank of India. The appellant-bank after taking recourse to Section 13(4) of the SARFAESI Act, more particularly having taken possession of the mortgaged project land, has certainly stepped into the shoes of the respondent no.2-promoter, who is the borrower, in relation to the secured asset. So, the contention of the appellant-bank that the learned Regulatory Authority has erred in directing it to act as the promoter in place of respondent no.2 ignoring the provisions of the SARFAESI Act, 2002, is not acceptable.


9) As already mentioned above, the project in question being still not a completed one is definitely under the fold of the RERA Act. The respondent no.1 has filed the complaint case seeking redressal of her grievance under the RERA Act relating to the flat allotted to her on the project land, whereas the appellant-bank has claimed its right as a secured creditor under section 13 of the SARFAESI Act over the project land as a whole. It is the categorical plea of the appellant-bank in the complaint case that in view of section 35 of the SARFAESI Act, 2002, the Act will override the provisions of the RERA Act, 2016. In this regard, in their order dated 14.12.2021 the Hon’ble High Court of Rajasthan in the case of Union Bank of India Vrs. Rajasthan Real Estate Regulatory Authority and others (Supra) have referred to the settled law in the decision of Hon’ble Supreme Court of India in the case of Bikram Chatterji and Others versus Union of India and Others reported in (2019) 19 SCC-161 that, in the event of conflict between the RERA Act and the SARFAESI Act, the provisions contained in the RERA Act would prevail. However, in dealing with the Hon’ble Supreme Court’s decision in the Bikram Chaterji case (Supra), the Hon’ble High Court of Rajasthan has put a rider by observing that, RERA would not apply in relation to the transaction between the borrower and the banks and financial institutions in cases where security interest has been created by mortgaging the property prior to the introduction of the Act unless and until it is found that the creation of such mortgage or such transaction is fraudulent or collusive.


10) As regards the claim of the appellant-Bank that no fraud or collusion is involved in the mortgage transaction dated 8.2.2014, it is to be noted that the respondent no.2-promoter has executed the sale agreement relating to the flat in question of the project with the respondent no.1-allottee on 6.9.2020, which is much after the mortgage transaction. The RERA Act having been operative since 1.5.2017, the security interest created in favour of the appellant-bank through the mortgage transaction on 8.2.2014 is certainly prior to the introduction of the Act. When the appellant-Bank has sanctioned the loan of Rs.460 lakhs to the respondent no.2-promoter on an equitable mortgage of the project land on a date which is much prior to the date of the sale agreement between the respondent no.2-promoter and the respondent no.1-allottee, the transaction between the respondent no.1-allottee and the respondent no.2-promoter cannot be said to be in the knowledge of the appellant-bank. It is however to be noted that, earlier relating to the present mortgage transaction between the promoter and the Bank this tribunal in disposing of OREAT Appeal No.49 of 2023, OREAT Appeal No.148 of 2023 and OREAT Appeal No.26 of 2024 vide orders dtd. 30.6.2025 and 17.11.2025 respectively has already held the transaction of mortgage between the promoter and the bank involving the present project land to be a collusive one and hence under the applicability of the RERA Act.


11) In view of the discussions made in the preceding paragraphs Nos.7 to 10, we come to the conclusion that, the appellant-Bank after taking recourse to Section 13(4) of the SARFAESI Act i.e. obtaining physical possession of the project land and publishing advertisement in the newspaper for its auction sale is certainly an assignee of the respondent no.2-promoter and has stepped into its shoes. The RERA Act which prevails over the SAFAESI Act will apply to the mortgage transaction dated 08.02.2014 in spite of the fact that security interest has been created by mortgaging the project land prior to the introduction of the RERA Act as it has been already held by this Tribunal in OREAT Appeal No.49 of 2023, OREAT Appeal No.148 of 2023 and OREAT Appeal No.26 of 2024 that creating such mortgage is the result of collusion between the appellant-Bank and the respondent no.2-promoter. It is further held that ORERA has the jurisdiction to entertain the present complaint case by the respondent no.1 against the appellant-Bank as a secured creditor as the appellant-Bank has taken recourse to the provision contained in section 13(4) 

of the SARFAESI Act and the respondent no.1 has initiated the proceeding to protect her rights. We are also of the opinion that, practical issues are likely to arise if the appellant-bank who has stepped into the shoes of the respondent no.2-promtoer, is entrusted the remaining construction work of the project without any expertise, experience and resources in this regard, when it is unwilling to take the said responsibility.


Accordingly, we think it appropriate in the facts and circumstances of the case to issue the following directions :

i) The direction of the learned Regulatory Authority in para-15 (ii) and (iv) of the impugned order are hereby confirmed.

ii) As regards the directions of the learned Regulatory Authority in para-15 (i), (iii) and (v) of the impugned order are concerned, the same are modified as follows :

  • (i) Like its obligation under Section 8 of the RERA Act in the event of lapse of the registration or on revocation of the registration under the Act, the ORERA may consult the appropriate Government to carry out the remaining development works of the project by the competent authority or by the association of allottees (if such association exists), or in any other manner as may be determined by the ORERA which may include appointment of an external developer through public tender with consent of the respondent no.1 and other allottees in consultation with the appellant-bank. The respondent no.1 shall pay the balance amount, if any, to the developer determined by the ORERA at the time of registration of the sale deed relating to her flat. The respondent no.2 shall transfer the amount of Rs.10,00,000/- taken from the respondent no.1 to the developer, who shall take steps for registration of the project with the ORERA U/sec. 3 of the Act.

  • (ii) The appellant-bank shall be without any entitlement to resort to section 13 (4) of the SARFAESI Act in respect of the interests of the respondent no.1 and other investing allotees in the project.

  • (c) The appellant-bank being the collusive creditor and the assignee of respondent no.2-promoter shall extend all co-operation to the ORERA in enforcing the above direction in (b) (i) of this para for completing the project and securing possession of the flats to the respondent no.1 and other allottees.


With the above mentioned directions and modifications, the appeal is disposed of on contest against the respondents no.1,2 and 3 and ex parte against the respondents no.4 to 6.


Send an authentic copy of this order alongwith the record of the complaint case to the learned Regulatory Authority for information and necessary action. Also send a copy of this order each to the appellant, the respondent no.1 and the respondent no.2. 

------------------------------------------


Friday, 26 December 2025

Relationship Properties Pvt. Ltd. Vs. Veena Ravishankar and Anr.. - However, we are of the considered view that Extension of RERA Registration of a project does not automatically mean that due date for completion are as per the signed Agreement also get extended.

 REAT Karnataka (2025.11.20) in Relationship Properties Pvt. Ltd. Vs. Veena Ravishankar and Anr.. [(2025) ibclaw.in 546 REAT, Appeal No. (K-REAT) 27/2025] held that; 

  • However, we are of the considered view that Extension of RERA Registration of a project does not automatically mean that due date for completion are as per the signed Agreement also get extended. The Agreement for Sale and Construction Agreement are legally enforceable documents under Indian Contract Act, 1872 and the Promoters cannot unilaterally alter the due date for handing over unless both the parties agreed to change the due date of handing over possession. 


Excerpts of the Order;

The captioned appeal arises out of the Order dated 14.11.2024 passed by the Karnataka Real Estate Regulatory Authority (hereinafter referred to as ‘the Authority’ for short) in Complaint No.CMP/220321/0009194, whereby the Authority allowed the Complaint filed by the Respondents No.1 /Allottee (hereinafter referred to as ‘the Allottee’ for short) against the Appellant-Promoter(hereinafter referred to as ‘the Promoter’ for short) for relief of interest on delay period and rental compensation upto 18% per annum.


# 2. The brief facts gathered from the pleadings, documents on record, and the impugned order reveal that the Promoter formulated a residential apartment complex in the name and style of ‘PARKWEST’ (hereinafter referred to as ‘Project’) and had obtained the Development Plan from the BDA, and building approval from the BBMP, and constructed the Project in accordance with law. During the course of construction, the Allottee had approached the Promoter and shown her interest to purchase the Unit T4-09-10 known as Maple-B0904, on the 9th floor of ‘Maple Tower’ in the said project, with the super built-up area of 1755 Sq.ft., with single car park, for total consideration of Rs.1,33,01,900/-, exclusive of applicable taxes and accordingly, allotment was made in favour of the Allottee on 01.08.2016. Pursuant to the allotment, the Promoter executed the Agreement of Sale for Rs.50,01,580.91 and Construction Agreement for Rs.83,00,319.09, both on 25.12.2016, out of which, the Allottee had paid Rs.1,02,03,088/-.


# 3. The Promoter was supposed to handover possession of the flat by 31.12.2019, with an additional grace period of 6 months, that is upto 30.06.2020 as per Clause-2 of the Construction Agreement, subject to Clause-10 of the said Agreement i.e. variation on account of Force Majeure. In the event of non-handing over the flat in time otherwise set out in Clause-10 of the Construction Agreement, the Promoter was required to pay a sum of Rs.5/- per Sq.Ft. per month as delay compensation till the registration of the said flat at the time of handing over the possession.


# 4. Further, in the Memorandum of Appeal, it is averred that, during the course of completion of the said project in the year 2020, the project got affected by COVID-19 pandemic, due to which the construction activity had to be stopped for several months. Due to the impact of COVID-19 pandemic, the Authority had extended the project completion date till 30.09.2022. After completion of the project, the Promoter filed application before the BBMP on 12.08.2022 to issue Occupancy Certificate. As there was a delay in procurement of Occupancy Certificate, the Promoter obtained further extension from the Authority upto 31.03.2023.


# 5. As there was a delay in completion of the subject Project, the Allottee lodged a Complaint No.CMP/220321/0009194 and sought for compensation & house rent with interest @18% p.a. till date; monthly compensation with 18% rate and monthly rental for further delay; no RERA extensions and no new tower to be registered without the consent of the Allottee.


# 6. In the Statement of Objections before the Authority, the Promoter has denied all the allegations made against it and contended that the Promoter has obtained Occupancy Certificate from BBMP on 25.01.2023 and initiated the process of handing over the possession to the Allottees. The Promoter never intentionally delayed the completion of the project but only due to several reasons which are beyond the control of the Promoter including Force Majeure due to COVID-19 which considerably impacted the project completion timeline. In the meantime, the Promoter requested the Allottee to forego the delay period interest due to COVID-19, but the efforts of Promoter went in vain. The Promoter has relied on the Judgment of the M/s.Newtech Promoters and Developers Pvt.Ltd. Vs. State of UP & Ors. and contended that granting of compensation at 18% & monthly rental compensation does not comes under the jurisdiction of the Authority to adjudicate.


# 7. In response to the Objections of the Promoter, the Allottee has filed written submission before the Authority stating that she has already paid 90% of the sale consideration. As the flat was not fully ready, the Allottee inspected the property on 04.07.2023 and was able to identify 108 defects, out of which 50 were major defects. The Carpet area also was found to be less by 61.31 Sq.feet and the said flat is not ready for registration. Further, the Allottee stated that the Promoter has not obtained Occupancy Certificate and only secured a Partial Occupancy Certificate before the Authority, subject to fulfillment of 20 conditions by the Promoter. But the Promoter has not produced any kind of proof before the Authority to have complied with the conditions imposed by the BBMP. However, on 06.02.2024, the Engineering team visited the Project and inspected the works done by the Promoter. The Engineering team was satisfied with the repair works completed by the Promoter as specified by the Allottee in the Complaint, which is seconded by the Allottee too.


# 8. After hearing arguments of Promoter as well as the Allottee, the Authority allowed the Complaint cited supra on 14.11.2024 which is as under:

  • The Promoter is hereby directed to pay interest on delay period on the amount paid by the Allottee i.e. Rs.1,02,03,088/- to the Allottee within 60 days from the date of this Order calculated at the rate of SBI MCLR plus 2% from 01.07.2020 to 06.02.2024. Further directed to handover possession by way of execution of Sale Deed of the flat bearing No.T4-09-10 known as Maple B0904, on the 9th Floor of Maple Tower project in favour of the complainant on immediate effect on receipt of balance sale consideration if any. With regard to prayer of the Allottee for rental compensation upto 18% per annum from the Promoter, the Allottee is at liberty to file a separate complaint before the Adjudicating Officer, KRERA. The Allottee is at liberty to enforce the said order in accordance with law if the respondent fails to comply with this order. No Order as to costs.”


# 9. Aggrieved by the said Impugned Judgment, the Promoter has preferred the present Appeal. The Promoter has further contended that as the Promoter has procured the Occupancy Certificate in the month of Jan-2023 and made the unit in liveable condition after having rectified the snags identified by the Allottee on 04.07.2023, hence, the question of paying delay period interest till 06.02.2024 i.e. the date of inspection of Allottee does not arise. The Promoter has contended that as the said Project is coming under the purview of RERA Act 2016, the Promoter is liable to pay interest on delay period from the month of delay as per Sec.18(1) of RERA Act, and, similarly, the Allottee also is liable to pay the interest on delayed payment of installments by her, as per Sec.19(7) of RERA Act, 2016. The Promoter has further contended that as the Promoter has already procured the Occupancy Certificate in the month of January-2023 and made the unit in liveable condition after having rectified the snags identified by the Allottee on 04.07.2023, the question of paying delay period interest till 06.02.2024 i.e. the date of inspection of Authority does not arise.


# 10. The Promoter further contended in the Appeal that, as the completion date of the said project falls during the period of COVID-19 pandemic, the Promoter was not able to complete the project due to lockdown and the resultant shortage of manpower, machinery and materials. Accordingly, request has been made to Allottee as well as Authority to deduct the delay period interest for 9 months, but they have not deducted the interest for 9 months. From April-2023 onwards, the Promoter has been requesting the Allottee to come forward for inspection and to take possession of the subject flat as per Sec. 19(10) of the RERA Act, but the Allottee has failed in her performance. The Impugned Order passed by the Authority is manifestly arbitrary manner, erroneous, which is contrary to law, facts of the case and accordingly prayed for following reliefs:

  • i) To allow the Appeal by setting aside the Impugned Order dated 14.11.2024 passed by the Authority;

  • ii) To modify the date of interest from 01.07.2020 till the date of offer of possession with invoice i.e. upto 22.07.2023 on the amount paid by the Allottee i.e. Rs.1,02,03,088/- in lieu of date of interest from the period 01.07.2020 till 04.02.2024 as decided by the Authority;

  • iii) To direct the Allottee to deduct the interest on delay period for 9 months as moratorium period under Covid-19 pandemic out of the interest accrued under prayer-ii;

  • iv) To give direction to Allottee to pay the interest on delay for the balance sale consideration amount of Rs.51,23,445/- from 22.07.2023 till the date of realization.


# 11. In response to the notice, the Allottee appeared before the Tribunal through her counsel and filed Statement of Objections to the Memorandum of Appeal inter alia contending that the appeal is not maintainable either in law or on facts and is therefore liable to be dismissed in limine. The Appeal is barred by limitation and the reasons assigned for delay, cannot be countenanced in law, hence the Appeal deserves to be dismissed at the threshold. The present Appeal is filed with an intention to delay the handover of the apartment unit and to cause annoyance to the Allottee.


# 12. Further, it is contended by the Allottee in her Statement of Objections that she is a senior citizen aged about 64 years, has invested her life savings for securing a residential dwelling for peaceful habitation. The Allottee has also obtained loan from State Bank of India to purchase the apartment and is compelled to pay the EMIs apart from incurring monthly rental losses. She has not denied entering Agreement for Sale and Construction Agreement on 25.12.2016 with respect to the subject apartment and conditions prevailed therein. The Allottee contended that a Force Majeure clause does not permit indefinite suspension of obligations, nor does it empower one party to unilaterally modify the terms of the Agreement.


# 13. Further, it is contended by the Allottee that the apartment was not ready in all aspects neither on the date the Occupancy Certificate was applied nor on the date when the partial Occupancy Certificate was issued. The Promoter has cured the defects pointed out by the Allottee only on 06.02.2024, except the carpet area. There is a shortfall to the tune of about 29.92 sq.ft. of carpet area after duly factoring the 5% allowable variation in terms of the Agreements, which ought to be compensated by the Promoter. The Allottee further contended that she was not allowed to conduct proper inspection with the necessary tools and was only allowed to conduct inspection using measuring tape and distometer.


# 14. Insofar as the contention of the Promoter that this Allottee did not come forward to take possession of the apartment, the Allottee submitted that since the proceedings before the Authority were still being heard and the Promoter at no point of time, informed the Authority that they were ready and willing to handover the possession of the apartment to the Allottee. Since the Appellant has not complied with the Order of the Authority, a Revenue Recovery Certificate dated 28.02.2025 was issued by the Authority for execution, however, the Promoter, with the sole intention to delay the execution of the said order, filed the present Appeal on 28.03.2025 with the sole intention to harass and arm twist this Allottee for a settlement. With these contentions raised in her Objections, the Allottee prayed this Tribunal to dismiss the Appeal, with exemplary costs; award costs of this proceeding and pass such other or further Order as deemed suitable.


The oral arguments submitted by the Appellant-Promoter on 27.03.2025:

# 15. The learned Counsel for the Promoter, more or less reiterated the points made in the Appeal Memo and further submitted hat his dispute with the Order of the Authority is with regards to the dates for calculation of interest since the Authority has awarded interest from 01.07.2020 to 06.07.2024, and 06.02.2024 is neither the date of Occupancy Certificate nor the date on which the Promoter intimated the Allottee to take over the possession, but the date of inspection by the Authority, which is not relevant for the purpose of calculation of interest.

15.1. He submitted that as per Clause-2 of Construction Agreement, the due date for completion was 30.01.2019 with a grace period of 6 months. The due date for completion, therefore, was right in the middle of COVID pandemic, and the Authority has extended the project completion date initially till 30.09.2022, and subsequently till 31.03.2023.

15.2. Learned Counsel for the Promoter stated that the Promoter received the Occupancy Certificate on 25.01.2023 and sent the e-mail to the Allottee on 04.04.2023 to submit necessary data for execution of Sale Deed. Since the Allottee wanted to get the inspection done by 3rd party which is not provided in the Construction Agreement, the Promoter asked the Allottee to come for the inspection on 29.06.2023.

15.3. The invoice was sent to the Allottee to pay the balance amount to get the Sale Deed executed. The total consideration was Rs.1.53 crores, of which the Allottee had paid Rs.1.02 crores leaving the balance of Rs.51 lakhs. The Promoter offered to give discount of Rs.23.76 lakhs towards compensation for the delay and asked to pay the net balance amount of Rs.27.46 lakhs. However, the Allottee refused to avail of this offer although, all other Allottees had agreed to similar proposal.

15.4. The Allottee insisted on a second inspection which was done in the month of December 2023 on 02.12.2023. The Promoter sent an e-mail to the Allottee on 11.12.2023 to release the balance payment. Since the Allottee had filed the complaint before the Authority in the mean time, the Authority offered to get the inspection done which took place on 06.02.2024 and the Authority confirmed at para No.27 of their Order that the unit was ready for possession and the Allottee also agreed and was satisfied with the finishing work and gave her consent in writing. The Promoter wrote to the Allottee by e-mail on 07.03.2024, 25.06.2024, 26.06.2024 to take over the possession but she still raised some issues pertaining to carpet area and did not come forward to take possession. The Promoter argued that once the Occupancy Certificate is issued and an Offer letter is made, he is not liable for any delay period interest, since the delay is on the part of the Allottee and therefore, for all delays beyond the first inspection on 04.07.2023, he is not liable to pay any compensation for delay after July 2023. The Promoter claims that the Allottee has not paid the balance amount towards the total sale consideration and requested that the delay period may be calculated on 31.07.2023 when the first inspection was made and that amount may be adjusted towards sale consideration.

15.5. The learned Counsel for the Promoter submitted a circular of Maharastra RERA dated 18.05.2020, Case Law pertaining to Balaji Construction Company Vs. Chintan Mahesh Sha in the Hon’ble High Court of Karnataka and an Office Order of U.P. RERA, in support of his arguments and prayed that his Appeal be allowed and the date of interest be modified from 01.07.2020 till date of Offer of Possession with invoice upto 22.07.2023 and to direct the Allottee to pay interest on delay on her part for balance sale consideration.


Oral arguments made by the Counsel for Allottee on 18.08.2025 :

# 16. The learned Counsel submitted that the Promoter has contended that the Allottee did not come forward to take over possession to which the reply of the Allottee is that the Occupancy Certificate is issued when the matter was pending before the Authority. The Promoter have stated in their argument that the interest was awarded by the Authority from 01.07.2020 to 06.02.2024 and that the Promoter is agreeable to pay interest till 31.07.2023, but is not agreeable to pay interest from 01.08.2023 to 06.02.2024. The Counsel further argued that due date for completion was pre-Covid which is 31.12.2019 with grace period additional six months, but the actual due date for handing over possession was 31.12.2019 and the additional six months period cannot be included while computing the due date for completion. The Counsel further argued that if there was any Force Majeure condition, the Promoter should have notified the Allottee about the same which he did not do. Also, that the Occupancy Certificate was issued on 25.01.2023 and Covid lockdown had not continued till that date, which goes to prove that indeed, there was delay in completing the Project.

16.1. The learned Counsel for Allottee also submitted that the Promoter sent e-mail to Allottee on 25.01.2023 informing about receiving Occupancy Certificate and again on 16.06.2023 to say that they are ready to handover property to the Allottee. Further, Allottee scheduled an inspection and three inspections were held and the defects were finally rectified beyond 26.06.2024. The Counsel disputed the stand taken by the Promoter that the Allottee had delayed the payment by stating that the Allottee has made all the payments as required, except for last installment, which was to be paid at the time of registration of the Sale Deed. The Allottee sent e-mail on 27.01.2025 offering to pay the final installment after deduction of interest on delay period. The Counsel further submitted that the Promoter has not complied with the Orders of the Authority to execute the Sale Deed and that Promoter has not given any reasoning for calculating interest till 31.07.2023.


# 17. Heard the arguments of learned counsel for the Promoter as well as Allottee. The Counsel for Promoter has a filed a Memo and produced the following documents:

i) Circular of MAHA RERA dated 18.05.2020 vide Order No.14/2020 wherein it is stated that the Force Majeure period will be treated as a “moratorium period” for the purpose of calculating the interest under Sec.12, 18, 19(4) and 19(7) of the Act.

ii) Order passed in Second Appeal No.731/2023 dated 20.02.2024 in the case of Balaji Construction Company Vs. Chintan Mahesh Shah by the Hon’ble High Court of Judicature at Bombay, wherein it is held that “While computing the interest payable to the Respondents at the time of delivery of possession, the period covered by the moratorium will have to be excluded. Thus, the amount of interest during moratorium period is not payable by the Appellant even in future”

iii) Order dated 18.08.2021 vide No.7225/U.P. RERA/Extension /Compliances /Order /LKO/2021-22 wherein in the representation of the CREDAI and NAREDCO, two confederations, requested that, Complete waiver of refund/interest/penalties compensation pertaining to the extended period of projects and no benefits to be passed on to the homebuyers as provided under Clause 7 of the Agreement for Sale.


# 18. On the other hand the counsel for the Allottee filed a memo along with E-mails dated 25.01.2023, 16.06.2023, 10.07.2023, 22.07.2023 and 11.12.2023.


# 19. The points that would arise for our consideration are:

  • i) Whether the Appellant/Promoter is entitled for the relief claimed in the Appeal?

  • ii) Whether the Impugned Order dated 14.11.2024 needs to be set aside?

  • iii) What Order?


# 20. Our findings on aforesaid point No.(i)and (ii) is partly in the affirmative for the following:


REASONS

# 21. Point No.(i): To reiterate the essential facts briefly, the Allottee entered into an Agreement for Sale and Construction Agreement on 25.12.2016 to purchase Unit No. T4-09-10 on the 9th floor of ‘Maple Tower’ in the project named ‘PARKWEST’ developed by the Promoter for a total consideration of Rs.50,01,580.91 towards undivided share of the land area and Rs.83,00,319/- towards construction, totaling to Rs.1,33,01,900/-. As per the Construction Agreement, the Promoter was supposed to handover possession of the flat by 30.06.2020, which includes grace period of Six months, subject to Clause-10 of Construction Agreement regarding likely delay on account of Force Majeure. The Promoter would have to pay a sum of Rs.5/- per Sq. Ft. per month, if he failed to handover possession as per the Agreement till Registration of the said flat at the time of handing over possession.


# 22. It is the case of the Promoter that the project got affected by Covid Pandemic, as a result of which, he could file application to the BBMP for issue of Occupancy Certificate only on 12.08.2022 and the BBMP issued Partial Occupancy Certificate on 25.01.2023 after the Promoter had completed the project. The Promoter obtained extension of RERA Registration from RERA till 30.09.2022 which was further extended till 31.03.2023. As there was delay in completion of the project, the Allottee filed Complaint No.CMP/220321/0009194 and sought for delay compensation and house rent with interest @ 18% per annum. It is further case of the Promoter that delay was due to the factors beyond the control of the Promoter on account of Covid-19 and the Promoter requested the Allottee to forego the delay period interest due to Covid-19 but there was no resolution of the dispute between the Promoter and the Allottee in this regard.


# 23. The Allottee has claimed that she had almost paid 90% of the sale consideration, and eventually, when she received offer from the Promoter to inspect the property, and upon first inspection on 04.07.2023, she found several defects including some shortfall in the Carpet Area. The Allottee also argued that the Promoter had only secured Partial Occupancy Certificate, which was subject to fulfillment of 20 conditions by the Promoter. Two more inspections were done, one on 02.12.2023, and the final one on 06.02.2024 when the Engineering team from the Authority inspected the works, and the Team as well as Allottee were satisfied with the repair works undertaken by the Promoter.


# 24. Allottee’s Complaint before the Authority was allowed and the Promoter was directed to pay interest on delay period on the total amount paid by the Allottee to be calculated at the rate of SBI MCLR plus 2% from 01.07.2020, being the scheduled date of inspection, till 06.02.2024 being the date on which the Engineering Team inspected the work and reported that the repair works were satisfactorily completed, the Promoter was also directed to handover possession by executing Sale Deed immediately on receipt of balance sale consideration, if any. Aggrieved by this Judgment, the Promoter preferred the present Appeal before the Tribunal. The Promoter has contended that he obtained the Occupancy Certificate on 25.01.2023 and rectified the snags on 04.07.2023 and hence he is not liable to pay interest from 01.08.2023 till 06.02.2024. He also claimed that since there was delay in payment installment by the Allottee also, the Allottee also is liable to pay interest as per Section 19(7) of the RERA Act.


# 25. The reason given by the Promoter for delay in completion of the Project is that completion date of the project falls during the period of ‘COVID Pandemic’ and also that the Promoter has been requesting Allottee to come forward for inspection and to take possession of the flat as per Section 19(10) of the RERA Act but, the Allottee did not come forward to do so. The Allottee has also contended that Force Majeure clause does not permit indefinite suspension of the obligation on the part of the Promoter. The Allottee has also contended that the defects found out by the Allottee were rectified only on 06.02.2024, except the Carpet Area, which is still unresolved. The Allottee has submitted that since the Complaint proceedings were being heard before the Authority, she did not come forward to take possession till the matter was resolved before the Authority.


# 26. We therefore, need to examine whether the delay in completion of the project is covered under the valid grounds such as lockdown variation, etc., and if so, how much of the delay can be attributed to Force Majeure factors, and for how much delay does the promoter have to pay interest towards delay compensation. We have also need to examine with reference to Extension of RERA Registration for the project from time-to-time and whether Extension of the RERA Registration would automatically mean if due date of completion also needs extended by virtue of the Extension of RERA Registration.


# 27. We have examined Clause-19 of the Construction Agreement regarding Force Majeure in this regard. We find that in Clause Force Majeure, nine circumstances for Force Majeure have been laid down. In the said Clause, not only Force Majeure condition laid down in explanation of Section 6 of the RERA were included, but also factors such as non-availability of building materials, Labour, delays in grant of NOC from various authorities, any change in rules and regulations by any Authority, Labour strike etc., and also any other eventuality which is beyond the reasonable control of the Developer.


# 28. The Explanation at Section-6 defines “Force Majeure to mean a case of war, flood, drought, fire, cyclone, earthquake or any other calamity caused by nature affecting the regular development of the real estate project.’ The Covid Pandemic, undoubtedly, falls under the definition of Force Majeure as described in Explanation above, but for some of the other factors illustrated in Section-10, such as non-availability of men and materials, or obtaining permission and approval etc. from competent authorities are something which are the direct responsibility of the Promoter and cannot, in our considered view, be included in the Force Majeure condition to escape liability for payment of delay compensation due to these factors. Merely the fact that the Allottee has signed the Construction Agreement and Sale Agreement which included this Clause does not mean that the entitlement of the Allottee for getting delay period interest for factors which are not genuinely Force Majeure will get adversely affected. It is the direct responsibility of the Promoter to ensure availability of men and material and to get the necessary permissions, approvals and certificates within the stipulated time and he cannot take shelter from including these factors in the Agreement to be valid grounds for denying the delay period interest to the Allottee.


# 29. Next main issue that we need to examine is whether Extension of RERA Registration would tantamount automatically to extension in the project completion date as per the Sale and Construction Agreement. We have examined the extensions granted by RERA to this project as per which first Extension was granted on 08.01.2021 for a period of 9 months until 30.09.2021 and the second Extension for Registration was granted on 05.10.2021 for further period of 12 months till 30.09.2022. Section 6 of the RERA Act is relevant provision regarding Extension of Registration which reads as under:

  • “6. The registration granted under section 5 may be extended by the Authority on an application made by the promoter due to Force Majeure, in such form and on payment of such fee as may be specified by regulations made by the Authority:

  • Provided that the Authority may in reasonable circumstances, without default on the part of the promoter, based on the facts of each case, and for reasons to be recorded in writing, extend the registration granted to a project for such time as it considers necessary, which shall, in aggregate, not exceed a period of one year:

  • Provided further that no application for extension of registration shall be rejected unless the applicant has been given an opportunity of being heard in the matter.

  • Explanation.— For the purpose of this section, the expression “Force Majeure” shall mean a case of war, flood, drought, fire, cyclone, earthquake or any other calamity caused by nature affecting the regular development of the real estate project.”


# 30. It is clear that Registration can be extended by the Authority due to Force Majeure based on the facts of each case and that reasons for the same should be recorded in writing. We find that no such reasons have been recorded while granting Extension. However, this is a lapse on the part of the Authority for which the Promoter not be held responsible.


# 31. However, we are of the considered view that Extension of RERA Registration of a project does not automatically mean that due date for completion are as per the signed Agreement also get extended. The Agreement for Sale and Construction Agreement are legally enforceable documents under Indian Contract Act, 1872 and the Promoters cannot unilaterally alter the due date for handing over unless both the parties agreed to change the due date of handing over possession. We are of the view that the Registration of project forms the core and substance of RERA Act, as it provides a framework for regulation. Registration process ensures that complete and accurate information is available to the buyers, thereby enhancing the transparency and credibility, and justice to both Promoter & Allottees. Registration of project reduces the risk of asymmetry of information between Seller and the Buyer and provides preventative, curable measures to all stakeholders. The mere fact that the Unit purchased by the Allottee is ready for possession does not imply that Registration of the project can be dispensed with since the promoter is required not only to complete the works pertaining to the purchased property but also to ensure that all external and internal development works in the entire project as described in Section 2(w) and 2(zb) of the RERA Act are fully completed. RERA Registration or extension of registration also allows Promoters to not only continue the development work but also to market & sell unsold units in the project which otherwise could become challenging without the assurance of a valid RERA Registration. Registration of the project establishes the legal framework which not only regulates future development but also extends its reach retroactively to projects which were not complete in all respects. While RERA Registration and its Extension allows the Promoter to continue to complete the development works and market/sale the unsold units, but it does not automatically modify date of possession which is a contractual obligation to which Promoters have to adhere to unless there are Force Majeure circumstance, and if developers failed to deliver possession at the contractual date, Allottees can approach the RERA for compensation or refund unless the Extension is on account of Force Majeure circumstance.


# 32. This brings us to the consideration of the subject as to the dates of lockdown on account of Covid Pandemic issued by RERA or any other Court of law from time-to-time. We have perused the Circular of RERA dated 04.04.2020, where in projects for which completion date expires on or after 15.03.2020, the period of validity of Registration of such projects may be extended by six months by invoking Force Majeure clause. Therefore, since this project was due for handover on 30.06.2020 which is during the Covid period, due date for completion gets extended by three months to 30.09.2020. Further extension for completion of RERA project was issued by RERA on 18.12.2020 in view of the prevailing Covid situation under which, the completion period was extended for a further period of three months. Therefore, completion period of this project on account of Force Majeure stands extended to 31.12.2020. RERA also issued another Notification dated 18.12.2020, as per which the due date of completion was extended for a further period of three months by invoking Force Majeure clause. Therefore, the due date of completion gets extended for a total period of 9 months till 31.03.2021.


# 33. The reason for extending the due date for completion from 31.06.2020, as agreed in the Construction Agreement, and not from 15.03.2020 being date of first RERA Circular as per which the validity of Registration was extended by invoking the Force Majeure clause due to Covid Pandemic, is that if the extended period permitted by the RERA Circular is computed from 15.03.2020, then the Promoter will get no additional time to complete the project on account of Covid, although the Covid Pandemic occurred during the agreed period allowed for completion of the project to the Promoter as per the Agreement. The Promoter hence is liable to pay interest to the Allottee as per RERA Act from 31.03.2021 till the date of issuance of Occupancy Certificate and intimation of the same to the Allottee for taking over possession.


# 34. It is admitted fact that the Occupancy Certificate was issued on 25.01.2023 and the Allottee was asked to come forward for inspection of the property on 29.06.2023. First inspection was conducted on 04.07.2023 in which several observations were made with regard to snags. The second inspection was undertaken on 02.12.2023 in which some of the unsolved problems were noted, after which the snags were rectified and it was noted on 06.02.2024 i.e. in the third inspection report, that all the repair works were completed to the satisfaction of the inspection team as well as the Allottee.


# 35. The report regarding Carpet area inspection was also submitted as per which the Carpet area is shown as 1232 sq.ft. as per the Agreement, but the actual measurement was found to be 1170.69 sq.ft., the difference being 61.31 sq.ft. We notice that in the order of the Authority, no direction has been given with regard to this issue and shortfall in the carpet area.


# 36. While it is admitted fact that Occupancy Certificate was given by BBMP on 25.01.2023 and the Promoter sent Email to Allottee to come for inspection on 29.06.2023 and communication was sent by the Promoter to the Allottee even after 06.02.2024, on 07.03.2024, 25.06.2024 & 26.06.2024 but the Allottee still raised some issues and did not take possession of the property. The Promoter has contended that once Occupancy Certificate is issued, though he is not liable to pay interest from the date he asked on 29.06.2023 to the Allottee to come for inspection and take possession. He is, however, agreeable to pay interest till 31.07.2023 after the first inspection report on 04.07.2023 when he claimed that he rectified the defects.


# 37. We are of the considered view that once Occupancy Certificate has been issued, and the intimation has been sent by the Promoter to the Allottee informing her about the same, it is the responsibility of the Allottee to take the possession and if the Allottee has any grievance with regard to defects etc. she can claim compensation for the defects but, cannot indefinitely delay in taking over possession for one reason or the other. An Allottee cannot refuse to take possession of a property solely on the grounds of snags or defects once the Occupancy Certificate has been issued. The Occupancy Certificate is considered as conclusive proof of project completion under RERA and while the Allottee is entitled to claim compensation for the defects or deficiencies but cannot claim interest for delay in handing over possession once the Occupancy Certificate is issued and intimation is sent to the Allottee to take over the possession.


# 38. In this case, however, since several defects which were pointed out in the First Inspection Report which were subsequently rectified to the satisfaction of the inspection team and the Allottee on 06.02.2024, we consider it acceptable to make an exception and held that the Promoter is liable to pay interest for the delay period from 31.03.2021 till 06.02.2024. With regard to the Carpet area, since no finding has been given by the Authority in its Order, the Allottee may approach the Authority for compensation in this regard if she wishes to do so.


# 39. We have considered Citations given by the Promoter regarding RERA Circulars for treating Force Majeure period as moratorium period for the purpose of calculating interest and the decision of the Hon’ble High Court of Bombay where it is laid down that the ‘moratorium period’ will have to be excluded while computing interest. We are of the view that the above Citations are relevant to the matter at hand.


# 40. With the above observations, we answer the point (i) & (ii) partly in the ‘affirmative’ and proceed to pass the following:


ORDER

  • 1) The Appeal is partly allowed;

  • 2) The impugned order dated 14.11.2024 passed by the 2nd Respondent-Karnataka Real Estate Regulatory Authority in Complaint No.CMP/220321/0009194 is hereby set aside;

  • 3) The Promoter is directed to pay interest on delay period on the amount paid by the Allottee of Rs.1,02,03,088/- at the rate of SBI MCLR plus 2% from 31.03.2021 till 06.02.2024.

  • 4) The Registry is directed to release the amount entitled to be paid to the Allottee as per Direction No.3, from out of the amount of Rs.36,20,769/- deposited by the Promoter, by issuing bankers cheque/DD in favour of the Respondent No.1-Allottee, after the expiry of the appeal period and by following the due procedure;

  • 5) The Registry is directed to release the remaining amount, if any, in favour of the Appellant-Promoter, by issuing the bankers cheque/DD in the name of the Appellant.

  • 6) The Promoter is directed to handover possession by way of execution of Sale Deed in favour of the Allottee with immediate effect on receipt of balance sale consideration;

  • 7) The Allottee is at liberty to file Complaint before the Authority with regard to the prayer for shortfall in the Carpet area and rental compensation;

  • 8) In view of disposal of the main appeal, pending I.As., if any, shall stand disposed of, as they do not survive for consideration;

  • 9) Registry is hereby directed to comply with the provision of Section 44(4) of the Act and to return the record to RERA, if received.


There is no order as to costs. 

------------------------------------------